NEWBUILDING SURVEYS

Revision of 1 November 2026

GENERAL

Scope of application

This procedure applies to the New Construction of seagoing ships and offshore floating units, the major conversion of seagoing ships and offshore floating units for the new built parts.

The new construction includes the prefabricated sub-assemblies or components.

Responsibility for implementation

Operational organization

M&O Region SVP, Area Directors & Country (Marine) Manager, NC Manager, Project Leaders and Surveyors.

Functional organization

New Construction Management Department (DO_NCM) for functional support

References

NC Marine & Offshore Quality Documentation

  • HSE, GEN, MPG, PNC, TNC, PNS, TNS, PTE, TTE; as applicable

Marine Reference Libraries

  • MO / Recognised Organisation (RO) Rules > Recognised Organisation (RO) Rules, NR, NI; as applicable

  • MO / HO Circulars > NCM Circulars in force; as applicable

IACS publications

  • PR, UI, UR, Recommendations; as applicable

IMO Instruments

  • SOLAS, MARPOL, Codes, Resolutions, Circulars, Guidelines, Other Conventions, unified interpretations, Performances standards; as applicable

  • Survey Guidelines under the Harmonized System of Survey and Certification (HSSC), as amended

Other International and National Regulations

EU Legislation

  • Marine Statutory Equipment - European Directive 2014/90/EU (New MED), as amended

Marine and Offshore Production Tools user manual and training material

  • Project management applications (VPM, VPM for SAY mobile Application)

  • Training and Qualification data base (QUALIF)

  • Request for Classification and classification report (SAM / GENESIS)

  • Certificates and Records editor (ASMS2)

  • Mail management (SEMAPHORE / SEA FILING)

graph1
IT Tools to be used during NC Process

Terminology

DO_NCM (NCM)

New Constructions Management Department (NCM) within Head Office Operations Management (DO), with main tasks defined in the related management procedure, Sec. 5, Par. 5.2.1.

NC Manager

Operational Area or Country M&O Managers or their Delegates, (NC Managers, NC Managers Delegate) in charge of New Constructions Services, with general responsibilities defined in NC Managers for the New Construction Surveys scope and for the other detail scope of responsibilities and authorities to be documented in local instruction as per the related management procedure.

NC Project Leader (PL)

Qualified Field Surveyor responsible for the construction surveys, project management and initial classification of one or more ships as per NC Project Leaders (PL). Refer to the new construction surveyor certification scheme for the qualification requirement.

NC Project Leader Delegate (PLD) and NC Project Leader under supervision (PLDus) refer to NC Project Leader Delegate (PLD) / Project Leader Delegate Under Supervision (PLDus).

NC Surveyor (SAY)

NC Surveyor at Yard (SAY) are exclusive and non-exclusive surveyors as defined in the new construction surveyor certification scheme authorized to carried out New Construction (NC) Surveys and to conclude whether compliance has been achieved.

Survey Team

Team of NC Surveyors at Yard (SAY) participating in each project and appointed by the NC Manager (or delegate) and / or Project Leader, acting independently as per qualification for the assigned survey, supporting and reporting to the Project Leader(s).

Subject Matter Expert (SME)

Support staff assisting in the performance of classification or statutory work as defined in the new construction surveyor certification scheme.

Gas & New Technologies Team (GNT)

The Gas & New Technologies Team (GNT) is a functional entity within DO_NCM providing technical expertise, project coordination support and competence development for projects involving innovative technologies, alternative fuels and other technically complex new construction projects. The team supports NC Managers, Project Leaders and operational structures through technical guidance, training, resource planning and cross-country coordination.

Project Coordinator

Technical Referent or experienced Specialized Project Leader acting as support and supplement to assigned Project Leader, appointed on specific projects by NCM/GNT Department as deemed necessary.

LPO Project Manager

LPO (Local Plan Approval Office) Surveyor appointed for a project by the LPO Manager of the LPO owner (defined in the local plan approval office procedure Sec.3, Par. 3.2) with responsibilities as detailed in 2.4.

MOC (NC)

Recognised Organisation (RO) Marine Operational Centre with general responsibilities defined at the fleet management organisation and responsibilities procedure Sec 13 and as per the related procedure for the new construction activities. The MOC(NC) is determined against the place where the shipyard is located.

Shipbuilder

A company which signs with the prospective owner a "Contract for Construction" for the design and construction of ships and/or offshore units. The shipbuilder also signs the "Request for Class" with the classification society for the assignment of class. The shipbuilder may subcontract the whole or part of a New Building to a shipyard having the adequate required installation facilities.

Shipyard

A company which has the adequate installation facilities needed for building ships and/or offshore units.

“Pure-sister ship and quasi-sister ship”

The definition of a “quasi-sister ship” applies to a ship of the same or similar design as a previously classed ship but which cannot be considered as a sister ship due to the fact that she does not comply with Recognised Organisation (RO) Rules, Part A, Ch 1, Sec 1, 1.2.2 and IACS PR 29 requirements, not belonging to the same contract between the prospective owner and the shipbuilder or exercised more than 1 year after the contract was signed. A “Pure-sister ship” is a ship part of series built under a single contract.

“Frozen” contract

A Contract is “Frozen” when the construction has stopped for a certain period of time, not officially abandoned but no activities are ongoing.

Ship Construction File (SCF)

As defined in NR467 Part A Chapter 3 Section 7 [3].

Recognised Organisation (RO) Record of Construction

In general: the set of documents made of Contractual documents; list of applicable rules and requirements; list of approved drawings and follow-up; list of material and equipment certification and follow-up; list of applicable shipyard fabrication standards and procedures; list of testing procedures; survey and testing program; request for survey, survey log book; the construction and all necessary inspections, tests and qualification tests that are to be made under the Surveyor’s satisfaction and the records, check lists, inspection and test records, etc. that prove Surveyors have complied with the requirement of the new building survey planning; the main correspondence; records, reports, certificates and attestation issued at delivery.

Patrol (P)

The act of checking on an independent and unscheduled basis that the applicable processes, activities and associated documentation of the shipbuilding functions continue to conform to classification and statutory requirements.

Review (R)

The act of examining documents in order to determine traceability, identification and to confirm that processes continue to conform to classification and statutory requirements.

Monitoring (M)

Survey method agreement to perform random verification of an ITP item either by Witnessing, Patrolling, Reviewing documentations or a combination of all those methods at the Surveyor satisfaction.

Witness (W)

The attendance at scheduled inspections in accordance with the agreed Inspection and Test Plans (ITP) to the extent necessary to check compliance with the survey requirements.

Hold point (H)

A survey hold point is a critical juncture in the construction process where work must stop pending surveyor approval before proceeding. The surveyor attendance is mandatory at scheduled inspections in accordance with the agreed inspection and Test Plans (ITP) to check compliance with the survey requirement.

ORGANIZATION AND RESPONSIBILITIES IN NEW BUILDING SURVEY at yard ACTIVITIES

New Construction Operational Management, Organization and Operation

NC Operational and Functional Reporting Lines

The operational structure entities (Marine Managers, New Construction Managers, Project Leaders and Surveyors):

  • Are hierarchically linked to the Operational Structure management (Region, Area, Country) for operational and commercial matters.

  • Maintain a functional reporting line to the Operations Department - New Construction Management (DO_NCM) regarding service quality, technical consistency and the achievement of New Construction objectives.

Within this functional relationship, DO_NCM provides procedures, functional guidance and support, promotes consistent implementation of New Construction requirements, and monitors operational performance. This functional reporting line does not constitute a formal line of authority.

graph2
M&O NC Organizational structure

The Project Leader and the survey team are responsible for the project and shall be qualified in compliance with the new construction surveyor certification scheme requirements.

Functional organization - Role and responsibilities

New Construction Management (NCM)

Within Head Office Operational Management (DO), DO_NCM activities cover all services related to new building survey at yard for New Construction initial Classification and Statutory Certification. Main responsibilities are defined in documents the related management procedure Section 5.2.1 and the marine and offshore HSSE management system Sec 5.3., including:

  • Monitoring and control the delivery of NC services by operational structure

  • Manage functional Department supporting operational units, providing technical support for units under construction

  • Define New building procedures and provide guidance for their implementation (e.g. use of Reporting Tool VPM)

Related Authority includes auditing the network operational units to assess their performance, final product and deliverables in compliance with statutory, regulatory and classification requirements.

NCM Quality and Technical Manager

Monitor the New Construction (NC) activities within their assigned areas.

Main Responsibilities
  • Monitor New Construction operations through VPM assessment, VCAs, direct communication with NC Managers and Project Leaders, and on-site visits.

  • Provide support to NC Managers, as required or upon request, to enhance client satisfaction, product conformity, and the effectiveness of support, management, and monitoring of NC Project Leaders & Surveyors at Yard.

  • Provide technical support to Project Leaders.

  • Investigate internal and external complaints.

  • Participate in the analysis of class related detentions involving newly delivered ships and follow-up with the relevant FM/MO on identified actions.

  • Lead NC office Internal Audits and VCAs.

  • Request corrective actions and monitor their implementation and effectiveness when deficiencies or opportunities for improvement are identified during monitoring activities or internal audits.

  • In coordination with the NC Manager, propose corrective actions for non-conformities identified during external audits and monitor their implementation and effectiveness.

  • Supervise the Project Leaders placed under “Increase Monitoring” for their assigned project.

NCM Training and Qualification Manager

Monitors the NC network of Surveyors and Project Leaders, the Order Book, and the achievement of NC KPIs.

Main Responsibilities
  • Defines qualification procedures and competency frameworks, and establishes in coordination with the NCM Director the training programmes associated with each qualification level for Surveyors and Project Leaders. Follows-up Training, Qualification and Monitoring activities as per the new construction surveyor certification scheme and provides support to NC Managers.

  • Organizes, leads or coordinates the development, maintenance and periodic update of training materials and learning solutions supporting the NC qualification scheme, including e-learning modules, case studies, virtual reality training, classroom training, mentoring and tutoring programmes.

  • Reviews and validates the annual Regional Training Centre (RTC) classroom training plan for New Construction personnel, ensuring alignment with qualification requirements, operational needs and strategic objectives of the New Construction network.

  • Follows up with NC Managers on the achievement of NC KPIs as defined by NCM and report the results to DO Management

  • Monitors the Order Book through the assessment of VPM dashboards, milestone updates, and SAY actors assignments.

  • Contributes to the organization and supervision of the annual NC Seminar and monitor its rolling out to the NC network.

  • Assists in Internal NC Office Audits and VCAs.

  • Proposes training actions, validate qualifications and review activity monitoring reports in accordance with the new construction surveyor certification scheme.

  • Decides, on case by case basis, whether the appointment of a Surveyor or Project Leader who does not hold the required qualification may be accepted under the specific provisions defined in the new construction surveyor certification scheme.

  • Review the nomination of Project Leaders for specific or complex projects.

  • Approves the annual RTC training plan for New Construction personnel and assigns trainers or subject matter experts as required to support qualification and competence development activities.

