PROCEDURE FOR NC SURVEYOR CERTIFICATION (NC SURVEYOR CERTIFICATIONS SCHEME)
General
Scope of application
This procedure defines the training and qualification requirements for New Construction (NC) Surveyors and Project Leaders involved in:• new construction surveys of ships and offshore floating units, for both seagoing and inland navigation activities; and• the survey of prefabrication components.The procedure also defines specific qualification requirements for Comfort and Habitability (COMF) and Underwater Radiated Noise (URN) activities.
Responsibility for implementation
The following functions are responsible, within their respective areas of responsibility, for implementing this procedure:
New Construction Management (DO_NCM)
Area and/or Country Marine Managers
NC Managers
Project Leaders
Surveyors
References
This procedure shall be read in conjunction with the following documents:
: ORGANISATION AND OPERATING OF MARINE & OFFSHORE DIVISION
: PERSONNEL MANAGEMENT
: QUALIFICATION, TRAINING and CERTIFICATION PROCESS
: APPOINTMENT OF NON-EXCLUSIVE SURVEYORS
: INTERNAL AND EXTERNAL AUDITS
: MONITORING OF QUALITY OF SERVICES
: MARINE AND OFFSHORE DIVISION MANAGEMENT REVIEW
: NEWBUILDING SURVEYS
PCI_0016: INLAND NEWBUILDING SURVEYS
Definitions
DO_NCM
New Constructions Management within Head Office’s Operations Management, with tasks defined in the related management procedure, Sec. 5, Par. 5.2.1.
NC Manager
Area or Country M&O Manager, or their delegate, responsible for New Construction services. General responsibilities for New Construction surveys are defined in the newbuilding surveys procedure. Other responsibilities and authorities are defined in accordance with the related management procedure.
Project Leader
A qualified NC surveyor responsible for coordinating the surveys of one or more ships or units in accordance with the newbuilding surveys procedure or PCI_0016.
Project Leader Delegate
A qualified NC surveyor designated to take over the Project Leader's responsibilities when the Project Leader is not available. The Project Leader Delegate has the same qualifications requirements, responsibilities and duties as the Project Leader.
Project Leader Delegate under supervision
A qualified NC surveyor having the level of technical qualification required for being nominated as Project Leader and having to demonstrate his/her capacity to manage, co-ordinate, supervise the tasks to be performed by the team (as per the applicable procedures). During one or more new construction projects he/she is supervised by Project Leader(s) assigned by the NC Manager holding valid Project Leader certification for that type of unit.
Surveyor
A qualified NC surveyor who participates in construction surveys under the supervision of a Project Leader. A Surveyor may work independently within the scope of activities for which they are qualified.
Trainer
A person designated by DO_NCM who has appropriate experience in the relevant activity or recognized expertise in a specialist field and is authorized to provide theoretical training. Training may be delivered through classroom sessions, seminars or individual training.
Tutor
A qualified NC surveyor designated by the Marine Manager or NC Manager who has appropriate experience and competence in the relevant activity and is responsible for supervising the practical training of a Trainee.
Trainee
A newly appointed NC surveyor or an already qualified NC surveyor seeking an additional or upgraded qualification and undergoing theoretical and/or practical training.
Non-exclusive and exclusive surveyor
As defined in IACS PR5, a Non-Exclusive Surveyor performs work on behalf of the Society but may also work for another organization. An Exclusive Surveyor performs work exclusively on behalf of the Society. (the related management procedure)
Subject Matter Expert
As defined in IACS PR7, a specialist providing assistance or technical advice in classification or statutory activities. The NC Surveyor remains responsible for the work performed with SME support and for the technical content of the service.
training and qualification for surveyors
General requirements
Surveyors shall meet the formal education requirements defined in the personnel management procedure, Annex A1.
Annex A1.1 of this procedure defines the Surveyor status required for each type of survey.
