Section
9 Ships for liquefied gases
9.1 General
9.1.2 Prior to the inspection of cargo tanks, surrounding spaces, associated
piping, fittings and equipment, etc. the respective items are to be cleaned and
thoroughly cleared of gas. Every precaution is to be taken to ensure safety during
inspection.
9.1.3 The following documentation, as applicable, is to be available on board the
ship:
-
Relevant instruction and information material such as cargo handling
plans, filling limit information, cooling down procedures, etc.
-
A copy of the Rules and Regulations for the Construction and Classification of Ships for the Carriage of Liquefied Gases in Bulk, July 2022.
-
Test records of secondary barrier.
-
Loading and stability information, including damage stability.
- A document specifying the maximum allowable loading limits for each
cargo tank and product, at each applicable loading temperature and maximum reference
temperature approved by the Administration. The pressures at which the pressure
relief valves (PRVs) have been set shall also be stated in the document.
- The cargo system operation manuals approved by the Administration.
9.2 Annual Surveys − Basic requirements
9.2.1 The
Annual Survey is preferably to be carried out during a loading or
discharging operation. Access to cargo tanks or inerted hold spaces,
necessitating gasfreeing/ aerating will normally not be necessary
unless required by the Regulations.
9.2.2 The
ship's log and operational records for the cargo containment system
covering the period from the previous survey are to be examined. Any
malfunction of the system entered in the log is to be investigated,
the cause ascertained, and that part of the system at fault is to
be found or placed in good order.
9.2.3 Instrumentation
and safety systems are to be surveyed as follows:
-
The instrumentation
of the cargo installations with regard to pressure, temperature and
liquid level is to be verified in good working order by one or more
of the following methods:
-
Visual external
examination.
-
Comparing
of read outs from different indicators.
-
Consideration
of read outs with regard to the actual cargo and/or actual conditions.
-
Examination
of maintenance records with reference to cargo plant instrumentation
maintenance manual.
-
Verification of
calibration status of the measuring instruments.
-
The low level,
high level, and overfill alarms are to be examined and tested to ascertain
that they are in working order.
-
The alarms associated
with the following are to be tested as applicable:
-
Cargo tank high
and low pressure.
-
Cargo tank
temperature.
-
Cargo hold
pressure.
-
Interbarrier
space pressure.
-
Inner hull temperature.
-
Secondary
barrier temperature.
-
Cargo Hold
or Interbarrier bilge level detection.
-
Control devices
for the cargo containment systems and cargo handling equipment, together
with any associated shutdown and/or interlock, are to be checked under
simulated working conditions and, if necessary, recalibrated. Such
safety systems include but are not limited to:
-
Cargo tank overfill
protection including cargo pump, compressor and other cargo machinery
automatic shutdown.
-
Cargo pump,
compressor and other cargo machinery shutdown on low cargo tank pressure
or cargo tank and interbarrier/hold space differential pressure.
-
Cargo pump
automatic shutdown on low level or current;
-
The emergency
shutdown system is to be tested, without flow in the pipe lines, to
verify that the system will cause the cargo pumps, compressors and
other cargo machinery, as applicable, to stop.
-
Consideration
will be given to the acceptance of simulated tests, provided that
they are carried out at the cargo temperature, or comprehensive maintenance
records, including details of tests held, in accordance with the cargo
plant instrumentation maintenance manual.
9.2.4 Cargo
gas leakage detection systems are to be examined and tested to ascertain
that they are in working order and calibrated using sample gas.
9.2.5 Inert
gas/dry air installations including the means for prevention of backflow
of cargo vapour to gas-safe spaces are to be verified as being in
satisfactory operating condition.
9.2.6 Ventilation
systems and air locks in working spaces are to be checked for satisfactory
operation.
9.2.7 Cargo
pipeline, valves and fittings are to be generally examined, with special
reference to expansion bellows, supports and vapour seals on insulated
pipes. It is to be verified that all accessible cargo piping systems
are electrically bonded to the hull.
9.2.8 Portable
and/or fixed drip trays, or insulation for deck protection in the
event of cargo leakage, are to be examined for condition.