  • Monitors the effectiveness of the training provided

GNT Project Coordinators / Technical Referents

Project coordinators / Technical referents may by assigned to provide project coordination for complex projects or whenever deemed necessary.

Responsibilities

They provide specialized technical expertise and support to Project Leaders and NC Managers and contribute to competence development within the NC Network. When formally nominated, they may deliver training activities within their area of expertise.

When designated by the NCM/GNT Director and appointed to a project by the NC Manager or the Project Leader, they may act as Project Coordinators as defined in §1.4.8.

In such capacity, they support and supplement the assigned Project Leader by:

  • Identifying the expertise required for project execution and recommending suitable resources within the NC Network;

  • Supporting coordination between the various stakeholders involved in the project;

  • Contributing to contract management and project follow-up activities;

  • Facilitating coordination and consolidation of project activities, particularly when multiple countries and sites are involved;

  • Leading or co-leading, with the Project Leader, the Preliminary Kick-off Meeting with the relevant LPOs;

  • Ensuring effective transfer of project-specific information and coordination arrangements to the assigned Project Leader.

Authorities

  • Recommend the involvement of technical experts and specialized resources required for project execution;

  • Escalate resource, competence or coordination concerns to the appropriate management level;

  • Coordinate technical exchanges between project stakeholders within the limits of their assignment.

Additional responsibilities for members of the Gas & New Technologies Team

For projects within their field of competence, GNT members may additionally:

  • Provide technical support during contract review and project preparation;

  • Contribute to the identification of training and qualification needs;

  • Support cross-country coordination and knowledge sharing;

  • Assist in the development and maintenance of competence related to alternative fuels, gas carriers, offshore units, wind-assisted propulsion systems and other emerging technologies;

  • Provide technical support and project coordination for particularly complex projects.

Operational organization - Role and responsibilities

NC Managers

NC Managers are committed to continuous improvement of the quality of the service delivered to clients by ensuring that Project Leaders and Surveyors under their control are performing surveys, providing reports of the required standard in line with applicable requirements and procedures and by raising and maintaining the expertise of the Surveyors and their knowledge of relevant Rules and Regulations.

NC Managers are committed to control one or several Project Leader and Surveyors, over a specific geographical sector as defined in the new construction surveyor certification scheme and QUALIF database. NC Managers may nominate NC Manager Delegates (or local area managers) to support their functions.

The detailed scope of responsibilities and authorities as Marine Manager, NC Managers and Delegates which depends on the local activities and / or organizations, shall be documented in a local instruction as depicted in the related management procedure and the marine and offshore HSSE management system.

NC Managers report functionally to DO_NCM on below SAY related area of responsibilities:

Responsibilities and Authorities
  • Ensure with Marine Managers the adequacy (in number and competency) of the resources in terms of NC Project Leaders and NC Surveyors with the new construction activities in their area of responsibility

  • Manage the certification and up-grading of Surveyors and Project Leaders under their responsibility, in adequacy with the local needs, using the Marine tools dedicated for the purpose

  • Manage the rolling-out of the annual NC Seminar they will have attended to their respective team of NC Surveyor (refer to the new construction surveyor certification scheme)

  • Prepare monitoring and training plans (*) of the NC staff, according to the new construction activities in their area. * NC Manager should liaise with DO_NCM for RTC training plan and organization

  • Schedule and organize (*) the monitoring and training according to the established plans

  • Review the completed activity monitoring report of field surveyors (and the additional specific report as applicable) and where necessary will ensure that the proposed course of action related to significant deviation, as appropriate, is implemented (evidence of such needed action shall be recorded locally); this review will be recorded in the QUALIF data base as validation of the monitoring

  • Manage the review and issuance of new construction contracts (in coordination with HO/ DCM) and in accordance with delegation granted by the Marine Manager

  • Appoint for each NC project a Project Leader with the required level of certification. If needed and in cooperation with the Project Leader, assign a team of surveyor(s) for those projects. For specific or complex projects (Gas, Offshore, Passenger, RoRo-passenger, SPS and some specific flag) the PL proposed appointment may be reviewed by DO_NCM

  • Validate the NRS and NPSS prepared by Project Leaders

  • Ensure that Project Leader monitoring, contract performance and review of ships files / Recognised Organisation (RO) record of construction is performed and in line with NC Objectives and KPI (**)

  • Provide root cause analysis and propose corrective action in case of findings during monitoring or Audit (internal or external) process. Implement and follow-up the approved corrective actions requested. (See Related Authorities)

  • Provide required annual analysis to be included in the unit management review.

Untitled

Consult with DO_NCM in case for a NC project, no Project Leader would be available with the needed qualification. The appointment of a Project Leader within the network needs to be validated by DO_NCM

Collaborate with DO_NCM in case of specific need related to operational/technical/training/certification matters (In particular for Gas, Offshore, Passenger, RoRo-passenger, SPS or complex project).

** For Country with a small NC SAY team (i.e. 2 Surveyors or less, NC Manager being active Project Leader and/or Surveyor) DO_NCM will implement on case by case basis specific requirements for the monitoring of the concerned NC SAY team and the project dealt with.

NC Project Leaders (PL)

The Project Leader is responsible for the construction surveys, project management and initial classification of one or more ships.

Project Leaders may also carry out surveys according to their technical certification as per the new construction surveyor certification scheme

Responsibilities and Authorities
  • When needed, in cooperation with the NC Manager, assign a team of surveyor(s) for their projects

  • Ensuring that each surveyor appointed for a task has the required certification for carrying out this task

  • Prepare projects as per guideline in Project leader office main tasks and the following Section 4 for preliminary kick off meeting with LPO, kick off meeting with the shipbuilder, and survey plan in the VPM > SAY tree

  • Follow-up through VPM the design review status and verify that the necessary documentation is available and reviewed for survey; Call for regular follow-up meeting with concerned LPO actors if necessary

  • Follow-up the materials and equipment are supplied with inspection at works certificates as required in applicable rules; Call for RO Manager or RO Surveyor support / clarification in case of incomplete certification at work (intermediate survey report) or if otherwise deemed necessary

  • Coordinate, assign and supervise the tasks to be performed by the appointed surveyors in the shipbuilder’s facilities

  • Coordinate with Project leader delegate when Ship is constructed partially in different country or location

  • Provide evidence through records, check lists, inspection and test records, etc. that survey teams had complied with the requirements of the new-building survey planning and duly participated in the relevant activities shown in the shipbuilder's examination and test plans. Follow-up survey reports issued by the survey teams (*)

  • Call for quality meeting with the Shipbuilder regularly or when necessary and issue regular reminder

  • Follow up and update milestones, quality meetings, reminders

  • Prepare records, classification and statutory reports during the construction as required for each specific project

  • Prepare and submit within the required timing NRS, NPSS, Classification reports

  • Issue at delivery provisional or definitive Class and Statutory certificates and attestations as required for each specific project

  • Call for advice from NC Manager (and/or DO_NCM through NC Manager) for technical matters during the construction or for issuance of certificates, at any time support is needed and in case of doubt

Untitled

Collaborate with DO_NCM in case of specific need related to quality and technical matters in particular for Gas, Offshore, Passenger, RoRo-passenger, SPS or complex project

* For Country with a small NC SAY team (i.e. 2 Surveyors or less, Project Leader being Surveyor) DO_NCM will implement on case by case basis specific requirements for the monitoring of the concerned NC SAY team and the project dealt with.

NC Project Leader Delegate (PLD)

Recognised Organisation (RO) field surveyor designated to take over the Project Leader's responsibilities when the Project Leader is not available. The Project Leader Delegate has the same qualification requirements, responsibilities and duties as the Project Leader.

The NC Manager in cooperation with the Project Leader and when applicable the other country NC Manager, may also nominate Project Leader Delegates in the following circumstances:

  1. to take over the Project Leader's responsibilities when the Project Leader is not available.

  2. when a significant part of the construction is built in a different location. The PLD will coordinate with the PL for the scope of work of each party and documentation expected.

Except for surveyors appointed as Project Leaders Delegates under supervision for a specific project (for upgrading) and performing their duties under the supervision of a qualified Project Leader, a Project Leader Delegate has the same qualification requirements as the Project Leader.

Project Leader Delegate Under Supervision (PLDus)

“Project Leader Delegate under supervision” are assigned in VPM on project as PLD for traceability of their activities for qualification record purpose, but they are supervised by Project Leader as described in the new construction surveyor certification scheme during this period.

Surveyor (SAY)

A Surveyor at Yard (SAY) is a qualified surveyor involved in New Construction activities and assigned to one or more shipbuilding projects under the coordination of a Project Leader. Surveyors operate within the scope of their qualifications and certifications and perform surveys in accordance with the applicable Recognised Organisation (RO) Rules and procedures, contractual requirements, and project instructions.

Surveyors are functionally supervised by the assigned Project Leader and report survey activities through VPM and the applicable reporting channels.

Responsibilities
  • Carry out construction surveys, inspections, tests, documents review and verifications assigned to them in accordance with applicable Rules, procedures, approved plans, specifications, and contractual requirements.

  • Assess whether the conditions necessary to perform surveys with the required level of quality, safety, and technical effectiveness are met, considering their own competencies, qualifications, and the prevailing site conditions.

  • Inform and seek guidance from the Project Leader whenever technical issues, situations, or decisions are considered beyond their authority, competence, or assigned responsibilities.

  • Ensure the quality, accuracy, and completeness of survey activities, records, and reports issued under their responsibility.

  • Prepare and submit survey reports, survey comments, and other project documentation in a timely manner.

  • Maintain effective communication with the Project Leader, shipyard representatives, owners, and other stakeholders involved in the project.

  • Support the Project Leader in monitoring construction progress, identifying technical concerns, and following up on outstanding actions.

  • Contribute to the achievement of project objectives related to safety, quality, client satisfaction, and compliance with Recognised Organisation (RO) requirements.

  • Maintain their qualifications and participate in training, monitoring, and qualification activities as required by applicable procedures.

  • Perform independently the surveys and related activities for which they are qualified and certified.

  • Decline or suspend a survey activity when the conditions necessary to perform the work in accordance with Recognised Organisation (RO) requirements, safety requirements, or applicable procedures are not met, and promptly inform the Project Leader.

  • Take technical decisions within the limits of their qualifications, delegated authority, and applicable operational authority rules.

  • Issue survey reports, records, survey comments related to the activities they have personally performed.

  • Raise comments, deficiencies, non-conformities to be dealt with within the scope of the assigned survey activities.

  • Request corrective actions and verify the satisfactory closure of identified deficiencies within the scope of their assigned responsibilities.

  • Escalate technical matters, deviations, or disputes requiring higher authority or project-level decisions to the Project Leader.

Subject Matter Expert (SME)

Subject Matter Expert is a support staff in the fields of Welding; NDT; LNG Cargo Containment installation; Hazardous Area’s (ATEX, IECEx); Diving System; Assembly materials - wood, measurements related to Comfort on board and Habitability, measurements related to Underwater Radiated Noise (URN), Cyber Security.