Status 1: Non-Exclusive surveyor
Status 2: Exclusive surveyor
All theoretical and practical training required for qualification shall be documented. Training records shall be completed by the Trainee and validated by the Trainer or Tutor.
Theoretical training
Theoretical Training may be completed through:
classroom training
dedicated seminars
self-study
computer-assisted training (My Learning)
individual training
Knowledge acquired through theoretical training shall be assessed by a written or oral examination or by an appropriate computer-based test.The Trainee may use relevant working documents during the examination, including Rules, Conventions, procedures and checklists.
To successfully complete a theoretical training module, the Trainee shall achieve:
at least 50% for each sub-module
at least 70% overall for the complete module
Where a Trainee fails one or more modules, only the failed module(s) need to be repeated.The period between completion of theoretical training and the certification shall not exceed three years. If more than three years have elapsed, refresher training and/or a new examination shall be completed before certification is granted.
Practical training
Practical training shall be performed under the supervision of a Tutor who holds at least an Advanced qualification for the activity concerned. A Surveyor holding only a Basic qualification shall not act as Tutor for that activity.
The practical training requirements for each qualification are defined in the applicable Practical Training Record attached to this procedure.
The completed Practical Training Record shall demonstrate that:
the required minimum number of tutored surveys has been completed; and
all key survey activities identified in the Practical Training Record have been covered.
During practical training, the Trainee shall demonstrate an adequate level of technical knowledge and practical competence. The Tutor may ask technical questions or request additional demonstrations where necessary to assess the Trainee's understanding.The Tutor shall document the assessment and final evaluation in the applicable Practical Training Record.
Basic qualification
Basic qualification applies to:
newly appointed surveyors joining the Society; and
Surveyors already qualified in another activity of the Society who are seeking an NC Surveyor qualification.
Basic theoretical training shall be completed by self-study in accordance with the applicable Theoretical Training Matrix attached to this procedure.
Modules already successfully completed for another qualification (Ships in Service or Equipment and Material Certification) do not need to be repeated where the corresponding equivalence applies.Basic qualification covers:
Steel 1: Hull surveys, including statutory items covered by Recognised Organisation (RO) Class Rules;
Machinery System: including statutory items covered by Recognised Organisation (RO) Class Rules; and
Electrical Cable and Equipment Fitting: including statutory items covered by Recognised Organisation (RO) Class Rules.
The corresponding practical training shall be completed and documented using the applicable Practical Training Record.
Newly hired Surveyors, not granted any reduced training program (see 2.5) shall complete a minimum of three months of Basic theoretical and practical training.
Advanced qualification
Advanced qualification applies to Surveyors extending their scope of qualification.The required theoretical training for each Advanced qualification is defined in the applicable Theoretical Training Matrix attached to this procedure.
The Surveyor shall:
successfully complete the required theoretical modules; and
complete the corresponding practical training using the applicable Practical Training Record.
As an exception, Polar Code qualification does not require practical training.COMF and URN qualifications are managed separately from the standard NC Surveyor qualification grid and are therefore addressed in Section 2.10
Prerequisites for Surveyor qualification
To apply for the certification as surveyor for below categories, following pre-requisites need to be obtained before application:
| Requested certification | Required certification 1 | Required certification 2 | Required certification 3 |
|---|---|---|---|
| Offshore Steel | Steel 2 | ||
| Electrical Propulsion | Diesel Propulsion | Electrical Installations | |
| Offshore Machinery and Electricity | Diesel Propulsion | Electrical Installations | |
| AUT (Automation) | Electrical Installations | ||
| Dynapos (Dynamic Positioning) | AUT | ||
| SOLAS | Hazardous Areas training performed | ||
| Offshore MODU | Load Lines | SOLAS | MARPOL |
| Polar Code | SOLAS | MARPOL | |
| IGF and Alternative Fuels | Diesel Propulsion | ||
| PSSC (Passenger Safety) | SOLAS | ||
| SPS (special Purpose Vessels) | SOLAS |
Requested certification | Required certification |
| Diesel Propulsion | Machinery System |
| Electrical Installations | Electrical cable and equipment fitting |
| Gas Fuel | Diesel Propulsion |
Equivalent training and reduced training plan
DO_NCM may approve a reduced training plan for a Surveyor who:
acquired relevant qualifications through professional experience before joining the Society; or
can demonstrate previous training and experience equivalent to the requirements of this certification scheme
DO_NCM shall determine the extent of the reduced training on a case-by-case basis after reviewing the supporting evidence.