9.2.9 The
means for accomplishing gas tightness of the wheelhouse doors and
windows is to be examined. All windows and side-scuttles within the
area required to be of the fixed type (non-opening) are to be examined
for gas tightness. The closing devices for all air intakes and openings
into accommodation spaces, service spaces, machinery spaces, control
stations and approved openings in superstructures and deckhouses facing
the cargo area or bow and stern loading/unloading arrangements are
to be examined. For ships carrying toxic gases such devices should
be capable of being operated from inside the space.
9.2.10 Venting
systems, including protection screens if provided, for the cargo tanks,
inter-barrier spaces and hold spaces are to be visually examined externally.
It is to be verified that the cargo tank relief valves are sealed
and that the certificate for the relief valves opening/closing pressures
is on board the ship.
9.2.11 Mechanical
ventilation fans in gas hazardous zones and spaces are to be visually
examined. Adequate spare parts should be carried for each type of
fan installed.
9.2.12 Electrical
equipment, cables and supports in gas hazardous zones and spaces shall
be examined as far as practicable. Alarms and safety systems associated
with pressurised lighting systems and any safety device associated
with nonsafe type electrical equipment that is protected by air-locks
are to be verified.
9.2.13 Heating
arrangements, if fitted, for cofferdams and other spaces shall be
verified in good working order.
9.2.14 All
accessible gas-tight bulkhead penetrations including gas-tight shaft
sealings are to be visually examined.
9.2.15 The
sealing arrangements for tanks or tank domes penetrating decks or
tank covers are to be externally examined.
9.2.16 The
survey is to consist of an examination for the purpose of ensuring,
as far as practicable, that the hull and piping are maintained in
a satisfactory condition.
-
The examination
of the hull and piping is to include the following:
- hull plating and closing appliances as far as can be seen
- watertight penetrations as far as practicable
- weather decks
- flame screens on vents to all bunker tanks
- bunker and vent piping systems
-
The examination
of the cargo pump rooms and compressor rooms and, as far as practicable,
pipe tunnels if fitted is to include the following:
- all pump room and compressor room bulkheads for signs of leakage
or fractures and, in particular, the sealing arrangements of all penetrations
of pump room and compressor room bulkheads
- condition of all piping systems (for cargo piping systems, see
Pt 1, Ch 3, 9.2 Annual Surveys − Basic requirements 9.2.7).
9.3 Annual Surveys − Reliquefaction/refrigeration equipment
9.3.1 Where
reliquefaction or refrigeration equipment for cargo temperature and
pressure control is fitted, the following are to be examined, so far
as practicable:
-
The machinery
under working conditions.
-
The shells of
all pressure vessels in the system, externally. Insulation need not
be removed for this examination, but any deterioration of insulation
or evidence of dampness which could lead to external corrosion of
the vessels or their connections, is to be investigated.
-
Primary refrigerant
gas and liquid pipes, cargo vapour and liquid condensate pipes and
condenser cooling water pipes. Insulation need not be removed, but
any deterioration or evidence of dampness is to be investigated.
-
The reliquefaction/refrigeration
plant spare gear.
9.3.2 Reference
should be made to the Special Survey requirements for guidance on
Continuous Survey arrangements.
9.4 Annual Surveys - Gas fuel burning equipment
and other equipment components
9.4.1 The following components are to be generally examined externally. If
insulation is fitted, this need not be removed, but any deterioration of insulation, or
evidence of dampness which could lead to external corrosion of the vessels or their
connections, is to be investigated:
-
Heat exchangers and pressure vessels for use with gas fuel burning in
boilers or machinery.
-
Cargo heaters, vaporisers, masthead heaters and other miscellaneous
pressure vessels.
9.4.2 Controls and interlocks are to be checked.
9.4.3 Alarm systems are to be checked to ascertain that they are in working
order.
9.4.4 Exhaust fans and/or pressurising system for gas trunking are to be
tested.
9.4.5 Ventilation systems are to be checked for satisfactory operation, if separate from the
cargo venting arrangements.