Such staff may carry out tasks to assist or consult a surveyor, but the surveyor remains responsible for the work of the support staff and the technical content of service. Refer to Section 1, paragraph 1.4 and Section 7 of the new construction surveyor certification scheme.

The SME name and task performed will be recorded as a “note” in the comment section of the survey record in VPM.

LPO Project manager

The LPO Project manager is appointed for the project by the LPO Manager of the LPO owner (The LPO owner is specified in the RFC and managing the greatest number of design review disciplines), his responsibilities are:

  • To liaise with the Project Leader when appointed, or the NC Manager / NC manager delegate to:

    • review the project as defined in 4.3 during a preliminary kick off meeting,

    • attend regular meetings during design review phase to provide feedback on the plan approval activities, identify / anticipate possible blocking points and discuss the necessary actions to be put in place, get an update of the building phase’s progress, (I.e. 5.1.3 / 5.7.2)

  • To liaise with the other LPOs and coordinate the plan approval activities of the project,

  • To monitor the progress of the design review activities.

DO_NCM Internal Auditor

Perform Internal Audit as per annual Office and VCA plan and additionally anytime upon request from DO_NCM Director.

Surveyors Rotation Policy

For New Construction activities, the rotation of Project Leader / Surveyors after completion of a New Construction Project(*) is compulsory. This ensures diversity and prevents the same individuals from consistently attending projects at the same Shipyard or for the same Ship Owner. However, they may exist cases in which, due to the country size and/or organization, rotation may not be feasible. On such cases, survey centers need to inform the head office (DO_NCM), and request for exemption of the general rules, under the provision of valid reasons, such as particular qualifications needed.

In those cases:

  • The NC Manager will provide local / site organization details

  • The relevant project leader will maintain specific vigilance over the robustness and integrity of survey performances and reports.

  • The Head Office (DO_NCM) will enforce specific monitoring requirements for the involved surveyor, occurring biennially.

CONTRACTS

Offer Preparation

For a new construction project, following receipt of a client enquiry and for the purpose of preparing a preliminary offer, a Register Project Number shall be requested from HO/DCM through SAM (Request for Classification database).

Contract Review

General

Contract reviews shall be performed in accordance with the related management procedure and the related procedure

Date of Contract

A Declaration of Date of Contract for Construction, established in accordance with the requirements of IACS PR29, shall be provided by the Shipbuilder.

The declared date shall be recorded in SAM.

A copy of the declaration shall be retained in VPM (SAY > Shipbuilder Documents), particularly for sister ship series.

RFC entries

The Request for Classification (RFC) shall include all relevant information related to:

  • the project and unit;

  • classification and statutory requirements;

  • sister ship status;

  • dual or double class arrangements; and

  • Memoranda of Understanding (MoU), where applicable.

Information entered in the RFC is automatically transmitted to VPM.

Building schedule follow-up

The initial Shipbuilder's construction schedule shall be recorded in the RFC and transferred to VPM as the contractual schedule.

Subsequent updates of the construction schedule are mandatory and shall be maintained directly in VPM under the "Forecast Dates" calendar.

Contracts Signature

Following validation by HO/DCM, the Request for Classification (Ad.ME 545 L) shall be signed by the Client and the Country Marine Manager.

The Country Marine Manager may delegate contract review and signature authority to the New Construction Manager or Office Manager, as applicable.

Following contract signature:

  • the original signed document shall be forwarded to HO FM_REG for record retention;

  • the electronic version shall be transmitted through SAM; and

  • a scanned copy shall be uploaded to VPM (SAY > Recognised Organisation (RO) Documents).

Modifications of contracts

Where the contractual scope is modified during construction, including changes affecting flag administration, class notations or other contractual conditions, an amendment to the RFC shall be prepared and signed by both the Client and the Recognised Organisation (RO) authorised signatory.

Following signature, the original amendment shall be transmitted to HO FM_REG for record retention.

The Project Leader shall ensure that all affected Plan Approval Offices are informed so that the impact of the modification on the approval status of drawings and technical documentation can be assessed.

Memoranda of Understanding (MoU) or Memoranda of Agreement (MoA)

General

Any MoU or MoA associated with a new construction project shall be reviewed by the relevant HO departments, including LC&R, LPO, EMC and NCM, prior to signature.

Dual Class Arrangements

Applying PR1B C 2.2, Trilateral and/or bilateral agreement is to be signed by the parties (at least between the two Class societies) on how to perform survey during fabrication, construction, and testing of the ship, exchange information and share survey records. The agreement adopted in to be available in VPM Recognised Organisation (RO) record of construction. Refer also to the dual class design review instruction for the design review phase.

In accordance with IACS PR1B, Section C 2.2, bilateral or trilateral agreements shall be established between the parties involved, including the participating Classification Societies.

Such agreements shall define, as applicable:

  • responsibilities for surveys during fabrication, construction and testing;

  • methods for exchange of technical and survey information; and

  • arrangements for sharing survey records.

The applicable agreement shall be retained in VPM as part of the construction records.

Reference shall also be made to the dual class design review instruction for requirements applicable to the design review phase.

Transfer of Class During Construction

Transfer of class during construction shall be managed in accordance with the related technical procedure and the dual class design review instruction.

MoU at New Building

Where an RFC incorporating an MoU is requested by the Shipbuilder for classification surveys based on prior design approval granted by another IACS Member Society, HO shall be consulted before the RFC or MoU is signed.

Regardless of any such arrangement, the present procedure shall be fully applied to the project.

From 1 January 2025, IACS PR42 shall apply, where applicable.

Pure-Sister Ship and Quasi-Sister Ship

SAM allows a ship to be recorded as a "pure-sister ship" or a "quasi-sister ship" at the time of RFC creation. Eligibility for the status of "quasi-sister ship" shall be assessed against the criteria defined in Annex A5, Table A.

The designation of a ship as a "quasi-sister ship" in SAM is an internal administrative feature intended to facilitate access to information available in VPM, including drawings, approval records and LPO comments related to ships of the same or similar design. Such designation does not modify the applicable classification, statutory or procedural requirements.

For each quasi-sister ship, the requirements related to complete approved documentation and Rules Gap Analysis shall be fulfilled in accordance with the local plan approval office procedure, Section 6.1 "Quasi-sister Ships".

Construction Performed in Different Countries or Locations

Where an RFC is signed in one country and construction activities are performed wholly or partly in another country or location, the respective responsibilities and scope of work of each involved Operational Structure shall be clearly defined and documented.

Particular attention shall be given to:

  • conducting kick-off meetings with the main hull subcontractors in accordance with 4.4.1; and

  • establishing a clear allocation of survey responsibilities between the involved survey locations in accordance with 4.7.2.

Frozen contracts

Frozen Status

New construction ship contract will be recorded in VPM as “Frozen” when the construction is stopped for an undetermined period of time, she is not officially abandoned but no activities are ongoing or, she is put in some sort of “Lay up” before delivery.

The decision to consider a project as Frozen is made by NC Manager. Owner CD and NCM are informed.

The status of “Frozen” contract is to be reviewed every year.

A new construction project may be designated as "Frozen" in VPM when:

  • construction activities have been suspended for an indeterminate period;

  • the project has not been formally cancelled or abandoned; or

  • the vessel has been placed in lay-up prior to delivery and no construction activities are ongoing.

The decision to assign Frozen status shall be made by the New Construction Manager.

The Owner CD and NCM shall be informed accordingly.

The status of each Frozen contract shall be reviewed at least annually.

Reactivation of a Frozen Contract

Before reactivation of a Frozen project at the request of the Shipbuilder, a condition survey shall be carried out in accordance with Section 6.12, Survey Before Reactivation of a Frozen Contract.

The contractual conditions shall be reviewed and the RFC amended as necessary in accordance with Section 3.5.7, Contract Modifications, and Section 4.8, Reactivation of a Frozen Contract.

The reactivation date shall be recorded in VPM and NCM shall be informed.

Cancelled Contracts or Classification Abandoned

Where:

  • the order has been cancelled;

  • construction has been definitively abandoned; or

  • surveys are continued without classification (SNC),

the vessel In/Out (I/O) status code shall be updated accordingly in VPM, SAM and/or Neptune, as applicable.

PREPARATION OF SURVEYS

Scope of Services and Applicability of Survey Planning

The scope of services to be provided by Recognised Organisation (RO) for a new-building project is defined in the Request for Classification (RFC) and its associated annexes. The RFC shall be signed, or at least be in a validated status, prior to the commencement of classification activities and survey services.

The Survey Planning process defined in this Section shall be applied to all new-building projects falling within the scope of IACS UR Z23.

For projects not subject to IACS UR Z23, the Survey Planning process shall be implemented whenever required by: contractual commitments, applicable Classification Rules, Flag Administration requirements, specific project risks identified during project assessment or upon decision of the NC Manager.

The content, extent and level of detail of the Survey Plan and related planning records shall be proportionate to the nature, complexity and risk profile of the project, taking into account the applicable classification, statutory and contractual requirements.

Survey Team

For each contract, the Marine Manager, NC Manager, or their delegate shall designate a Project Leader and the required Surveyors, ensuring that all assigned personnel hold the appropriate certification in QUALIF in accordance with the qualification requirements defined in the new construction surveyor certification scheme.

The survey team shall be recorded in VPM under the relevant Actors tab. The composition of the survey team may be adjusted throughout the construction period to reflect the workload, project complexity, and specific technical requirements. Accordingly, the NC Manager or the Project Leader may assign additional Surveyors who were not part of the initial project team, provided that they hold the appropriate certification in QUALIF.

Any modification to the survey team during the construction period shall be updated in VPM, including the designation of the Project Leader, any Project Leader Delegates, and all Surveyors involved in construction survey activities.

Where construction activities involve multiple countries or sites, the same principle shall apply, and all personnel participating in project execution shall be registered in VPM.

For projects requiring specific technical expertise or enhanced oversight, including but not limited to Flag, Gas, Offshore, Passenger Ship, RoRo-Passenger Ship, SPS, or other complex projects, the appointment of the Project Leader and/or specialized Surveyors may be supported, coordinated, or reviewed by DO_NCM.

Applicable Documentation and Preparation of the Kick-off Meeting

Applicable Documentation

The list of project-specific applicable documents and requirements shall be established at the earliest possible stage and made available to the Project Leader no later than the Kick-off Meeting. The applicable documentation shall subsequently be maintained and made accessible in VPM throughout the construction period for use by the assigned surveyors.

Preliminary Kick-off meeting

A Preliminary Kick-off Meeting shall be held as early as practicable between the Project Leader (when already appointed) or the NC Manager / NC Manager Delegate and the designated LPO Project Manager to review the project and establish the framework for subsequent project execution.

A Preliminary Kick-off Meeting is generally required for:

  • First-of-type ships to be built at a shipyard;

  • New ship types or novel designs for the Society or the shipyard;

  • Complex projects involving innovative technologies, extensive class notations, alternative designs, or significant regulatory challenges;

  • Projects involving specific Flag Administration requirements requiring early clarification;

  • Projects conducted under unusual contractual, technical, organizational, or operational conditions;

  • Any project for which the NC Manager, Project Leader, LPO Project Manager or DO_NCM considers that early coordination is necessary.