Reduced training for Basic qualifications
This provision applies to:
Steel 1
Machinery System
Electrical cable and equipment fitting
The following requirements apply:
The Surveyor shall complete the full Basic theoretical training and examination.
The Surveyor shall complete the REDUCED applicable practical training Record
Reduced training for Advanced qualifications
This provision applies to:
Assembly Material; and
Machinery & Electricity & Automation
The Surveyor shall:
complete the required self-study and pass the theoretical examination;
complete the applicable REDUCED Practical Training Record;
create the corresponding survey report in VPM for each survey recorded in the Practical Training Record and have it validated by the Tutor
Qualifications not eligible for reduced training
Reduced training shall not be accepted for Offshore and Statutory qualifications.
Equivalence with Ships in Service qualifications
Equivalence for Class surveys
See 2.5.1 and 2.5.2
Equivalence for Statutory surveys
Except for passenger ships, Surveyors already qualified for Ships in Service activities and holding initial statutory survey qualifications are considered qualified to perform the corresponding initial statutory surveys in New Construction.For SOLAS qualification, the additional Safety Construction module shall nevertheless be completed followed by successful completion of the corresponding examination.
Requests to transfer an Inland Navigation qualification to a Seagoing qualification shall also be assessed under the equivalence provisions of this section.
Maintenance of knowledge and Seminar Rolling out
DO_NCM shall organize an annual NC seminar. Attendance is mandatory for NC Managers and/or their Delegates.The seminar shall provide updates on:
Rules and Regulations;
relevant technical subjects; and
new developments affecting NC activities.
The content of the annual seminar shall subsequently be rolled out to all NC Surveyors within the period defined by DO_NCM.
The NC Manager shall ensure that the required rolling-out training is organized for the Surveyors under their responsibility.Training may be delivered through:
e-learning modules provided by DO_NCM through the Marine and Offshore Qualification website; and/or
local training sessions organized by the NC Manager.
Where DO_NCM identifies a module as requiring a mandatory classroom training session, that session shall be completed and recorded in the Marine and Offshore Qualification website.Completion of the required rolling-out shall be monitored through the Marine and Offshore Qualification website.A Surveyor's certification may be suspended if the required rolling-out is not completed within the period specified by DO_NCM.
Activity monitoring
The validity of an NC Surveyor certification shall be maintained through Activity Monitoring, performed to verify the Surveyor's ability to apply the applicable methods, procedures, Rules and Regulations in practice.
Activity Monitoring shall be performed at least every other calendar year, and will have a duration of at least 1/2 day.
The monitoring shall include, as applicable:
witnessing the Surveyor during survey activities;
evaluation of the Surveyor's technical competence and application of procedures;
review of the relevant survey records and documentation (validation of the survey record in VPM by the monitor)
assessment of the effectiveness of training completed since the previous monitoring; and
identification of any additional training needs (related to the monitored survey).
The monitoring may cover one or more surveys and should, where applicable, include activities related to advanced or statutory qualifications held by the Surveyor.
The Monitor shall be one of the following:
a Surveyor holding at least an equivalent level of qualification for the activity being monitored;
the NC Manager or Delegate, provided they are qualified for the activity concerned; or
DO_NCM, its Delegate or another person designated by DO_NCM and qualified for the activity concerned.