9.4.6 Fuel tanks and relief valves are to be externally examined, where applicable.
9.5 Annual Surveys − Cargo containment systems
9.5.1 Where
the insulation arrangement is such that the insulation cannot be examined,
the surrounding structures of wing tanks, double bottom tanks and
cofferdams are to be examined for cold spots, prior to the survey.
This examination is to be held at a convenient cargo discharge operation
with the cargo tanks loaded at approximately the minimum notation
temperature.
9.5.2 On application
by the Owner, consideration will be given to the cold spot examination,
where applicable, being carried out by the ship's staff.
9.5.3 When tests are required after repairs, independent cargo tanks, other than
independent tanks type C, are to be tested by hydraulic or hydropneumatic means as
appropriate. Test heads and pressures should be as defined in Part E - Tank Types of the Rules and Regulations for the
Construction and Classification of Ships for the Carriage of Liquefied Gases in
Bulk. Cargo tanks of the membrane or semi-membrane type are to be tested by means
of a detectable gas in the inter-barrier spaces and discolouring paint on the weld seams
of the cargo tanks wall, or other suitable means. Independent cargo tanks of type C are
to be tested hydraulically at 1,25 times the approved maximum vapour pressure.
9.5.4 For
membrane containment systems, the Surveyor is to receive confirmation
from the Master that the nitrogen control system for insulation and
inter-barrier spaces is operating normally.
9.6 Intermediate Surveys
9.6.1 The
Intermediate Survey intends to supplement the Annual Survey by testing
cargo handling installations with related automatic control, alarm
and safety systems for correct functioning. The Intermediate Survey
is preferably to be carried out with the ship in a gas-free condition.
The extent of the testing required for the Intermediate Survey will
normally be such that the survey cannot be carried out during a loading
or discharging operation.
9.6.2 In addition to the requirements for Annual Survey and the requirements of
Pt 1, Ch 3, 3.3 Intermediate Surveys 3.3.1 to Pt 1, Ch 3, 3.3 Intermediate Surveys 3.3.9, the following are to be dealt with as applicable:
-
Examination of
means for draining the vent piping system.
-
Verification that
pipelines and cargo tanks are electrically bonded to the hull.
-
Verification that
the heating arrangements, if any, for steel structures are satisfactory.
-
Where required
by the manufacturer's maintenance instructions, cargo tank and inter-barrier
space pressure and vacuum relief valve settings are to be checked
and adjusted as required. Cargo tank pressure relief valve harbour
settings are also to be checked, if applicable. Cargo tank pressure
relief valves are to lift at a pressure not more than the percentage
given below, above the maximum vapour pressure for which the tanks
have been approved.
- For 0 to 0,15 MPa, 10 per cent.
- For 0,15 to 0,3 MPa, 6 per cent.
- For pressures exceeding 0,3 MPa, 3 per cent.
- Valves may be removed from the tanks for the purpose of checking.
-
A General Examination
within the zones and spaces deemed as hazardous, such as cargo compressor
rooms and spaces adjacent to and zones above cargo areas, for defective
and non-certified safe-type electrical equipment, improperly installed,
defective and dead wiring. An electrical insulation resistance test
of the circuits terminating in, or passing through the hazardous zones
and spaces, is to be carried out. If the ship is not in a gas free
condition the results of previously recorded test readings may be
accepted.
9.6.3 For
ships over 5 years of age and up to 10 years of age, an overall survey
of representative ballast tanks is to be carried out. Where a hard
protective coating is found to be in POOR condition, as defined in Pt 1, Ch 3, 1.5 Definitions, where a soft or semi-hard coating
has been applied or where a protective coating was not applied from
the time of construction, the survey is to be extended to other ballast
tanks of the same type.
9.6.4 For
ships over 10 years of age, an overall survey of all ballast tanks
is to be carried out.
-
If such examinations
reveal no visible structural defects, the examination may be limited
to verification that the corrosion prevention system remains in GOOD
or FAIR condition.
-
The condition
of the corrosion prevention system identified during the Survey may
result in the tanks being subject to further examination at Annual
Surveys, in accordance with Pt 1, Ch 3, 2.2 Annual Surveys 2.2.32.