A Preliminary Kick-off Meeting may be omitted for:

  • Pure sister ships;

  • Quasi-sister ships, provided that the scope differences have been reviewed and addressed through a simplified project review;

  • Ship types routinely and continuously constructed by the same shipyard, where equivalent projects have recently been successfully executed without significant interruption, design changes, or regulatory changes.

The justification for omitting or simplifying the Preliminary Kick-off Meeting shall be recorded by the NC Manager or Project Leader.

The involvement of DO_NCM shall be ensured when required for complex projects, projects under monitoring, projects subject to specific Flag requirements, projects assigned to a Project Leader under monitoring, or whenever deemed necessary to strengthen coordination and collaboration with the LPO.

  • For vessels intended to fly the Canadian Flag, the involvement of Recognised Organisation (RO) Canada is mandatory in accordance with Transport Canada requirements.

  • For vessels intended to fly the French Flag and constructed outside France, the involvement of DO_NCM is mandatory.

Minimum Agenda of the Preliminary Kick-off Meeting

The Preliminary Kick-off Meeting shall address, as a minimum, the following topics:

  • Project description, scope and technical specifications.

  • Contract review, RFC status, project data in VPM, clarifications, applicable MOU/MOA, series construction arrangements and key project milestones.

  • Review of the list of applicable documents and requirements.

  • General Class and Statutory requirements, including any specific requirements associated with the assigned Class notations.

  • Specific Flag Administration requirements and instructions. Where necessary, consultations may also be arranged with MOC (NC), MOC (CD), the relevant Country Department, or DO_NCM, particularly for Canadian and French Flag projects.

  • Communication channels and document circulation arrangements, including the distribution of drawings and correspondence managed outside VPM.

  • Identification of key project stakeholders and VPM actors, including:

    • LPO Owner;

    • LPO Project Manager;

    • Premium account representatives, where applicable;

    • Design offices responsible for each discipline;

    • Assigned surveyors and their preferred points of contact.

  • Review of VPM categories, applicable checklists and the list of drawings expected from the shipyard.

  • Preliminary identification of materials and equipment subject to certification in accordance with NR266.

  • Review of major technical concerns, including structural arrangements, materials, scantlings, welding plans, critical design features and major equipment. Where the necessary information is not yet available, this topic may be deferred to subsequent project follow-up meetings.

  • Feedback and lessons learned from similar previous projects, where available.

Records

The minutes of the Preliminary Kick-off Meeting, together with any subsequent follow-up actions deemed necessary, shall be recorded in VPM. The meeting records could be prepared using the content and structure of the Pre Kick-off Meeting template provided Annex 6 or using Table 1 of NR540.

Kick-off Meeting with the Builder

General

Prior to the commencement of surveys for a newbuilding project, a Kick-off Meeting shall be held with the Shipbuilder in accordance with the requirements of NR467 Pt A, Ch.3, Sec.7 [4.1.1].

The purpose of the meeting is to establish a common understanding of the project organization, survey arrangements, communication channels and other matters required by the applicable Rules. The agenda and topics to be discussed are to comply with the requirements of NR540.

The preparation and conduct of the meeting shall take into account the shipbuilder's organization, construction strategy, production sites, subcontracting arrangements and any other project-specific factors that may affect survey planning and execution.

Where a Project Leader has been assigned, the Project Leader shall participate in the Kick-off Meeting. Where no Project Leader has yet been appointed, the NC Manager shall ensure suitable representation by Recognised Organisation (RO) and designate a Project Leader as appropriate. Other Recognised Organisation (RO) participants, including representatives from the Operational Structure, LPO, RO or other specialist functions, may attend depending on the project complexity and subject to any necessary agreement with the Shipbuilder.

Where construction activities are planned at multiple locations and such activities are considered significant for the project, additional Kick-off Meeting(s) may be organized for the concerned location(s). In such cases, a Project Leader Delegate may be appointed in accordance with this procedure.

Where the Request for Classification or contractual agreement is concluded before the construction shipyard has been selected or contracted, a preliminary meeting may be held with the Client and other relevant parties to support project preparation. Such meeting does not replace the Kick-off Meeting required by NR467, which shall be conducted with the participation of the contracted Shipbuilder before commencement of surveys.

Quality standards

Prior to the commencement of fabrication or construction activities, the applicable fabrication and quality standards shall be reviewed with the Shipbuilder and agreed as part of the Kick-off Meeting process.

The Project Leader shall verify that the proposed fabrication, inspection and acceptance standards comply with the applicable Recognised Organisation (RO) Rules, recognized industry standards accepted by the Society, and any project-specific contractual requirements.

Where alternative standards, procedures or acceptance criteria requiring Society review are proposed, their acceptability shall be assessed and agreed in accordance with the applicable Rule requirements before fabrication or construction commences.

For constructions in materials other than steel, including aluminum and composite structures, and for offshore units, the applicable fabrication, quality and certification requirements shall be addressed in accordance with the relevant Rules, contractual scope and certification scheme.

Series of ships

For a series of ships of the same design constructed at the same shipyard, either concurrently or successively without significant interruption, the Kick-off Meeting held for the first ship may be considered applicable to subsequent ships, provided that the shipyard organization, construction arrangements and other factors affecting survey activities remain substantially unchanged.

Where significant changes are introduced, including modifications to ship design, applicable requirements, construction arrangements, production sites or shipyard organization, a dedicated meeting shall be held to review the impact of such changes and confirm the survey arrangements for the project. The outcome of the meeting shall be documented and retained in the project records.

For shipyards regularly constructing the same type of Recognised Organisation (RO) classed units, such as fishing vessels, tugs or similar vessels of less than 65 m in length, a Kick-off Meeting may remain valid for a period not exceeding two years, provided that the shipyard organization, construction arrangements and applicable requirements remain substantially unchanged.

Where a new Kick-off Meeting is not held in accordance with this section, the records of the reference Kick-off Meeting, together with any project-specific updates, shall be retained in the Recognised Organisation (RO) Record of Construction and associated project documentation.

Minutes of Kick-off meeting

A record of the Kick-off Meeting shall be prepared and maintained as part of the project documentation.

The meeting record shall be established using the applicable template provided in NR540, including the standard template for conventional new-building projects or the dedicated template for composite construction projects, as applicable.

The Kick-off Meeting shall be prepared, conducted and documented in accordance with NR540.

The minutes shall document the subjects discussed, agreements reached, actions identified and any project-specific arrangements relevant to the planning and execution of surveys.

The approved minutes of the Kick-off Meeting shall be retained in the project records and appended to the Recognised Organisation (RO) Record of Construction in VPM.

Change to Activities Agreed at the Kick off Meeting

The Shipbuilder shall inform the Society of any significant change affecting the activities, arrangements or assumptions reviewed during the Kick-off Meeting.

Such changes shall be assessed by the Project Leader to determine their impact on survey planning, survey attendance and applicable requirements. Where necessary, the survey plan shall be revised and the corresponding arrangements documented in the project records.

Changes requiring review may include, but are not limited to, modifications to construction arrangements, production sites, subcontracting arrangements, inspection or testing methods, applicable Rules or statutory requirements, structural design modifications, or the implementation of additional survey or inspection activities resulting from identified non-conformities or other project-specific circumstances.

Where the significance of the changes warrants further coordination between the Society and the Shipbuilder, an additional meeting may be convened and its outcome documented as part of the project records.

Review of the construction facility

General

The Society is to familiarize itself with the shipbuilder's production facilities, management processes, and safety arrangements, as necessary to support survey planning and compliance with the requirements of NR540 prior to the commencement of steelwork or other construction activities.

A review of the construction facility is to be conducted in the following circumstances:

  • when the Society has no previous experience, or no recent experience, of the construction facility, typically following a period of more than one year without construction activities under survey, or where significant new infrastructure or production facilities have been introduced;

  • when significant changes in management, organization, or key personnel may affect the shipbuilding process;

  • when the shipbuilder undertakes construction of a vessel type not previously built at the facility, or a vessel incorporating substantially different design features, construction methods, or technologies.

The construction facility review is to be completed and available prior to the Kick-off Meeting referred to in §4.4, whenever such a review is required by this section. The information gathered during the review is to be taken into consideration when preparing the Kick-off Meeting and defining the survey arrangements, attendance strategy, and other matters discussed with the shipbuilder.

Shipbuilder Review Record (SRR)

Where a review of the construction facility is required in accordance with §4.5.1, a Shipbuilder Review Record (SRR) shall be completed and maintained in VPM - Shipbuilder Review Management (SRM).

The purpose of the SRR is to document relevant information regarding the shipbuilder's facilities, organization, production capabilities and subcontracting arrangements in support of survey planning. The SRR is not intended to constitute a quality management assessment.

The SRR shall be completed and validated before the Kick-off Meeting described in §4.4 whenever a construction facility review is required.

Detailed instructions for the completion, validation and management of SRRs are provided in VPM Guideline “NC00051 SAY Shipyard Review Record – User guide”.

A VPM warning (C12) is generated when: a required Shipbuilder Review Record is missing; or an existing Shipbuilder Review Record is awaiting validation.

Project documents, Examination and Test Plan for New Building activities

The Shipbuilder is to provide the Society with access to all documentation required for classification and statutory surveys, including relevant documentation held by subcontractors, manufacturers, suppliers, or other third parties.

The Project Leader is responsible for identifying, requesting, and monitoring the documentation necessary for the execution of the survey programme.

  • VPM > Survey at Yard > Shipbuilder Documents List is used to record requested documents and monitor their status.

  • VPM > Tree View > Relevant Items is used to plan and follow up survey activities, including document reviews, document revisions, survey records, comments, and outstanding actions.

The Project Leader may delegate specific document reviews or technical verifications to suitably qualified Surveyor or SME; however, overall responsibility for survey preparation, coordination, and follow-up remains with the Project Leader.

Preparation for Survey of the hull structure

The Project Leader shall ensure that the documentation necessary for planning and performing the surveys is identified, requested and reviewed, as applicable to the scope of construction.

Document reviews may be performed by the Project Leader or delegated to suitably qualified surveyors, specialists or technical referents. The Project Leader remains responsible for ensuring that all required reviews have been completed and that any identified issues are adequately followed up.

Shipyard Standards and Procedures

As applicable to the construction project, the following documentation is to be made available for review:

  • Inspection and Test Plans (ITP);

  • Non-Destructive Examination (NDE) plans;

  • Welding Consumable Specifications and Approval Details;

  • Welding Procedure Specifications (WPS) and Welding Procedure Qualification Records (WPQR);

  • For composite constructions, the relevant manufacturing procedures, material specifications and qualification records;

  • Welding Plans or equivalent fabrication details;

  • Welder Qualification Records;

  • NDE Operator Qualification Records;

  • Applicable fabrication, workmanship and quality standards adopted by the Shipbuilder.

Where the additional class notation VeriSTAR-HULL CM is assigned, the reviewed hot-spot map of the structure is also to be made available.