Surveyors holding both New Construction and Ships in Service qualifications may, subject to approval by DO_NCM, use a Ships in Service Activity Monitoring in lieu of 1 New Construction monitoring cycle. For the following monitoring cycle, a new construction survey needs mandatory to be the subject of monitoring.
A monitoring performed for seagoing activities is also valid for inland.
Failure to complete the required Activity Monitoring within the prescribed period may result in suspension of the Surveyor certification until a satisfactory monitoring has been completed.
Reactivation of an archived Surveyor qualification
To restore an archived Surveyor certification, the following actions shall be completed:
Surveyor responsibilities:
complete the annual seminar applicable to the year of re-activation
NC Manager (or delegate) responsibilities:
perform and document a Surveyor Activity Monitoring on a survey within the scope of the certification being re-activated
Following satisfactory completion of the above requirements, DO_NCM shall reinstate the archived certification.
Complex conversion projects
Ships in Service Surveyors assigned to complex conversion projects, as defined in the occasional and miscellaneous surveys procedure, shall obtain the applicable NC qualification.
Depending on the type of ship or project, the Surveyor shall hold the applicable Ships in Service qualifications defined in the ships-in-service personnel qualification and certification scheme, including:
Hull and Structural Renewal, with dry-docking and repair experience;
Machinery Renewal, with dry-docking and repair experience;
SOLAS, Load Lines and MARPOL, with dry-docking and repair experience; and
for Offshore projects, Hull and Structural Renewal Offshore and MODU, with dry-docking and repair experience.
In addition, the Surveyor shall complete through RTC or classroom training, as applicable:
Project Leader training;
VPM training,
DO_NCM may grant an equivalent qualification on a case-by-case basis.
Where an equivalent qualification is granted through this route, it shall be restricted to"complex conversion projects only" and shall not authorize the Surveyor to perform other NC projects outside that scope.
Specific qualifications for Comfort and Habitability (Noise and Vibration), and Underwater Radiated Noise (URN)
General
Qualifications for Comfort and Habitability (COMF) and Underwater Radiated Noise (URN) are managed separately from the standard NC Surveyor qualification grid.The COMF and URN qualification grid is attached to the Survey at Yard qualification grid in the Qualif Tool, under Noise and Vibration measurements.Both COMF and URN qualifications are structured into three competency levels:
Basic
Intermediate
Advanced
Each level has specific prerequisites, training requirements and authorized activities.
Basic Level
The Surveyor shall complete theoretical training provided by a Head Office-appointed Trainer. No practical training is required.
Once qualified at Basic level, the Surveyor is authorized to witness measurements performed by an external specialist company and verify that the measurements are carried out in accordance with the applicable reference documents.
Intermediate Level
The Surveyor shall hold a valid Basic-level qualification and shall complete theoretical and practical training provided by a Head Office-appointed Trainer. The practical training shall be performed under the supervision of the appointed trainer.
Once qualified at Intermediate level, the Surveyor is authorized to review the measurement procedure and measurement report against the applicable reference documents.
This qualification applies to all ships except Ro-Pax and Passenger vessels.
Advanced Level
The Surveyor shall hold a valid Intermediate-level qualification and shall complete the theoretical and practical training provided by a Head Office-appointed Trainer.The practical training shall be performed under the supervision of the appointed trainer.
Once qualified at Advanced level, the Surveyor is authorized to review the measurement procedure and measurement report for Ro-Pax and Passenger vessels against the applicable reference documents.
Activity Monitoring
Surveyors holding Comfort and Habitability (COMF) and/or Underwater Radiated Noise (URN) qualifications shall undergo Activity Monitoring every other calendar year in accordance with the above requirements and the additional provisions defined below.
If the surveyor has been trained and obtained a higher level of qualification in the period that is covered by the monitoring, then this training will cover the requested monitoring.