For independent double bottom ballast tanks, the examination at Annual
Surveys will be at the discretion of the Surveyor.
9.6.5 The
minimum requirements for Close-up Survey are given in Table 3.9.1 Ships for liquefied gases -
Intermediate Surveys.
Table 3.9.1 Ships for liquefied gases -
Intermediate Surveys
Ships between 10 and
15 years old
|
Ships greater than
15 years old
|
(1) Close-up survey of all web frames
and both transverse bulkheads in a representative ballast tank. See
Notes 1, 2, 3, 4, 5 and 6.
|
(1) Close-up survey of all web frames
and both transverse bulkheads in a two representative ballast tanks. See
Notes 1, 2, 3, 4, 5 and 6.
|
(2) Close-up survey of the upper part
of one web frame in one other representative ballast tank. See Notes
1, 2, 3, 4, 5 and 6.
|
|
(3) Close-up survey of one transverse
bulkhead in one other representative ballast tank. See Notes 1, 3,
4, 5 and 6.
|
|
Note
1. Ballast tanks include topside, double
hull side, double bottom, hopper side, or any combined arrangement of
the aforementioned, and peak tanks where fitted.
Note
2. Complete transverse web frame
including adjacent structural members.
Note
3. Transverse bulkhead complete,
including girder system and adjacent structural members and adjacent
longitudinal bulkhead structure.
Note
4. For areas in cargo tanks and
salt-water ballast tanks subject to Close-up Survey, the Close-up
Survey may be specially considered but not dispensed with in its
entirety, provided the Surveyor is satisfied with the Close-up Survey
that there is no structural diminution and the overall tank protective
coating remains in GOOD condition.
Note
5. The Surveyor may extend the Close-up
Survey, if deemed necessary, taking into account the maintenance of
the tanks under survey, the condition of the corrosion prevention
system, the structural arrangements or details which have suffered
defects in similar spaces or on similar ships and tanks having
structures approved with reduced scantlings.
Note
6. For ships having independent cargo
tanks of Type C, with a midship section similar to that of a general
cargo ship, the extent of Close-up Survey may be specially
considered.
|
9.7 Special Survey I (ships five years old) − General requirements
9.7.3 All
cargo tanks are to be examined internally, also externally so far
as practicable, particular attention being paid to the plating in
way of supports of securing arrangements, tower structures, seatings
and pipe connections, also to sealing arrangements in way of the deck
penetrations. Provided that the structural examination is satisfactory,
that the gas leakage monitoring systems have been found to be operating
satisfactorily and that the voyage records have not shown any abnormal
operation, cargo tanks do not require to be hydraulically tested.
The primary membranes of 'Gas Transport' design should be examined
with the primary insulation space under a vacuum of at least -500
mbar gauge. For 'Moss Type' LNG cargo tanks, the Structural Transition
Joints (STJ) are to be examined at the port, starboard, forward and
aft locations. Insulation is to be removed as required. Non-destructive
testing may be required where considered necessary. For membrane containment
systems with corrugated primary barriers, in view of the sloshing
loads experienced in service, measurements should, if required, be
taken inside the cargo tanks of deformations of the primary barrier
corrugations in order to assess the condition of the containment system
in accordance with the system designer’s procedures as approved
by LR.
9.7.4 The
non-destructive testing of cargo tanks is to be carried out as follows:
-
Non-destructive
testing is to supplement cargo tank inspection with special attention
to be given to the integrity of the main structural members, tank
shell and highly stressed parts, including welded connections as deemed
necessary by the Surveyor. The following items are, inter alia, considered
as highly stressed parts:
-
Cargo tanks
supports and anti-rolling/antipitching devices;
-
Web frames
or stiffening rings;
-
Swash bulkhead
boundaries;
-
Dome and stump
connections to tank shell;
-
Foundations
for pumps, towers, ladders, etc.;
-
Pipe connections.
-
For independent
tanks of Type B, the extent of non-destructive testing shall be as
given in the programme specially prepared for the cargo tank design.