The absence of any of the above documents, where required by the applicable Rules, is to be justified and documented in the project records.

Material and Equipment

As required by NR467 Pt A, Ch 2, Sec 1 [2.1.5], evidence of compliance is to be made available by the Shipbuilder to demonstrate that materials, components and equipment subject to classification or delegated statutory requirements have been manufactured, tested and certified under the applicable survey regime.

The Project Leader shall ensure that suitable arrangements are established for the identification and follow-up of materials and equipment requiring Recognised Organisation (RO) certification, inspection at works, or other forms of survey during manufacture.

As part of the survey preparation process and normally during the Kick-off Meeting, the Shipbuilder should be requested to describe the arrangements established for:

  • identification of materials and equipment subject to certification;

  • monitoring of procurement and manufacturing status;

  • planning of inspections at works and attendance by the Society;

  • collection and control of certificates and related documentation.

A record for the follow-up of materials and equipment requiring certification or inspection at works should be established and maintained throughout the construction process. The use of the template provided in Annex A7 is recommended for monitoring purposes by EMC department but may be adapted to the size and complexity of the project.

Where available, the vendor list and the identification of major manufacturers should be obtained at an early stage of the project. Early communication with the relevant Recognised Organisation (RO) Network Manager or responsible certification entities is recommended in order to facilitate planning of inspections and certification activities.

Examination and Test Plans

The Shipbuilder is to provide the examination, inspection and test plans required by the applicable Rules sufficiently in advance to allow review before the relevant survey activities commence.

The Project Leader shall ensure that the plans necessary for survey preparation are identified, requested and reviewed, as appropriate to the scope of the project. Particular attention is to be given to:

  • structural examination and inspection arrangements;

  • block assembly and erection stages;

  • fit-up examinations;

  • structural and tightness testing arrangements;

  • non-destructive examination (NDE) activities; and

  • any additional inspections, examinations or tests required for the specific ship type or delegated statutory services.

The review and follow-up of these documents should be recorded in the project records and, where applicable, in VPM.

Additional Requirements for Ships Subject to SOLAS Chapter II-1 Regulation 3-10

For ships subject to SOLAS Chapter II-1 Regulation 3-10, the Shipbuilder is to provide the Survey Plan required by the applicable Rules.

The Survey Plan should be reviewed at an early stage of the project, preferably during or before the Kick-off Meeting, to verify that the proposed survey arrangements adequately address the construction process, critical areas, inspection activities, testing programme and follow-up required by the applicable Rules.

Preparation for Survey of the outfitting

Prior to the commencement of the relevant outfitting activities, the Project Leader is to ensure that the information, documentation and arrangements necessary for the intended surveys are available and adequate to support the survey programme.

In accordance with the applicable Rules, statutory requirements and project-specific arrangements, the Project Leader is to identify and, where necessary, request the documents and records required for survey preparation and verification. Depending on the scope and complexity of the project, these may include:

  • approved or reviewed drawings and plans relevant to the survey scope, particularly when not submitted through the standard plan approval process;

  • material, component and equipment certification records, including records of follow-up inspections where applicable (e.g. NR266);

  • installation procedures, method statements and associated inspection records for critical items such as shafts, propellers, rudders or other major equipment;

  • applicable fabrication, inspection and testing standards, together with inspection and test programmes for piping systems, machinery installations and other outfitting activities, as required by the applicable Rules;

  • records demonstrating compliance with specific Rule or statutory requirements;

  • any additional documentation necessary to support the execution of the surveys, taking into account the ship type, systems installed and project-specific risks.

The extent of the preparation is to be commensurate with the complexity of the project and the survey activities to be performed.

Preparation for Quay, Sea and Gas Trials

The Project Leader shall ensure that the trial programmes, test procedures and associated documentation required by the applicable Rules are requested and reviewed sufficiently in advance of quay, sea and gas trials

Particular attention should be given to:

  • trial schedules and attendance planning;

  • functional test procedures;

  • acceptance criteria and recorded parameters;

  • computerized and automated systems, where applicable;

  • measurement programmes associated with assigned class notations.

The review and follow-up of these documents should be recorded in the project records and, where applicable, in VPM.

Preparation for Statutory surveys

Where the Request for Classification (RFC) includes the issuance of statutory certificates, Statements of Compliance, or other attestations subject to the Harmonized System of Survey and Certification (HSSC), the applicable Initial Statutory Survey Guideline Checklist should be generated in VPM before the Kick-off Meeting.

The Project Leader shall use the checklist to support preparation of the statutory survey plan, including the review of the Shipbuilder's Inspection and Test Plans (ITP) and the preparation of the initial patrol plan.

When preparing the survey plan, the Project Leader should:

  • review the statutory requirements applicable to the project;

  • verify that the inspections, tests and trials proposed by the Shipbuilder adequately address the applicable statutory requirements;

  • identify within the SAY Tree the locations where the planned inspections, tests and trials are to be recorded;

  • ensure that the planned survey activities are linked to the relevant checklist items;

  • identify any statutory requirements not covered by the Shipbuilder's ITP or trial programme; and

  • request additional surveys, inspections or tests where necessary to demonstrate compliance.

The patrol plan should be established to ensure that the required statutory surveys can be carried out at the appropriate stages of construction, testing and trials.

Latest applicable Flag Administration requirements, published interpretations, relevant TNS instructions and specific flag requirements are also to be considered when preparing the survey plan and reviewing the checklist.

Where the scope of services is modified and such modification affects the applicable statutory requirements, the Project Leader shall verify that the checklist is updated accordingly in VPM.

Where a guideline checklist cannot be generated in VPM (e.g. non-convention ships, statutory services not included in the RFC, or ship types not covered by the HSSC checklists), the guidance provided in Annex A11 may be used to support preparation of the survey plan and statutory inspection programme.

A similar approach should be applied for other attestations covered by the RFC, such as compliance assessments performed on behalf of third parties or administrations (e.g. USCG requirements).

Patrol Plan

General

The Project Leader shall establish and maintain a Patrol Plan defining the scope, number, timing and frequency of patrol inspections required during construction.

The Patrol Plan is intended to complement the approved Inspection and Test Plans (ITPs) by addressing construction activities, workmanship verifications and production areas that are not adequately covered by scheduled inspection points.

When Classification Rules, statutory requirements or approved procedures require Surveyor attendance at a specific stage, such activities are normally to be included in the applicable ITP.

For ships subject to IACS UR-Z23, the Patrol Plan shall be established taking into account the construction activities identified during the Kick-off Meeting and recorded in accordance with NR540. For hull construction, NR540 Table 2 may be used as the basis for defining and documenting the initial Patrol Plan.

The initial Patrol Plan shall be presented during the Kick-off Meeting and recorded in VPM.

Patrol Plan Principles

The Patrol Plan shall be commensurate with:

  • ship type and complexity;

  • construction methods and production rate;

  • shipyard experience and past performance;

  • extent and effectiveness of Builder's quality control;

  • involvement of subcontractors;

  • identified project risks;

  • applicable Rule, statutory and contractual requirements.

The Patrol Plan is to ensure adequate Surveyor monitoring of construction quality and workmanship throughout the project.

Series Production of Small Ships

For series-built Recognised Organisation (RO) classed ships of less than 65 m in length, such as fishing vessels, tugs, patrol boats, crew boats, lightships or high-speed craft, the Patrol Plan may be established at series or workshop level rather than on an individual ship basis, provided that:

  • the vessels are constructed by the same shipyard;

  • construction is performed within the same production facilities;

  • the same production, supervision and quality control arrangements are applied;

  • the hulls are under construction during the same production period;

  • approved fabrication procedures and standards are available;

  • workmanship remains satisfactory to the Surveyor;

  • Builder quality control is demonstrated to be effective;

  • inspection records are made available to the Surveyor;

  • significant defects or recurring deficiencies are promptly reported and addressed.

Such arrangements are normally limited to a defined production period not exceeding two years.

Any deficiencies identified during patrol inspections shall be recorded and followed up in VPM against the affected hull(s). When recurring or systematic deficiencies are identified, the Builder shall investigate the root cause, implement corrective actions across the series and demonstrate effective closure to the satisfaction of the Surveyor.

Patrol Plan in Satisfactorily Evaluated Production Areas

For series construction or repetitive production activities performed in a workshop or production area that has demonstrated satisfactory and consistent quality performance, the Project Leader may, on a case-by-case basis, establish a Patrol Plan covering the production area rather than individual ships, unless otherwise required by applicable Rules or statutory requirements.

Such arrangements may be accepted when:

  • the Builder has demonstrated effective quality management and supervision;

  • workmanship has been found satisfactory through previous Surveyor monitoring;

  • Builder inspection records are available and reliable;

  • historical performance indicates effective control of manufacturing and inspection activities.

The basis for such arrangements shall be documented in writing and retained as part of the construction records.

The arrangement shall be reviewed at least annually or whenever significant quality concerns are identified, including:

  • repeated workmanship deficiencies;

  • unacceptable defect rates identified through NDT results;

  • inadequate implementation of corrective actions;

  • significant deficiencies identified during Surveyor monitoring.

Where such an arrangement is applied, the Builder shall provide the Project Leader with relevant production schedules and advance notification of activities requiring Surveyor monitoring or attendance.

Construction stages subject to mandatory attendance, closed-up surveys, hold points, witness points or Construction Monitoring requirements shall continue to be surveyed in accordance with the approved ITP and applicable Rule requirements.

Revision of the Patrol Plan

The Patrol Plan is a living document and shall be reviewed throughout the construction process.

Based on survey findings, quality performance, construction progress, identified risks or recurring deficiencies, the Project Leader may modify the scope, frequency or extent of patrol inspections.

Patrol activities may be increased where additional monitoring is considered necessary to provide confidence in the Builder's quality control processes and construction quality. Conversely, the extent of patrol inspections may be reduced where sustained satisfactory performance has been demonstrated and no significant concerns have been identified.

Note to Surveyors

General

The Project Leader may issue instructions to the assigned Surveyors whenever several Surveyors are involved in the project or whenever specific coordination is required. Such instructions should define the survey requirements, extent of verification, areas of responsibility and reporting arrangements.

The instructions may cover, as applicable:

  • Applicable Rules, Regulations and statutory requirements;

  • Reviewed drawings, plans and documents, including outstanding comments and required follow-up actions;

  • Applicable Shipbuilder fabrication standards, procedures and quality control arrangements;

  • Implementation of the Patrol Plan and survey schedule;

  • Inspection and Test Plans (ITP), Survey Plans and statutory survey checklists;

  • Welding processes, supervision, welder qualifications and NDE activities;

  • Steelwork fabrication, fit-up, assembly and erection activities;

  • Forgings, castings and associated certification requirements;

  • Materials and equipment requiring certification, inspection at works or other survey activities during manufacture;

  • Machinery, piping and accessories installation on board;

  • Electrical installations and testing;

  • Passive fire protection, penetrations of fire boundaries and draught stops;

  • PSPC implementation and coating inspections;

  • Watertight cable transit seal systems;

  • Quay, sea and gas trial preparation, including applicable test procedures and acceptance criteria;

  • Flag Administration requirements, instructions and relevant TNS publications;

  • Particular statutory requirements applicable to the project;

  • Any specific technical, operational or regulatory matters requiring increased survey attention;

  • Implementation and maintenance of project records in VPM.