The required Monitor depends on the qualification level and whether the monitoring is the first monitoring following qualification or a subsequent monitoring.
| Activity monitoring to be performed for | Monitor for first Activity Monitoring after qualification | Following Activity Monitoring |
| Basic | SAY qualified for Intermediate level or SME (Subject Matter Expert) | another SAY qualified for the same level of competency or higher (or SME) |
| Intermediate | SAY qualified for Advanced level, another SAY qualified for Intermediate level who performed the 1st monitoring or SME | |
| Advanced | SME or another SAY qualified for Advanced level who performed the 1st monitoring |
Subject Matter expert
The Society may recognize the accreditation, certification, professional recognition, or demonstrated experience of an expert or specialist to support or advise surveyors in specific technical fields.
Fields of Service
The following specialist disciplines may be recognised:
Welding Engineer or Welding inspector
NDT Engineer or NDT Operator
LNG Cargo Containment Installation Inspector
Electrical Engineer specialized in Hazardous Areas (ATEX / IECEx)
Diving System Specialist
Specialist in Advanced Wood Assembly materials
Specialist in Comfort and Habitability Measurements
Specialist in Underwater Radiated Noise (URN) Measurements
Cyber Security Specialist
Application requirements
The following documentation shall be submitted to DO_NCM for review:
Curriculum Vitae
Record of training and relevant experience
Evidence of qualification to a recognized national, international or industry standard, where applicable
General requirements
In accordance with IACS PR.7, a Subject Matter Expert is considered support personnel and is therefore not subject to the surveyor qualification requirements defined in this procedure.
Training requirements
Before performing services on behalf of the Society, the Subject Matter Expert shall complete the following training:
HSE Induction Training modules
Code of Ethics training
If the expert belongs to another division of the society, above training does not need to be repeated.
Supervision
A Subject Matter Expert shall work under the supervision of a certified surveyor.The supervising surveyor remains fully responsible for all class and statutory matters associated with the service being performed by the Subject Matter Expert
training and qualification requirements for project leaders
General requirements
A Project Leader shall first be a qualified NC Surveyor with an exclusive status and meet the applicable Surveyor qualification requirements defined in Section 2.
| Project Leader certification | Required Material certification | Required Statutory certification | Other required certification |
|---|---|---|---|
| Passenger ship, Ro-ro Pax | Steel 2 | PSSC | |
| HSC | Aluminium | HSC | |
| GAS Tanker | Steel 2 | IGC | |
| Chemical Tanker | Steel 2 | IBC code | |
| Other ship L> 65m | Steel 2 | SOLAS / Load Lines / Marpol | |
| Other ship L< 65m | Applicable material | ||
| Offshore floating unit | Offshore Steel | MODU | Offshore Machinery and Electricity |
Initial Theoretical Project Leader Training
For initial Project Leader qualification, the applicant shall successfully complete the Initial Project Leader theoretical training.
Project Leader Delegate under Supervision - Practical training
As part of the qualification process, the applicant shall be assigned in VPM as a Project Leader Delegate under Supervision (PLDUS).
The PLDUS shall perform Project Leader activities under the supervision of one or more Project Leaders assigned by the NC Manager.
A Project Leader shall demonstrate the ability to:
manage the survey team
coordinate survey activities
supervise the work of the attending Surveyors
apply the relevant NC procedures
use VPM appropriately
maintain the required records and traceability throughout the project
demonstrate an appropriate understanding of applicable Flag requirements, Rules and Regulations.
The required experience may be gained during one or more NC projects, provided that all mandatory activities and milestones are completed under appropriate supervision. The supervising Project Leader(s) shall maintain evidence of the supervision performed and may be combined in 1 Record of Supervision.
At the end of the supervised period, a Record of Supervision shall be issued by the supervising Project Leader(s). It shall identify the activities and construction milestones completed by the applicant and include an evaluation of the applicant's performance. The PLDUS Record of Supervision is attached to this procedure.