-
Independent cargo
tanks of Type C are to be subjected to non-destructive testing of
the plating in way of supports and also at selected lengths of welds.
Where such testing raises doubt as to the structural integrity, a
hydraulic test should be carried out at 1,25 times the approved maximum
vapour pressure. Alternatively, consideration will be given to pneumatic
testing under special circumstances, provided full details are submitted
for approval.
-
At each alternate
Special Survey (i.e. SSII, SSIV and so on), all independent cargo
tanks of Type C are to be either:
-
Hydraulically
or hydro-pneumatically tested to 1,25 times MARVS, followed by non-destructive
testing in accordance with paragraph Pt 1, Ch 3, 9.7 Special Survey I (ships five years old) − General requirements 9.7.4 above, or,
-
Subjected
to a thorough, planned, non-destructive testing. This testing is to
be carried out in accordance with a programme specially prepared for
the tank design. If a special programme does not exist, the following
applies:
- cargo tank supports and anti-rolling/anti-pitching devices;
- stiffening rings;
- Y-connections between tank shell and a longitudinal bulkhead of
bi-lobe tanks;
- swash bulkhead boundaries;
- dome and sump connections to the tank shell;
- foundations for pumps, towers, ladders etc.;
- pipe connections.
At least 10 per cent of the length of the welded connections
in each of the above mentioned areas is to be tested. This testing
is to be carried out internally and externally as applicable. Insulation
is to be removed as necessary for the required non-destructive testing.
9.7.5 Deck
mounted cargo storage tanks are to be examined in the same manner
as main cargo tanks.
9.7.6 For
membrane containment systems, a tightness test of the primary and
secondary barrier shall be carried out in accordance with the system
designer's procedures and acceptance criteria as approved by LR. Low
differential pressure tests may be used for monitoring the cargo containment
system performance, but are not considered an acceptable test for
the tightness of the secondary barrier. For membrane containment systems
with glued secondary barriers, if the designer’s threshold values
are exceeded, an investigation is to be undertaken and additional
testing such as thermographic or acoustic emissions testing should
be carried out.
9.7.7 Where
a cargo tank or the hull structure is insulated and the insulation
is accessible, the insulation should be examined externally, together
with any vapour or protective barrier, and sections removed for examination,
if considered necessary by the Surveyor. Special attention should
be given to insulation in way of chocks, supports and keys. Portions
of the insulation are also to be removed, if required by the Surveyor,
to enable the condition of the plating to be ascertained. Where the
insulation is not accessible, see
Pt 1, Ch 3, 9.5 Annual Surveys − Cargo containment systems 9.5.1.
9.7.8 Cargo
tank internal pipes and fittings are to be examined, and all valves
and cocks in direct communication with the interiors of the tanks
are to be opened out for inspection and the connection pipes are to
be examined internally, so far as practicable.
9.7.9 Relief
valves are to be surveyed as follows:
-
The pressure relief
valves for the cargo tanks are to be opened for examination, adjusted,
function tested, and sealed. If the cargo tanks are equipped with
relief valves with non-metallic membranes in the main or pilot valves,
such non-metallic membranes are to be replaced.
-
Pressure relief
valves are subsequently to be adjusted to lift at a pressure in accordance
with Pt 1, Ch 3, 9.6 Intermediate Surveys 9.6.2.(d). Relief valve
harbour settings are to be checked, if applicable. Valves may be removed
from the shell for the purpose of making this adjustment under pressure
of air or other suitable gas.
-
Where a proper
record of continuous overhaul and retesting of individually identifiable
relief valves is maintained, consideration will be given to acceptance
on the basis of opening, internal examination, and testing of a representative
sampling of valves, including each size and type of liquefied gas
or vapour relief valve in use, provided there is logbook evidence
that the remaining valves have been overhauled and tested since crediting
of the previous Special Survey.
-
Relief valves
on cargo gas and liquid pipelines are to have their pressure settings
checked. The valves may be removed from the pipelines for this purpose.
At the Surveyor's discretion a sample of each size and type of valve
may be opened for examination and testing.