Surveyors should ensure that the documentation relevant to their assigned survey activities has been reviewed sufficiently in advance and that any hold points, witness points, statutory inspections, tests, trials or outstanding issues are clearly understood before attendance.

Records of instructions issued by the Project Leader and evidence of their communication and follow-up should be maintained in VPM (SAY > Recognised Organisation (RO) Documents).

Constructed in Different Locations

When construction is performed in different countries or locations, the respective scope of work and responsibilities of the Project Leader (PL), Project Leader Delegate (PLD) and involved survey teams shall be agreed, documented and recorded in VPM.

Where the PLD cannot attend the Pre-Kick-off Meeting or Kick-off Meeting, the Project Leader shall ensure that a suitable briefing is carried out covering the agreed scope of work, project requirements, survey planning, statutory matters and any outstanding issues. Records of the agreed arrangements and briefing shall be maintained in VPM.

Reactivation of “Frozen” contract

Following completion of the condition survey described in §6.12, the NC Manager and Project Leader shall assess the implications of reactivating the project and determine the actions required before construction activities may resume.

This assessment shall include, as applicable:

  • liaison with LPO and other relevant stakeholders to identify any changes to applicable classification, statutory or flag requirements;

  • review of the scope of services and, where necessary, initiation of an amendment to the Request for Classification (RFC);

  • organization of a new Kick-off Meeting with the Shipbuilder/Shipyard;

  • review and agreement of the scope of classification and statutory surveys to be completed, repeated or supplemented, including bottom surveys where considered necessary;

  • identification of installations, systems and equipment requiring re-commissioning, re-testing or additional verification;

  • review of fabrication procedures, construction standards, testing procedures and associated documentation for the remaining work.

For the portions of construction remaining to be completed, fabrication procedures, production standards, testing procedures and related documentation are to be reviewed and approved, as applicable, in accordance with the requirements effective at the time of reactivation.

New materials, equipment, systems, or significant modifications to the approved design shall be assessed against the applicable Rule and statutory requirements in force at the time of their submission, unless otherwise agreed by the Society.

Any specific requirements of the Flag Administration arising from the period of suspension or from changes in regulations shall also be identified and addressed before the corresponding statutory certification activities are resumed

Delay in construction schedule

See Amendment to RFC

Where a significant delay to the construction schedule results in the entry into force of new classification, statutory or Flag Administration requirements, the Project Leader shall assess the impact on the project and determine whether the arrangements established at the Kick-off Meeting remain valid.

As applicable, the Project Leader shall:

  • liaise with LPO and other relevant technical stakeholders to assess the impact on design approval activities;

  • identify any new or revised Rule, statutory or Flag requirements applicable to the project;

  • review the impact on approved drawings, documents and design assumptions;

  • assess whether additional surveys, inspections, testing or certification activities are required;

  • review the impact on the Inspection and Test Plan (ITP), patrol plan and trial programme; and

  • ensure that any necessary revisions are appropriately reflected in the project records and VPM.

Where required, a project review meeting (Quality Meeting) shall be held with the Shipbuilder to agree the actions necessary to maintain compliance, including revisions to the design, installation arrangements, drawing reviews, inspection and test plans, testing procedures and survey programme.

Any agreed actions and responsibilities shall be documented and followed up through completion.

MANAGEMENT OF DOCUMENTS

Drawings and Documents Review

General

The Project Leader is responsible for the continuous follow-up of the documents and drawings (class and statutory) to be submitted, in sufficient time, in order that such documents, drawings and any modifications to them are reviewed before the relevant survey activities commences (Availability of drawing for Survey).

To that effect, the checklist for categories, the list of drawings / comments available in VPM, identifying the status of categories, the number of drawings received, their applicable revision status, shall be used for follow-up. During pre-kick off meeting the applicable design categories with the expected list of drawings to be reviewed was normally checked with LPO. Otherwise, the plans, documents to be submitted for classification are listed in the different chapters of the Rules.

At the time of NRS (Closing of Design Categories) the Project leader shall receive a written confirmation from LPO project manager (LPO owner) that all drawings required by the rules and applicable to the project were received and reviewed.

External Contacts

The Owner may be granted access to VPM subject to the shipbuilder agreement.

Follow-up with LPO

Further to the “Preliminary Kick off meeting” (Applicable Documentation and Preparation of the Kick-off Meeting) with LPO to review applicable categories and set up as far as possible the expected list of drawing, regular follow-up between project Leader and LPO owner and / or in charge is needed to early identify missing drawing, critical pending comments to be resubmitted and any other specific point of concern. The frequency of such meeting is to be agreed with LPO owner and / or in charge and adapted to the project size, type and series, as well as production schedule. At least for simple projects such meeting shall be held 3 months before scheduled delivery, unless otherwise agreed (Shipbuilder / Shipyard reminder / Closing of Design Categories / Notified Remarks Status (NRS)). As a general case and for leadership a follow-up at each milestone is needed.

Amendment to RFC

During the ship construction, in case of change of flag and/or class notations, and/or application of new regulation(s) due to milestone(s) delayed etc., the Project Leader will liaise with the concerned LPO/person in charge of RFC in order for them to verify the status of the drawing’s approval with regards to the changes occurred.

In case the modification impacts the Kick-off meeting agreement, inspection and test plans, statutory survey requirements or any other major issues, the changes and implications are to be discuss during quality meeting and the agreement on a new survey plan, if needed, recorded in VPM.

Procedures and documents reviewed by SAY

The Project leader or a qualified Surveyor may review some local detail drawings provided they do not affect the general drawings reviewed by the LPO, such as, but not limited to, the examination and testing plans (including tank testing plan), the Non-Destructive Testing plan, more generally the documents listed in Project documents, Examination and Test Plan for New Building activities “Project documents, Examination and Test Plan for New Building activities”, Modifications and repairs during construction, as well as minor structural modifications which will be above the requirements in the reviewed drawings, such as an increase of a plate thickness or additional local reinforcements, etc. Except for ships subject to certain notations (i.e. ship designed and constructed based on structural modelling, load modelling and stress and fatigue calculations) where the approval of structural modifications shall be done by, or in liaison with the LPO as it might affect conditions for the assignment of additional class notations.

The traceability of the review, the follow-up of the comments and revision, if any, is to be done through VPM (see VPM updated user guideline for the appropriate location) and linked to original approved drawing, as applicable, to comply with Availability of drawing for Survey.

A copy of these drawings and documents stamped by Recognised Organisation (RO) Survey Centre (Recognised Organisation (RO) round rubber stamp described on the general administrative instructions) with remark “reviewed, reviewed with comments, acknowledged, for information only, as appropriate” is sent back to the Shipyard (or Shipbuilder). Another copy being filed with the ship's file in VPM or e-drawing and electronic stamping is used.

The Project Leader (PL) or a suitably qualified Surveyor may review selected local drawings and project documents, provided that such reviews do not affect the scope or validity of the general drawings approved by the LPO. This may include, but is not limited to:

  • Examination and Test Plans (ITP), including tank testing plans;

  • Non-Destructive Testing (NDT) plans;

  • Project documents listed in §4.6 Project Documents, Examination and Test Plans for New Building Activities;

  • Modifications and repairs identified during construction; and

  • Minor structural modifications that remain more conservative than the approved design, such as increased plate thicknesses, additional local reinforcements, or equivalent enhancements.

For ships assigned, or intended to be assigned, additional class notations based on structural modelling, load modelling, stress analysis, fatigue assessment, or similar calculations, any structural modification that may affect the conditions for assignment or maintenance of such notations shall be reviewed by, or in consultation with, the LPO.

The review activity, including traceability of the review, management of comments, and verification of revised submissions where applicable, shall be recorded in VPM in accordance with the latest VPM User Guide and linked, where relevant, to the corresponding approved drawing, in compliance with §5.1.6.

A copy of the reviewed drawing or document, stamped in accordance with Annex A14 and marked with the applicable review status ("Reviewed", "Reviewed with comments", "Acknowledged", or "For information only"), shall be returned to the Shipyard (or Shipbuilder).

The reviewed document shall also be retained in the vessel file within VPM or e-Drawings, as applicable. Electronic stamping may be performed using Recognised Organisation (RO) Abrobate (accessible through MOVE).

Availability of drawing for Survey

Reviewed drawings in hard copies are to be kept adequately filed, preferably sorted out by specialty (i.e. Steel structure, hull equipment, machinery, piping, electricity, automation, class notations, statutory, etc.), and be easily available to the surveyor before relevant survey activities commences.

When the reviewed version is only available in electronic version (VPM e-drawing) the Surveyor is to be equipped with appropriate tools to access and adequately read this e-drawing and its comments in VPM. For such purposes the use of tablets is recommended.

Inspection and Test plans

The review of the Inspection and tests plan (Examination and Test Plans) proposal from the Shipbuilder / Shipyard is performed based on rules and statutory requirements (including additional notations and specific flag requirements and interpretations). The Project Leader is to identify the most appropriate survey methods to be used by the surveyor for each particular item (Witness, Monitoring, Review) to confirm the compliance to applicable rules and regulations considering the ship type, size, survey requirements and the shipyard quality systems. The Patrol plan (General) is to be consistent with the ITP for the Hull item under monitoring. The review is to take into account the statutory guidelines check lists as indicated in Preparation for Statutory surveys.

Welding Procedures

Reminder: Welding consumables and welding procedures adopted for the construction are to be approved by the Society (refer to NR216 Ch 11 and NR 216 Ch 12 for applicable requirements).

WPS and WPQR are reviewed by the Project Leader, a qualified Surveyor or by a Subject Matter Expert assigned by the NC Manager. WPS and WPQR approved by others IACS class societies may be accepted by Recognised Organisation (RO) after verification of compliance with applicable IACS UR W28 rev2 requirements, and the WPS will be stamped (Recognised Organisation (RO) round rubber stamp described on the general administrative instructions) with remark “accepted” and signed and dated. A copy of the WPQR approved by the other IACS class society is to be mandatory attached to the WPS and kept in the ship’s files (a refusal from the Shipyard to allow Surveyor to take a copy of the WPQR is to be recorded). A copy of WPQT when approved by Recognised Organisation (RO) is also to be available to Surveyor, if necessary.

The “reviewed” list of WPS with their application on the welding plan is to be available in VPM (SAY > Tree > Project Procedures and Test Plans > WPS > Survey), to confirm each welding detail is covered by a WPS (including for piping). The detailed WPS and WPQR do not need to be uploaded unless allowed by the shipyard but can be stored in local files and shall be available to the Surveyors for reference.

(BPS) Lamination process details replace WPS for composite construction as per NR546 Sec. 12 [5.1.2].