As a minimum, the applicant shall perform and document Project Leader activities associated with the following milestones under supervision:
signature of contract
Kick-Off meeting, including the associated main Project Leader tasks (review of ITP, NDT, Tank testing,...)
use of VPM related to the management of the project
quality meetings with the shipyard
ship delivery (NRS and NPSS), including issuance of certificates and records
Extension of Project Leader qualification to an additional ship type
A qualified Project Leader seeking qualification for an additional ship type shall first hold or obtain the technical qualifications specified in Table 4.
The Project Leader shall then complete the Project Leader-specific supervised activities needed to demonstrate competence for the new ship type, covering the full construction stage from contract till delivery.
The completed activities shall be documented in the applicable PLDUS Record of Supervision.
Activity Monitoring
The validity of a Project Leader certification shall be maintained through Activity Monitoring.
Activity Monitoring shall be performed at least once every five years, following completion of a New Construction project for which the individual has acted as Project Leader throughout the construction cycle.
The Monitor shall be appointed by the NC Manager and shall be:
a Project Leader not assigned to the monitored project and qualified for the relevant ship or unit type;
a Project Leader not assigned to the monitored project, assisted by a Subject Matter Expert where necessary; or
DO_NCM, its Delegate or any person designated by DO_NCM and qualified for the activity concerned.
Before validation of the Activity Monitoring, completion of the applicable Project Leader training requirements shall be verified.
Where completion of a full construction cycle is not possible, DO_NCM may, on an exceptional basis, authorize completion of the Project Leader training in lieu of Activity Monitoring to maintain certification validity.
Re-activation of a Project Leader certification
An archived Project Leader certification may be reinstated by DO_NCM upon request.Following re-activation:
The Project Leader shall be assigned a designated tutor, who shall be a certified Project Leader in the relevant discipline.
The tutor shall support and monitor the Project Leader throughout the first project performed after certification reinstatement.
Where the re-activation occurs more than five years after the certification became inactive, the Project Leader shall complete the Project Leader Training. This training replaces the Project Leader Activity Monitoring requirement.
Increased Monitoring
The Increased Monitoring status may be activated by the HO Manager in the Marine Surveyor Qualification database to ensure enhanced oversight of a surveyor’s performance.
This status may be requested by the NC Manager following unacceptable or unsatisfactory performance as a Project Leader and/or Surveyor. It may also be activated directly by the HO Manager based on findings identified through random reviews of tools and records.
The responsible NC Manager shall ensure that evidence of the required corrective actions is uploaded to the Marine Surveyor Qualification database.
Once all corrective actions have been satisfactorily completed and verified with DO_NCM, the HO Manager shall remove the Increased Monitoring status.
Appendix — LEVEL OF QUALIFICATION REQUIRED
Surveyor’s status:
| Types of Surveys - SEAGOING | Status of surveyor | ||
|---|---|---|---|
| STEEL ASSEMBLY (HULL & PIPING) | Steel 1 | 1 or 2 | |
| MACHINERY | Machinery system | 1 or 2 | |
| Electrical cable and equipment fitting | 1 or 2 | ||
| ASSEMBLY MATERIAL (HULL & PIPING) ADVANCED | Steel 2 | 1 or 2 | |
| Offshore Steel | 2 | ||
| Aluminium | 1 or 2 | ||
| Composite | 1 or 2 | ||
| Wood | 1 or 2 | ||
| MACHINERY & ELECTRICITY & AUT ADVANCED | Diesel Propulsion | 1 or 2 | |