9.7.10 All
cargo pumps, cargo booster pumps and cargo vapour pumps are to be
opened out for examination. If requested by the Owner, these items
may be examined on a Continuous Survey basis, provided the interval
between examination of each item does not exceed five years. Pumping
systems for inter-barrier spaces are to be checked and verified to
be in good working order.
9.7.11 Piping
for cargo and process systems including valves, actuators and compensators
are to be opened for examination. Insulation may need to be removed,
as deemed necessary, to ascertain the condition of the piping. If
any doubt exists regarding the integrity of the piping based upon
visual examination then, where deemed necessary by the Surveyor, a
pressure test at 1,25 times MARVS for the pipeline is to be carried
out. The complete piping systems are to be tested for leaks after
re-assembly.
9.7.12 Equipment
for the production of inert gas is to be examined and shown to be
operating satisfactorily within the gas specification limits. Pipelines,
valves, etc. for the distribution of the inert gas are to be generally
examined. Pressure vessels for the storage of inert gas are to be
examined internally and externally and the securing arrangements are
to be specially examined. Pressure relief valves are to be demonstrated
to be in good working order. Liquid nitrogen storage vessels are to
be examined, so far as practicable, and all control equipment, alarms
and safety devices are to be verified as operational.
9.7.13 Gastight
bulkhead shaft seals are to be opened out so that the sealing arrangements
may be checked.
9.7.14 Sea
connections associated with the cargo handling equipment are to be
opened out when the ship is in dry-dock.
9.7.15 The
arrangements for discharging the cargo overboard in an emergency are
to be checked.
9.8 Special Survey I (ships five years old) − Reliquefaction/refrigeration
equipment
9.8.1 Each
reciprocating compressor is to be opened out. Cylinder bores, pistons,
piston rods, connecting rods, valves and seats, glands, relief devices,
suction filters and lubricating arrangements are to be examined. Crankshafts
are to be examined, but crankcase glands and the lower half of main
bearings need not be exposed if the Surveyor is satisfied with the
alignment and wear.
9.8.2 Where
other than reciprocating-type compressors are fitted, or where there
is a program of replacement instead of surveys on board, alternative
survey arrangements will be considered. Each case will be given individual
consideration.
9.8.3 The
water end covers of condensers are to be removed for examination of
the tubes, tubeplates and covers.
9.8.4 Refrigerant
condenser cooling water pumps, including standby pump(s) which may
be used on other services, are to be opened out for examination.
9.8.5 Where
a pressure vessel is insulated, sufficient insulation is to be removed,
especially in way of connections and supports, to enable the vessel's
condition to be ascertained.
9.8.6 Insulated
pipes are to have sufficient insulation removed to enable their condition
to be ascertained. Vapour seals are to be specially examined for their
condition.
9.8.7 The
Surveyor is to satisfy himself that all pressure relief valves and/or
safety discs throughout the system are in good order. No attempt,
however, is to be made to test primary refrigerant pressure relief
valves on board ship.
9.9 Special Survey I (ships five years old) -
Gas fuel burning equipment
9.9.1 Where gas fuel is used for main propulsion purposes, the associated
compressors and heat exchangers are to be opened out and examined as for
reliquefaction/refrigeration equipment. The glycol/water or steam side of the heaters is
to be hydraulically tested to 1,5 times the design pressure.
9.9.2 Gas fuel pipe trunks or casings are to be generally examined and the
exhaust or inerting arrangements for these trunks are to be verified.
9.9.3 All alarms associated with the gas fuel burning systems are to be
verified.
9.10 Special Survey II and Special Surveys thereafter (ships 10 years
old and over)
9.10.2 Water
cooled condensers in which the primary refrigerant is in contact with
the shell are to have the end covers removed and the shell pneumatically
tested to a pressure equal to the designed working pressure.
9.10.3 All other pressure vessels in the reliquefaction/refrigeration system, gas
fuel burning system and other handling systems are to be pneumatically tested to a
pressure equal to the designed working pressure.
9.11 Special Survey III and Special Surveys thereafter (ships 15 years
old and over)
9.11.2 For
independent tanks of Type B, the Owner is to submit proposals for
the extent of non-destructive testing of the cargo tanks well in advance
of the Special Survey.
