Section
1 General requirements
1.1 General description
1.1.1 A elevating
wheel-house system generally consists of several concentrically mounted
slidable columns with the wheel-house fitted on the top of the innermost
column, see
Figure 13.1.1 General sketch elevating wheel-house.
The number of columns normally varies between 2 and 4. The columns
are usually square or rectangular. The wheel-house can be moved up
and down by means of one or more (hydraulic) lifting cylinder(s) to
reach the desired height. Another configuration may consist of a wheel-house
fitted on a scissor lift, see
Figure 13.1.2 Scissor lift, or may consist of a wheel-house suspended by hydraulic
jacks. This Chapter mainly deals with elevating wheel-house systems
of the type with the slidable columns. Other systems will be specially
considered.
Figure 13.1.1 General sketch elevating wheel-house
Figure 13.1.2 Scissor lift
1.1.2 The forces
between the columns are transferred by support/sliding blocks, here
after referred to as blocks.
1.1.3 The elevating
wheel-house columns may be integrated into the ship's structure as
follows:
-
The outer column
is fully integrated with the (flexible mounted) deck-house, see Figure 13.1.3 Wheel-house configuration 1. In this case one or more
pillars may need to be fitted underneath the outer column for additional
vertical support. In cases where the deck-house is flexibly mounted
on vibration mounts vibration mounts will also need to be fitted between
the column and the additional pillar(s).
-
The outer column
is integrated in the (flexibly mounted) deck-house and is continued
up to the bottom construction of the ship, see
Figure 13.1.4 Wheel-house configuration 2. In cases where the deck-house
is flexibly mounted on vibration mounts the outer column will need
to be mounted on vibration mounts in way of the bottom structure as
well.
-
The outer column
is independent of the flexibly mounted deck-house and directly fitted
onto the bottom construction of the ship, see
Figure 13.1.4 Wheel-house configuration 2. In this case the columns
are fully integrated with the ship's structure and it may be desired
to mount the wheel-house on vibration mounts at the connection with
the top of the innermost column in order to isolate it from vibrations
generated within the ship.
Figure 13.1.3 Wheel-house configuration 1
Figure 13.1.4 Wheel-house configuration 2
Figure 13.1.5 Wheel-house configuration 3
1.1.4 In the
case of the elevating wheel-house being arranged with columns (see
Figure 13.1.3 Wheel-house configuration 1), the bottom
structure of the wheel-house should consist of 4 main girders fitted
in line with the inner column plating and forming a cross of a pair
of beams. The ends of the girders in way of the wheelhouse external
walls can be considered as ‘free’ whilst the girders can
be considered as ‘clamped’ in way of the inner column
plating. The primary bottom structure should therefore be considered
as being built of eight girders clamped at one side (at the inner
column). See
Figure 13.1.6 Primary floor girders.
Figure 13.1.6 Primary floor girders
1.2 General requirements
1.2.2 The wheel-house
is to be capable of supporting its own weight, including all equipment,
and the maximum number of persons allowed in the wheel-house simultaneously.
A noticeplate in way of the entrance of the wheel-house should be
fitted stating the maximum number of persons allowed in the wheel-house.
The total mass corresponding with the number of people allowed should
also be indicated. These figures are to be designated by the manufacturer.
A minimum average weight of 75 kg per person is to be taken into account.
Further specific design loads are given in Table 13.1.1 Design loads on columns and
wheel-house and Table 13.1.2 Design loads on wheel-house floor
and roof.
Table 13.1.1 Design loads on columns and
wheel-house
Type load
|
Condition
|
Normal ( transverse
heeling)
|
Collision on the blow
|
Wind
|
p
w = 0,150 tonf/m2
|
p
w = 0,010 tonf/m2
|
Heel
|
10° static
|
—
|
Acceleration
|
—
|
0.5g
|
Table 13.1.2 Design loads on wheel-house floor
and roof
Item
|
Load (kN/m2)
|
Floor
|
p
floor = 3,18
|
Gallery or walkway
around wheel-house
|
p
walk = 2,12
|
Roof
|
p
roof = 1,0
|
1.2.3 The columns
are to be capable of withstanding loads induced by heeling or rolling
of the ship as well as loads induced by a collision.
1.2.4 The blocks
are to be capable of transferring the loads transferred by the columns.
1.2.5 The hydraulic
cylinder(s) is/are to be capable of supporting the wheel-house, the
number of columns connected, and the specified number of persons in
the wheelhouse, taking into account a dynamic factor of 1,20 on the
static load.
1.2.6 The hydraulic
cylinder(s) is/are to be of an approved type.
1.2.7 The cylinder
support constructed in the bottom of the outer column is to be capable
of withstanding the loads imposed by the hydraulic cylinder including
its own weight and the dynamic factor mentioned in Pt 3, Ch 13, 1.2 General requirements 1.2.5.