NDT Plans and Records

NDT Service Suppliers

IACS UR W35 apply

Remark: In case of non-destructive testing carried out by an independent company from the shipyard, such company must comply with the requirement set out in NR669 ‘Recognition of non-destructive testing suppliers’ (NR 467 Pt B, Ch. 13, Sec 3.1.4) and UR W35

NDT Plans

The extent and method of testing, and number of checkpoints are normally agreed between shipyard and the Classification society, with due reference to:

  • Pt B, Ch 13, Sec 4 Non-Destructive Testing, [5] General plan of testing and App 2 Special structural details

NDE plans are reviewed by the Project Leader, a qualified Surveyor or by a Subject Matter Expert assigned by the NC Manager. For each construction, the plan is to specify the areas to be examined, the extent of testing and the quality levels, with reference to the NDT procedures to be used. Such written procedures are to contain appropriate details about the applied codes or standards, testing method, equipment, calibration, testing conditions and personnel qualification. For each NDT technique, appropriate details mean typically the details described in NR467, Pt. B, Ch.13 and NR216, Ch.14.

Minimum requirements on methods and quality levels to be adopted for NDT testing are also given in UR W33 and UR W34.

The NDT Plans as “reviewed” are to be available in VPM (SAY > Tree > Project Procedures and Test Plans > NDT plan > Survey)

The Project Leader Delegate or the qualified Surveyor attending the project at a shipyard location where a significant part of the hull is built must review those NDT plans.

NDT Records

The Shipbuilder is to ensure that report (see 6.9) is made available to the Surveyor for the:

  • Review of NDT records (PT and MT) as per NR540 table 2 item 1.4

  • Verification of NDT and ANDT records (UT, PAUT, TOFT, RT-D) as per NR540 table 2 item 1.5

  • Systematic review of Radiography as per NR540 table 2 item 1.5

The record of review of radiographs carried out by the surveyor is to be available in VPM. The follow-up that all NDT checkpoints agreed in NDT Plan as well as extended and additional areas requested during survey were carried out satisfactorily is also to be recorded in VPM.

The review of the NDT records of the welds on underwater shell plating has to be done before launching.

Testing Procedures of Watertight Compartments

Tank Test Plan is “reviewed” against NR467, Part B, Ch 13, Sec 6 (IACS UR S14) otherwise specifically instructed by the Flag Administration. (Refer to the related survey procedure - Countries and Flag Administration publication such as Marine Notice).

The plan of tank testing (category H24) could be reviewed by LPO and confirmed by PL or reviewed by PL only.

The follow up and records of the tank tests is made through VPM > SAY tree > Structure, Stability and Outfitting > Watertight compartments

COMF and URN Notations

COMF and URN Notations measurement programs and reports are reviewed by a qualified Surveyor or by a Subject Matter Expert assigned by the NC Manager and recorded in VPM with a dedicated survey.

Asbestos free declaration

(Reference to SOLAS II-1/3-5, UI_SC249 / Rec.130) The following reviews / surveys are to be recorded:

  • Verification that the Shipyard has established written procedures for purchasing and controlling the supply of asbestos free material, equipment and components; and Asbestos free declaration by manufacturer / supplier.

  • Random verification that material, equipment and components are supplied with asbestos free declaration.

  • Review of Shipyard asbestos free declaration and relevant supporting documentation

ATTENTION: refer to the related survey procedure Country for specific flag requirement

Inventory of Hazardous Materials (IHM) inventory Part I

The IHM Part I submitted for a newbuilding project shall be reviewed by an IHM-qualified Surveyor designated by the NC Manager or the Project Leader.

The review shall include, as applicable:

  • verification by sampling of the information recorded in the IHM Part I;

  • verification by sampling, during onboard surveys, of the location and identification of listed equipment, systems and areas; and

  • confirmation that the inventory has been developed in accordance with the applicable statutory requirements.

The review and associated survey activities shall be recorded in VPM in accordance with statutory survey reporting requirements.

Upon satisfactory completion of the review, the IHM Part I may be endorsed with the statement:

“Reviewed for consistency”.

Applicable Requirements

The Project Leader and assigned Surveyor shall verify compliance with the requirements applicable to the ship's intended certification, including:

  1. EU Ship Recycling Regulation (EU SRR)

    • applicable provisions of Regulation (EU) No. 1257/2013, as amended;

    • EMSA Best Practice Guidance on the Inventory of Hazardous Materials;

    • the ship recycling procedure and its associated annexes.

  2. Hong Kong International Convention (HKC)

    • IMO Guidelines for the Development of the Inventory of Hazardous Materials (MEPC.379(80));

    • IMO Guidelines for Survey and Certification under the Hong Kong Convention (MEPC.222(64)); with particular attention to paragraph 3.1.1. applicable to new ships;

    • the ship recycling procedure and its associated annexes.

Cable Transit Seal Systems Register

The shipbuilder is to provide a Cable Transit Seal Systems Register covering all watertight cable transits installed on the vessel or MOU. The Register may be maintained in hard-copy or electronic format and is to include:

  • Identification of each cable transit;

  • Applicable manufacturer documentation;

  • Relevant Type Approval certificates;

  • Installation drawings;

  • As-built records following final shipyard inspection; and

  • Records of inspections, modifications, repairs, maintenance, and surveys.

The attending Surveyor is to review the Register to confirm that it identifies all watertight cable transits, contains the relevant technical documentation, and provides for the maintenance of in-service records.

During new construction surveys, it is to be verified that cable transits are installed in accordance with the manufacturer's instructions and the applicable Type Approval requirements.

Computer Base Systems

During the final integration phase, the Surveyor at Yard verifies the installation, integration, testing, and operational performance of Class-related systems and their interfaces through SAT, integrated system tests, and sea trials, ensuring compliance with approved documentation, Classification Rules, and applicable statutory requirements.

Record of Inspection at Works of Materials and Equipment

Continuous follow-up and verification

The Project Leader is responsible for continuous follow-up and verification that the corresponding materials and equipment listed in rule note NR 266 are supplied with the inspection at works certificates.

  • The follow up of the materials and equipment to be supplied with the inspection at works certification is to be recorded (use template provided in Material and equipment).

  • When necessary, follow up of LPO/RO comments when carryover from FAT to SAT test / verification.

  • When the “inspection at works” certificates are not provided, but the Society deems that the procedure for the assignment of the classification is acceptable, construction mark (dot) may be assigned to the relevant part of the ship. Acceptance is based on builder's responsibility that those materials and equipment meet the Rules requirements and that, if required, they have been subject to appraisal of their design by Recognised Organisation (RO). The documentation received and accepted is to be kept in Ship’s file (VPM).

EU Mutual Recognition Type Approval

Where the NC surveyor ascertains by inspection or otherwise that the product or component covered by the EU MR type approval certificate is not in compliance with its certificate, the NC surveyor must inform the shipyard (and/or manufacturer) of the case. The NC surveyor must inform his NC manager who will liaise with DO_NCM and DO-EMC about the case to receive further guidance. (Refer to the related procedure)

Record of Marine Statutory Equipment

European Directive 96/98 EC (MED) as amended and 2014/90/EU (NEW MED)

Statutory surveys - General Section 8 and the related survey procedure Country for specific requirement

The follow-up of MED equipment is to be recorded - use template provided in Statutory equipment

UK Marine Equipment

From 1 January 2023, marine equipment must be UK approved in order to be placed on board UK ships.

See the related survey procedure UK and flag instructions (Marine notices)

Canada

Contact Recognised Organisation (RO) Canada for specific requirement and instruction from Transport Canada

See the related survey procedure Canada

France

For construction outside France contact DO_NCM for instructions

See the related survey procedure France

Other Countries - Non EU

Refer to the related survey procedure - Country

Observations and Non-conformities

Follow-up from Design review

Observations on reviewed drawings which require a Shipyard action will be identified, recorded and discussed with the Shipyard. The result of such meeting will be recorded in quality meeting in VPM. The Project Leader will ensure that, when necessary, the revised documentation and drawings are submitted by the yard for review and closed or dealt with before relevant survey. (Refer to Follow-up with LPO for LPO or NCM support)

  • To be resubmitted comments: means the manufacturer or the shipbuilder should reply to the issued comments to the satisfaction of the Plan Approval Office, without which the survey at works or the survey at yard cannot be completed.

  • To be dealt with comments: means the manufacturer or shipbuilder should reply to the issued comments to the satisfaction of the attending Surveyor at works or at yard.

    • Comment inherited from the leadership: An inherited comment is a ‘to be dealt with’ made on a drawing of the leadership project. They are meant to be dealt with the same way as any other comment on the sister ship.

Record and Follow-up from Survey at Yard

Significant deviations observed during scheduled or unscheduled inspections, are to be notified to the shipyard using the comment sheet generated by VPM and any equivalent form used by the Shipyard. The follow up of these findings shall be fully documented using VPM. Refer to VPM user manual and training documentation.

Minor remarks will be mentioned on the survey records issued by the shipbuilder/ shipyard for further follow-up. Requests for survey and records will be filed and kept in VPM.

Record of Survey

A Survey Logbook will be established during the construction of each ship or unit to allow the transmission of information to all involved surveyors on a day-by-day basis and record the scheduled and patrol surveys performed and comments raised by the surveyors during the construction.

The use of VPM is compulsory: The SAY Tree is the frame of the VPM logbook. The surveys are created in the appropriate location, the result recorded and followed up.

In VPM SAY tree was set up to support the PL/Surveyor to provide traceability of survey. The primary structure of the tree including intervention level is not to be modified. For specific needs DO_NCM to be contacted.

Hand-over process between Recognised Organisation (RO) Construction sites

General

When a project is constructed partially in different countries / locations, a hand-over dossier need to be prepared by PLD in-charge before arrival of vessel (or her parts) to integration yard. This dossier is to consist of:

  • Mandatory VPM entries for quality management process (refer to “Recognised Organisation (RO) record of construction” / “Recognised Organisation (RO) Records to be made available in VPM”) – relevant quality standards, welders periodical review reports, NDT specialists annual qualification review reports etc. for each assembly yard involved. Where shipyard construction facilities review report is not available in SRM tool, a copy of the report to be attached to Recognised Organisation (RO) Documents section;

  • Mandatory VPM entries for survey at yard scope. Where surveys are completed, raised comments are closed and no activity is expected at integration yard – survey status to be turned “Completed”. When all surveys within intervention are completed, the intervention status to be turned “Done”;

  • Cumulative NDT follow-up record;

  • Material and equipment continuous follow up record (to upload to Recognised Organisation (RO) Documents section);

  • Cumulative record of pipe workshop pressure tests;

  • Record of local modifications and repairs approved (to upload to Recognised Organisation (RO) Documents section).

  • Quality meetings, relevant communications regarding local agreement affecting classification scope.

Hand-over statement from PLD to PL with brief explanation of works performed and outstanding tasks listed. This statement is to be uploaded to Recognised Organisation (RO) Documents section and e-mail notification is to be sent to PL to trigger his/her attention. The statement can be prepared in free form. An example ANNEX A9 (A9.1) template may be used by PLD for this purpose.