9.12 Close-up Survey
9.12.2 The
Surveyor may extend the Close-up Survey, if deemed necessary, taking
into account the maintenance of the tanks under survey, the condition
of the corrosion prevention system and the structural arrangements
or details which have suffered defects in similar spaces or on similar
ships and tanks having structures approved with reduced scantlings.
9.12.3 For
areas in tanks where coatings are found to be in GOOD condition, as
defined in Pt 1, Ch 3, 1.5 Definitions, the extent of
Close-up Survey may be specially considered.
Table 3.9.2 Minimum requirements for Close-up
Survey - Ships for liquefied gases
Special Survey I (Ships 5 years old)
|
Special Survey II (Ships 10 years old)
|
Special Survey III (Ships 15 years old)
|
Special Survey IV (Ships 20 years old and
over)
|
(1) One web
frame in:
(a) a topside ballast tank
(b) a
hopper side ballast tank
(c) a double hull side ballast
tank
See Notes 1, 2, 5 and 6.
(2) One transverse bulkhead in a ballast tank. See
Notes 1, 3, 4, 5 and 6.
|
(1) All web
frames in either a topside ballast tank or a double hull side ballast tank.
If such tanks are not fitted, another ballast tank is to be selected.
See Notes 1, 2, 5 and 6.
(2) One web frame in each
remaining ballast tank. See Notes 1, 2, 5 and 6.
(3) One transverse bulkhead in each ballast tank. See Notes 1, 3,
5 and 6
|
(1) All web
frames in all ballast tanks. See Notes 1, 2, 5 and 6.
(2) All transverse bulkheads in all ballast tanks. See Notes 1,
3, 5 and 6.
|
(1) All web
frames in all ballast tanks. See Notes 1, 2, 5 and 6.
(2) All transverse bulkheads in all ballast tanks. See Notes 1,
3, 5 and 6.
|
Note
1. Ballast tanks include topside, double
hull side, double bottom, hopper side, or any combined arrangement of
the aforementioned, and peak tanks where fitted.
Note
2. Complete transverse web frame ring
including adjacent structural members.
Note
3. Transverse bulkhead complete,
including girder system and adjacent structural members and adjacent
longitudinal bulkhead structure.
Note
4. Transverse bulkhead lower part
including girder system and adjacent structural members.
Note
5. For ships having independent cargo
tanks of Type C, with a midship section similar to that of a general
cargo ship, the extent of Close-up Survey may be specially
considered.
Note
6. The Surveyor may extend the Close-up
Survey, if deemed necessary, taking into account the maintenance of
the tanks under survey, the condition of the corrosion prevention
system, the structural arrangements or details which have suffered
defects in similar spaces or on similar ships and tanks having
structures approved with reduced scantlings.
|
9.13 Thickness measurement
9.13.2 In
areas where substantial corrosion, as defined inPt 1, Ch 3, 1.5 Definitions, has been noted, then additional
measurements are to be carried out in accordance with Table 3.9.4 Thickness measurement - Ships for
liquefied gases - Structural areas with substantial corrosionto determine the full
extent of the corrosion pattern. The survey will not be considered
complete until these additional thickness measurements have been carried
out.
Table 3.9.3 Minimum requirements for
thickness measurement - Ships for liquefied gases
Special Survey I (Ships 5 years old)
|
Special Survey III (Ships 15 years old)
|
Special Survey IV and subsequent (Ships 20 years old
and over)
|
(1) 1
section of deck plating for the full beam of the ship within 0,5L
amidships in way of a ballast tank, if any.
(2) Measurements
for general assessment and recording of corrosion pattern of the
structural members subject to Close-up Survey in accordance with Table 3.9.2 Minimum requirements for Close-up
Survey - Ships for liquefied gases.
(3) Suspect
areas, as required by the Surveyor. See Note 5.
|
(1) Within the cargo area:
(a) Each deck plate
(b) 2 transverse
sections. See Notes 2, 3 and 4.