| Steam propulsion | 2 | ||
| Electrical propulsion | 2 | ||
| Gas turbine | 2 | ||
| Offshore | 2 | ||
| Electrical installation | 1 or 2 | ||
| AUT | 2 | ||
| Dynapos | 2 | ||
| STATUTORY | Load Line | 2 | |
Solas | 2 | ||
Marpol | 2 | ||
| Hazardous areas - explosion proof equipment | 2 | ||
| Ballast Water Management | 2 | ||
| Offshore MODU | 2 | ||
| Polar Code | 2 | ||
| IHM | 2 | ||
| IGC - Gas Carriers | 2 | ||
| IGF and Alternative Fuels | 2 | ||
GAS - Membrane Tanks | 2 | ||
GAS - Independent Tanks | 2 | ||
| HSC code | 2 | ||
| Passenger safety | 2 | ||
| SPS vessels | 2 | ||
| PSPC | 2 | ||
| OTHER | Cyber Security | 2 | |
| Diving | 2 | ||
| Technical | Level | Status of Surveyor |
|---|---|---|
| Comfort and Habitability | Initial | 2 |
| Basic | 2 | |
| Advanced | 2 | |
| URN | 2 | |
| Types of Surveys - INLAND | Status of surveyor | ||
|---|---|---|---|
| CLASS | ASSEMBLY (HULL & PIPING)MACHINERY | Steel | 1 or 2 |
| Aluminium | 1 or 2 | ||
| Composite | 1 or 2 | ||
| MACHINERY | Machinery System and Electrical cable and equipment fitting | 1 or 2 | |
| Diesel propulsion | 1 or 2 | ||
| Electrical propulsion | 1 or 2 | ||
| Gas-Fuel | 2 | ||
| Electrical Installation | 1 or 2 | ||
| AUT | 2 | ||
| STATUTORY | ADN Surveys | Transport of dangerous goods EC Directive 2008/68 | 2 |
| EC Directive 2006/87 / EC Directive 2016/1629 | EC Directive 2006/87 / EC Directive 2016/1629 | 2 | |
| RR | Gas turbine | 2 | |
| LL | Load Line | 2 | |
| Normam02 | Normam02 | 2 | |
Status of the surveyor:
1 = non-exclusive (for non-convention ships only)2 = exclusive
Untitled
Extent of Competency of Surveyor Certification :
| Type | Extent of Competency of Surveyor Certification |
|---|---|
| Steel 1 | Covers all types of hull surveys on steel ships as listed in Rule Note NR 540 – Kick-off Meeting Templates for Newbuilding Table 2 (including statutory items covered by Recognised Organisation (RO) Classification rules) |
| Machinery system | Covers all types of machinery surveys (including statutory items covered by Recognised Organisation (RO) Classification rules) except main engine & generators installation and trials, shaft, alignment and steering gear tests. |
| Electrical cable and equipment fitting | Covers electrical cable installation and equipment fitting surveys including insulation tests. |
| Steel 2 | Covers all types of hull surveys on steel ships as required by rules and regulations including inclining test, welding procedures qualification tests and welders certification review of test reports and issuance of certificate. |
| Dual Fuel | For Dual Fuel ships, in addition to the “Diesel Propulsion” certification, the “IGF and Alternative Fuel” certification as “Membrane Tanks” or “Independent Tanks” certification (relevant to the project) needs to be covered by the surveyor Team. |
| IGF and Alternative Fuels | Covers all Fuel types and related alternative designs covered by the IGF code. |
| Other advanced types of surveys | Cover all surveys required by rules and regulations of the corresponding advanced certification. |
| Steel (Inland) | Covers Steel 1 and 2 as mentioned above |
Untitled
Extent of Competency of Project Leader Certification
| Type | Extend of Competency of Project Leader |
|---|---|
| Passenger ship, Ro-ro Pax | Covers other ships with L<>65m, Passenger ships and Ro-ro Pax |
| HSC | Covers other ships with L<>65m and HSC |
| GAS tanker | Covers other ships with L<>65m and all Gas tanker types |
| Chemical tanker | Covers other ships with L <>65m and Chemical tankers |
| Other ship L> 65 m (seagoing) | Covers all types of ships except Passenger ships, Ro-ro Pax, HSC, LNG, LPG, chemical tankers, Offshore floating units |
| Other ship L< 65 m (seagoing) | Covers all types of ships L < 65 m except Passenger ships, Ro-ro Pax, HSC, LNG, LPG, chemical tankers, offshore floating units |
| Offshore floating unit | Covers offshore floating unit only |