1.2.10 The
elevating wheel-house system is to be operated by the ship's crew
only after complete installation and appropriate instructions by the
manufacturer and final acceptance by Clasifications Register.
1.3 Design loads and columns forces
1.3.4 The column
forces are the reaction forces resulting from the following:
- Loads due to the static heeling (Zone 3) or dynamic rolling (Zones
1 and 2 ) of the ship.
- Loads induced by a collision.
- Wind loads.
The method of calculation of these forces on the blocks is given
in Table 13.1.4 Block force. Table 13.1.4 Block force is based on the assumption
that the longitudinal and transverse centre of gravity of the system
is approximately at the centre of the columns. If this is not the
case the effects are to be taken account of by further direct calculations.
Table 13.1.4 Block force
Load
|
Requirement
|
Design horizontal
load, F
|
|
Design bending
moment, M
|
|
Upper block force
R
upper, per block
|
|
Lower block force
R
lower, per block
|
|
Symbols
|
A
i
|
= |
projected area of part i of the elevating wheel-house
system, perpendicular to the wind direction, in m2
|
h
wi
|
= |
distance of the centre of area Ai up to
upper block, in metres |
m
i
|
= |
mass of part i of the elevating wheel-house system, in
ton |
h
mi
|
= |
distance of the centre of gravity of part i of the
elevating wheel-house system up to upper block, in metres |
n
|
= |
total number of parts of the elevating wheel-house
system, including the wheel-house, excluding the column of the
upper block under consideration and columns below, see also
Note 1 |
ζ |
= |
sin φ for heeled or rolling conditions; = 0,50
for collisions |
overlap
|
= |
distance between lower blocks of a column and the
upper blocks of the column below when the wheelhouse is in the
outmost lifted position, see also Note 2 |
|
Note
2. The required minimum overlap depends
on the allowable forces. The following values could be used as a
recommendation in the initial design stage: overlap ≈
1 x maximum width of outer column for services in Zone 3,
overlap ≈ 1,2 x maximum width of outer column for
services in Zone 2, and overlap ≈ 11/2 x maximum width
of outer column for services in Zone 1 for the determination of the
overlap between the outer column and the lowest middle column.
|
Figure 13.1.10 Overview support/sliding blocks
Figure 13.1.11 Mass forces
Figure 13.1.12 Wind forces
1.4 Structural requirements
1.4.1 Where
the outer column is integrated in the deckhouse (building methods
in accordance with Figure 13.1.3 Wheel-house configuration 1 and Figure 13.1.4 Wheel-house configuration 2) the upper blocks of the
outer column are to be in line with the topdeck of the deck-house.
Provisions are to be made for an efficient and adequate distribution
of loads into this deck. A buckling analysis of the topdeck plating
in way may be required. If necessary, anti-buckling strips are to
be fitted. Preferrably, the side plating of the outer column is to
be arranged in line with the beams and girders in the top and lower
deck of the deck-house. Where deck girders and beams are not in line,
brackets are to be fitted in line with the column side plating connecting
the outer column with the beams and girders in the deck-house.
1.4.2 Where
the outer column is independent from the flexibly mounted deck-house
and directly fitted on to the single or double bottom construction
of the ship, provision is to be made to support the outer column at
a distance as large as possible above the top of the bottom structure
but not less than 2,0 m. These supports, consisting of heavy beams
efficiently connected to the ship's supporting structure, are to be
provided in the horizontal transverse and longitudinal direction of
the ship in order to provide additional transverse and longitudinal
support. In this way the occurrence of high bending moments induced
by the outer column on the bottom structure is to be prevented.
1.4.3 The number,
type and position of vibration mounts or so called flexibles are dependent
on the type of mount, the weight of the elevating wheel-house, the
method of building in and the amount of weight of the deck-house that
is supported by the outer column. The vibration mounts should be of
an approved type and should be installed in accordance with the manufacturer's
recommendations.
1.4.4 If the
cylinder support in the bottom of the outer column consists of an I-shaped beam, anti tripping brackets are to be placed on the
beam in way of the cylinder. Tripping brackets are also to be placed
on the beam in line with the vibration mounts below.
1.5 Wheel-house
1.5.1 In this
Section, only requirements for the construction of the bottom structure
of the wheel-house are given. The construction of the side walls and
roof is to be carried out in accordance with good shipbuilding practice
in line with the Builder's procedures and standards.
1.5.2 The main
girders are defined as primary members. Other beams and stiffeners
are defined as secondary members.
1.5.3 The connection
of the main girders to the inner column is to be such that these can
be considered as clamped. Accordingly, the web of the main girder
is to be in line with the plating of the inner column. (Double) continuous
welding is required.