(2)
Measurements for general assessment and recording of corrosion pattern of
the structural members subject to Close-up Survey in accordance with
Table 3.9.2 Minimum requirements for Close-up
Survey - Ships for liquefied gases.
|
(1) Within the cargo area:
(a) Each deck plate.
(b) 3 transverse
sections. See Notes 2, 3 and 4.
(c) Each bottom
plate.
(d) Duct keel plating and internals.
(2) Measurements for general assessment and recording of
corrosion pattern of the structural members subject to Close-up Survey in
accordance with Table 3.9.2 Minimum requirements for Close-up
Survey - Ships for liquefied gases.
|
Special Survey II (Ships 10 years old)
|
(3) Selected wind and water strakes
outside the cargo area.
|
(3) All wind and water strakes over
the full length of the ship, port and starboard.
|
(1) Within
the cargo area:
(a) Each deck plate.
(b) 1
transverse section. See Notes 2, 3 and 4.
(2)
Measurements for general assessment and recording of corrosion pattern of
the structural members subject to close-up survey in accordance with
Table 3.9.2 Minimum requirements for Close-up
Survey - Ships for liquefied gases. See Note 1.
(3) Selected wind and water strakes outside the cargo
area.
(4) Where considered necessary by the Surveyor,
the inner bottom plating and adjacent tank supports are to be subject to
thickness measurement for general assessment and recording of the
corrosion pattern.
(5) For those ships designated to
carry light oils in the independent cargo tanks, thickness measurement of
the independent cargo tank structure is to be carried out as considered
necessary by the Surveyor.
(6) Suspect areas, as
required by the Surveyor. See Note 5.
|
(4) All
wind and water strakes within the cargo area.
(5) Where
considered necessary by the Surveyor, the inner bottom plating and
adjacent tank supports are to be subject to thickness measurement for
general assessment and recording of the corrosion pattern.
(6) For those ships designated to carry light oils in the
independent cargo tanks, thickness measurement of the independent cargo
tank structure is to be carried out as considered necessary by the
Surveyor.
(7) Suspect areas, as required by the
Surveyor. See Note 5.
|
(4)
Remaining exposed main deck plating not considered in item (1) and
representative exposed superstructure deck plating (i.e. poop, bridge and
forecastle deck).
(5) All keel plates outside the cargo tank
length. Also additional bottom plates in way of cofferdams, machinery
space and aft end of tanks.
(6) Plating of sea chests.
Also side shell plating in way of overboard discharges, as considered
necessary by the Surveyor.
(7) Where considered
necessary by the Surveyor, the inner bottom plating and adjacent tank
supports are to be subject to thickness measurement for general
assessment and recording of the corrosion pattern.
(8)
For those ships designated to carry light oils in the independent cargo
tanks, thickness measurement of the independent cargo tank structure is
to be carried out as considered necessary by the Surveyor.
(9) Suspect
areas, as required by the Surveyor. See Note 5.
|
Note
1. For areas in tanks where coatings are
found to be in GOOD condition, as defined in Pt 1, Ch 3, 1.5 Definitions, the extent of thickness measurements may be
specially considered, but not dispensed with in its entirety.
Note
2. Transverse sections should be chosen
where the largest reductions are likely to occur, or as revealed by
deck plating measurements.
Note
3. Where transverse sections are required
to be measured, at least one is to include a ballast tank within
0,5L amidships.
Note
4. A transverse section includes all
continuous longitudinal members such as plating, longitudinals and
girders at the deck, sides, bottom, inner bottom and longitudinal
bulkheads. For transversely framed vessels, a transverse section
includes adjacent frames and their end connections in way of
transverse sections
Note
5. Suspect areas are locations showing
substantial corrosion and/or are considered by the Surveyor to be
prone.
|
Table 3.9.4 Thickness measurement - Ships for
liquefied gases - Structural areas with substantial corrosion
Structural member
|
Extent of
measurement
|
Pattern of
measurement
|
Plating
|
Suspect area and adjacent plates
|
5 point pattern over 1 m2
of plating
|
Stiffeners
|
Suspect area
|
3 measurements each in line across web and
flange
|
|