1.5.4 The effective
plate width of the attached cover plating on the bottom side of the
wheel-house foundation is to be determined in accordance withPt 3, Ch 3, 3 Structural idealisation, with the factor f to
be divided by 2. The effective width of a plate attached to the main
girder is then calculated as follows:
1.5.5 The number
of holes in the main girders is to be kept to a minimum. Holes are
not allowed in the main girder in way of the connection to the inner
column. Generally, a minimum of 1,50 times the web depth of the main
girder under consideration is required between the edge of a hole
and the inner column.
1.5.6 Openings
in beams are to have well rounded corners. The diameter or height
of any opening should not exceed half the depth of the web of the
beam. For rectangular openings, the length of the opening is limited
to 65 per cent of the web height. The distance between openings should
generally not exceed 75 per cent of the diameter or length of the
opening
1.5.7 Where
larger holes are proposed, these are subject to special consideration
and reinforcements by means of double plates or flanges having increased
properties are required to compensate the loss of material.
1.5.9 In case
of a gallery or walkway partly or totally being fitted around the
wheel-house, extra attention is to be paid to its supporting arrangement.
It is to be ensured that the beams are in line with local beams or
main girders fitted in the wheel-house and are well clamped without
the presence of any hard spots.
1.5.10 The
stresses in the main girders of the wheel-house foundation can be
calculated as stated in Table 13.1.5 Stresses in main girders of
wheel-house.
Table 13.1.5 Stresses in main girders of
wheel-house
Item
|
Parameter
|
Requirement
|
Bending Stress
|
σb
|
|
Shear stress
|
τ
|
|
Symbols
|
Z
|
= |
section modulus of main girder under consideration,
in cm3
|
AW
|
= |
web area of main girder under consideration, in
mm2
|
|
1.5.11 The
stresses in the other beams can be calculated as stated in Table 13.1.6 Stresses in secondary members of
wheel-house.
Table 13.1.6 Stresses in secondary members of
wheel-house
Item
|
Parameter
|
Requirement
|
Bending stress
|
σbl
|
|
Shear stress
|
τ
1
|
|
Symbols
|
φZ
|
= |
section modulus coefficient, to be taken as 0,1 for
secondary members where the end fixity of both ends is considered
to be partial; to be taken as 0,5 for cantilever beams (as for the
beam in the gallery) |
φA
|
= |
web area coefficient, to be taken as 0,5 for
secondary members where the end fixity of both ends is considered
to be partial; to be taken as 1 for cantilever beams (as for the
beam in the gallery) |
s
|
= |
stiffener spacing, in mm |
l
|
= |
length of stiffener, in metres |
Z
|
= |
section modulus of stiffener, in cm3
|
A
W
|
= |
web area of stiffener, in mm2
|
|
1.6 Columns
1.6.1 The thickness of the column plating is to be
determined for each column. Parameters are the reaction forces in the blocks and the
design bending moment in the columns. The thickness of the plating of the outer column
is to be equal to the thickness of the lowest middle column (or inner column in the case
of the total number of columns is 2). The minimum thickness, t
p is to be taken as the greater of t
p1 and t
p2:
 
where
t
p
|
= |
plating thickness of column under consideration, in mm, to be ≥ 8 mm
for steel plating and ≥ 8 mm for aluminium alloys |
k
|
= |
material factor
|
σ0
|
= |
yield stress of the used plating material or the 0,2 per cent proof
stress (in the welded condition), in N/mm2
|
fos
|
= |
factor of safety with respect to buckling aspects; to be taken as
1,2 for normal (rolling) conditions and 1,0 for collision condition |
f
block
|
= |
reaction force in upper block of the column below, in tonf, =
R
upper as calculated in accordance with Table 13.1.4 Block force and, if applicable, Table Table 13.1.7 Determination of transverse forces
of each individual componet of the elevating wheel-house system in Zones 1 and 2 , either in transverse or longitudinal
direction |
E
|
= |
modulus of elasticity of material, in N/mm2
|
b
c1
|
= |
breadth of column under consideration, in mm, measured in the
direction of F
block
|
b
c2
|
= |
breadth of column under consideration, in mm, measured perpendicular
to the direction of F
block
|
M
|
= |
design bending moment, in tonfm, as calculated in accordance. with
Table 13.1.4 Block force and, if applicable, Table 13.1.7 Determination of transverse forces
of each individual componet of the elevating wheel-house system in Zones 1 and 2
|
sf
|
= |
safety factor for axial stresses, see
Table 13.1.8 Safety factors on yield or 0,2 per
cent proof stress. |
Table 13.1.7 Determination of transverse forces
of each individual componet of the elevating wheel-house system in Zones 1 and 2
Item
|
Requirement
|
Wind pressure, p
w
|
0,038 tonf/m2
|
Roll period, T
r
|
to be taken as 6 if GM is unknown
|
Transverse component of static roll,
F
roll, static, i, of the part i of the elevating
wheel-house system, see also Note 1
|
ζ mi, tonf
|
Transverse component of dynamic
roll, F
roll, dyn, i, of the 0,07024 mi zi, tonf part i of the elevating
wheel-house system, see also Note 2
|
0,07024 mi
|
Symbols
|
m
I
|
= |
mass of the part i of the elevating wheel-house
system, in tonf |
z
I
|
= |
distance (perpendicular to deck) of centre of gravity
of the part i to ship's centre of gravity, metres |
φ
|
= |
max roll angle of the ship, in degrees, to be taken
as: For Zone 1 service: 20º if the actual heeling angle is unknown
For Zone 2 service: 15º if the actual heeling angle is unknown |
B
|
= |
breadth of ship, in metres |
GM
|
= |
metacentre height of ship, in metres |
|
Note
3. Due to the different ship's sailing
conditions, the rolling conditions may differ for each individual
sailing condition. Therefore the transverse forces on the columns are
at least to be calculated for the two main sailing conditions, i.e.
the full load condition and the ballast condition.
|
1.6.2 Where the proposed thickness is not in accordance to the required
thickness, a double plate may be fitted in line with the blocks to assure sufficient
strength against buckling. The double plate should be such that the least moment of
inertia of the two plates together,
l
comb, has a minimum value of:
taking into account an effective breadth of the column plating
itself equal to the value of b
c1.
1.6.3 Generally,
when a double plate is proposed, the dimensions b
x
t are to be as follows:
|
proposed columns
dimensions
|
proposed
columns dimensions
|
breadth
|
b
c
|
b = 0,3 x
b
c
|
thickness
|
t
p
|
t = t
p
|
1.6.4 In view
of potentionally high block forces the strength and means of attachment
of the column plating in way of the blocks is to be specially considered
and details of the blocks and plating in way are to be submitted for
consideration.
1.7 Service in Zones 1 and 2
1.7.2 The Builder
of the elevating wheel-house system is to be provided with proper
values of the hydrodynamic and hydrostatic parameters B, GM, and f.
1.8 Allowable stresses
1.8.1 The safety
factors listed in Table 13.1.8 Safety factors on yield or 0,2 per
cent proof stress are
the limiting stress coefficients to be multiplied with the yield stress
or the 0,2 per cent proof stress of the material as applicable. Thus
the allowable stress = safety factor x
σo
,
with σo
as defined in Pt 3, Ch 13, 1.6 Columns.
Table 13.1.8 Safety factors on yield or 0,2 per
cent proof stress
Type of stress
|
Condition
|
General Construction
|
Inland waterways-
Normal conditions (Zone 3)
|
Zone 1 and Zone 2
|
Collision
|
Bending + normal,
σ
x
|
0,60
|
0,75
|
0,90
|
Shear τ
|
0,42
|
0,53
|
0,64
|
Equivalent, σ
eq
|
0,75
|
0,85
|
1,0
|
Local stresses on safety pins, axles, brackets, etc.
|
Axial
|
0,50
|
0,63
|
0,75
|
Shear
|
0,35
|
0,44
|
0,53
|
Equivalent
|
0,63
|
0,71
|
0,83
|
Note The bending and normal stresses are known as axial
stresses.
|
1.8.2 In the
determination of the magnitude of the equivalent stress, σ
eq, it is assumed that the stresses are combined using the following
formula:
1.9 Welding requirements
1.9.1 (Double)
continuous welding is to be adopted in the following locations and
may be used elsewhere if desired:
-
Primary and secondary
members to plating in way of end connections.
-
Face flats to webs
of built-up/fabricated stiffening members in way of knees/end brackets.
-
The cylinder supporting
structure in the bottom of the outer column to the column plating.
-
The connection of
the main girders of the wheel-house foundation to the side plating
of the inner column.
-
Double plate on middle
column if needed to fulfill buckling requirements.
-
Double plate on cylinder
support if needed to fulfill shear strength requirements.
-
Anti-tripping brackets
where high local loadings are imposed.
1.9.2 The throat
thickness of the (double) continuous welds is to be 0,44 x
t
p, with t
p being the least
value of the plating thicknesses being joined. Full or deep penetration
welding may be required where high local loadings are imposed.
1.10 Non structurally related items
1.10.1 The
recommendations listed in this paragraph are non-Classification items
and may be overruled or waived by different or additional requirements
from the applicable National Authorities. It is however strongly recommended
to implement these recommendations.
1.10.2 It is
recommended to designate clearly and mark the area directly below
the wheel-house as an area of non trespassing.
1.10.4 External
stairs for access to the wheel-house are not a classification item.
It is however strongly recommended to indicate clearly the number
of persons that are allowed simultaneously on the stairs and for which
the stairs have been approved by the relevant authority.
|