Offshore Units Transit conditions

A Case-by-case procedure will be establish depending on the nature of the unit, the stage of construction and the transit conditions. (For Offshore project refer also to the related procedure).

In any case a detail “Punch List” is to be prepared according to the pending comments on the design review and Survey at yard. Completed or pending commissioning items shall be identified with reference to the approved tests procedures. All pending items shall be reflected in the punch list with related comment number, type and statutory requirement reference if applicable. Then the same pending items is to be reflected in the relevant statutory check list. Such punch list may replace the NRS. Responsibilities in Punch List closure is to be defined and agreed by all interested parties before units’ departure.

Ship's Delivery preparation

Shipbuilder / Shipyard reminder

Progress / Quality meeting

Before key milestone the Project Leader will send reminder to the shipbuilder / shipyard for the outstanding points as follows:

  1. Drawings not submitted for review (the list of required drawings being previously verified with the concerned LPO;

  2. Outstanding observations on reviewed documents and nonconformities;

  3. Inspection at works certificates not received, or with outstanding;

  4. Survey to be performed or completed (before the milestone / delivery);

  5. Outstanding comments raised during the Unscheduled / Scheduled inspections and Sea Trials;

  6. Statutory surveys status, as applicable.

The follow-up of the outstanding points is to be done preferably through a progress / quality meeting to keep records of the agreed action plan and person in charge.

Providing the design review comments “to be resubmitted” & “to be dealt with”, the design categories for “missing drawings” and the “Survey at Yard” comments are regularly and properly followed-up in VPM, the sending of the reminder through VPM (NRS > Current NRS status > Export outstanding items) will be of added value to support the progress / quality meeting with the shipbuilder / shipyard.

The goal is to be able to close, as far as possible, for the Hull part design categories and survey comments before launching, and similarly for outfitting part (Machinery, Electricity & Automation, Cargo) and class / statutory part (Fire & Safety, Stability) before the sea trials. So that preferably, for the last reminder before delivery will only remain the sea trials outstanding comments.

Or, to identify at an early stage if exemption will be needed or short term statutory certificate issued in order to contact (via MOC) the flag administration.

Reminder before delivery

The reminder before delivery, with a similar agenda, will be given with sufficient notice for the Shipbuilder to complete the a.m. outstanding points in time, through VPM.

Closing of Design Categories

It is expected that three months before scheduled delivery LPO surveyors have closed the design review categories. As part of the follow-up with LPO Project Leader shall also send a reminder to LPO in charge to confirm the date of delivery and follow-up the categories status, and to prepare the reminder to shipyard. This follow-up is to be regular until NRS is to be sent in case of outstanding. DO_NCM is to be called for support in case of difficulties.

Notified Remarks Status (NRS)

General

A “Notified Remark Status” is issued through VPM, by the NC project Leader before issuing any Classification & Statutory certificates, confirming that:

  • Adequate documentation related to Design review has been submitted and reviewed satisfactorily (After written confirmation from LPO),

  • Adequate documentation related to inspection at Works of Materials and Equipment was verified satisfactorily

  • All comments raised during the construction have been dealt with to the surveyor’s satisfaction.

If any minor outstanding point remains, an agreed solution between Shipbuilder, Owner, Project Leader shall be specified for follow-up after delivery (i.e through Memoranda, Condition of Class).

NRS preparation

The following is detailing the steps to prepare NRS:

  • Design review categories

    • Open categories: All categories must be closed by LPO in charge

    • Closed categories with missing or no drawings: An agreed solution with designer, shipbuilder / shipyard, ship-owner and flag administration if concerned, must be written and transmitted to NRS

  • Design review Pending comments:

    • ‘To be resubmitted’: in principle NO ‘to be resubmitted’ comment shall remain open

      The option ‘cleared-transmitted to NRS’ shall be an exception, accepted on case-by-case basis, with a clear agreed solution with the designer, shipbuilder / shipyard, ship-owner and flag administration if concerned

      In case of series of ships when a ‘to be resubmitted’ is ‘sent to NRS’ for the leadership, the same comment shall be reopened in VPM by LPO until the agreed solution has been fulfilled to the satisfaction of the LPO. In such cases, the agreement must be sufficiently documented and promptly recorded in VPM and NCM shall be informed in addition to MOC(NC).

    • ‘To be dealt with’: the agreed solution shall be described with clear information for follow-up. ‘To be dealt with’ comments are “inherited” to all ship of the series (pure or quasi sister ship).

  • Product certification Outstanding documentation (i.e. missing certificates):

  • Product certification Pending comments:

    • Any pending comment from inspection at work, if not solved during survey at yard, must be described and solution agreed found with interested parties for follow-up.

  • Survey at yard Pending comments:

    • Any pending non-conformities must be described and solution agreed with shipbuilder / shipyard, ship-owner and flag administration if concerned, for follow-up

  • Survey at yard Missing / Outstanding Survey:

    • Required survey (Class / Statutory) partially completed or not performed shall be identified and solution agreed with shipbuilder / shipyard, ship-owner and flag administration if concerned, for follow-up.

Statutory survey outstanding

For statutory, if any outstanding remain leading to issuance of a short-term certificate the Flag Administration agreement shall obtain through the MOC(NC) and this to be documented and recorded in VPM

There should be consistency between the Initial survey report (Statutory checklist), The NRS agreed solution, the record in NPSS when exemption is accepted and the certificates issued including the reports and records associated.

Condition for NRS to be “Submitted” for validation and “transmitted”

The NRS will be processed using VPM for submission for validation by NC Manager and transmission to MOC(NC) after validation providing:

  • All actual dates were entered except the delivery date (See VPM “calendar” tab)

  • All initial statutory survey reports (statutory check lists) were transmitted (See “progress > Statutory checklists” tab)

  • All design categories were closed (to be checked with LPO) (See “NRS > Design review > Categories open” tab)

  • All design categories closed with no or missing drawing has agreed solution (See “NRS > Design review > Categories closed” tab)

  • All comments were cleared or transferred to NRS (See “Pending Comments” tab under “NRS > Design review / Product Certification / Survey at Yard”) with agreed solution

  • All RO documentation / certificate required were received and validated (declaration by the Project Leader “NRS > Product certification > Outstanding Documentation” tab

DO_NCM support

Project Leader / NC Manager should consult NCM on the drafting of agreed solutions, in case the number of outstanding is anticipated to be such that NRS could not be sent electronically and if any outstanding statutory items. (Before using the form provided in Notified Remarks Status (Paper form))

Ship Construction File (SCF)

The purpose of the documents held in the Ship Construction file on board the ship is to facilitate inspection (survey) and maintenance of the ship.

The Project Leader is to confirm with the shipbuilder that the documents of the Ship Construction file, as required by Recognised Organisation (RO) Rules, Pt. A, Ch. 3, Sec. 7, have been delivered to the ship.

SCF for all ships, except those subject to GBS construction standards

Refer to NR 467 Pt. A, Ch 3, Sec 7 [3.1].

SCF for ship subject to GBS construction standards

Refer to NR 467 Pt. A, Ch. 3, Sec 7 [3.2] and in particular [3.2.10 to 3.2.12]

Reports or Records, Certificates and Documents to be issued by Project Leader, NC Survey Centre.

(see Project leader office main tasks and Distribution of documents issued)

Milestone dates before delivery

Forecast shall be followed-up and actual dates shall be recorded in VPM timely.

Steel cutting date

Start of lamination will be used for composite project.

Keel laying date

This date triggers the applicability of most of statutory regulations. The shift in the schedule is to be follow-up carefully. In case of long delay between keel laying and delivery, check for specific flag requirement.

Launching date

A pre-launching check list is available in Hand-over and launching checklistA9-2 for the use of Project Leader / Surveyors

A Launching report (AdME 112) is automatically generated by VPM on the actual launching day, which will be sent to MOC (NC) and MO automatically through electronic transmission via VPM.

Sea trial date

The last sea trial date is to be recorded.

Surveyor(s) attending sea trials

The names of the surveyors attending the sea trials and gas trials must be recorded in VPM.

Contract “Frozen / Unfrozen” dates

The date when the project construction is “Frozen”, and date the project construction is re-started need to be input in VPM Project data.

Notified Remarks Status (NRS)

NRS shall be validated in VPM by the NC Manager and transmitted through VPM to the MOC(NC) before the issuance of any Class/Statutory certificates.

The date of transmission is recorded in ‘VPM > Calendar’ with a copy of the document made available to MOC(NC).

Delivery date

Forecast and actual date must be recorded in VPM.

The follow-up by Project Leader and NC Manager of the forecast delivery date is compulsory and monitored by DO_NCM and is one of the NC KPI. Some new statutory regulation or flag requirement may enter in force due to long delay from the original contractual date.

The Actual delivery date registered in VPM Calendar shall normally, match the date of issuance of certificates recorded in NPSS.

ATTENTION: DO NOT ENTER A DATE UNLESS DELIVERY (Builder to Buyer) IS CONFIRMED.

Classification certificate:

Refer to the related procedure and the related survey procedure.

Provisional or definitive Classification Certificate is issued, as per RFC, after satisfactory completion of the surveys of construction and sea trials or if the outstanding items are acceptable, with the adequate condition(s) of class.

The original of the certificate is intended for the customer (subscriber of the contract).

The issuance date of the certificate shall be recorded in VPM (NPSS).

Condition for issuing a Definitive Class certificate

A definitive certificate could be issued by NC Project Leader, if:

  • Notified remark status (NRS) is transmitted, and

  • If there is no “open” outstanding item:

    • all outstanding are cleared “closed”, or

    • acceptable items ‘to be dealt with’ are with agreed solution recorded in NRS with adequate condition of Class in NPSS for follow-up in service

  • Classification conditions are signed by shipowner or ship manager for ship in service and,

  • Request for classification (RFC), including last update if any, was signed by shipbuilder for new building.

Condition for issuing a Provisional Class certificate

If there is any other acceptable outstanding a provisional certificate is to be issued by the Project Leader, in particular when:

  • Notified remark status (NRS) is issued with minor pending remarks and agreed solution not transferred into Condition(s) of Class but to be followed up by NC Project Leader (such as missing documentation at time of delivery with no impact on Class or Statutory requirement),

  • Notified remark status (NRS) with a ‘to be resubmitted’ comment “cleared - transferred to NRS” regardless of the agreed solution,

  • Notified remark status (NRS) was not issued through VPM due to the number of outstanding (like for offshore unit to be transferred to integration shipyard). The “punch list” items describe in Offshore Units Transit conditions are to be reflected in ‘Condition of Class’ and a Memoranda endorsed to clarify the condition for the release of the provisional class certificate with eventually a certificate of survey issued as per condition set in the occasional and miscellaneous surveys procedure, when the construction is to be completed elsewhere.

  • The ship is delivered with a notation other than unrestricted navigation, for a voyage by her own propulsion, to bring the ship from a shipyard, when the yard is not located in the operational area (See condition in the occasional and miscellaneous surveys procedure for issuance of a certificate of survey)

  • Classification conditions are not signed by shipowner or ship manager. DO_NCM to be consulted before issuance of the certificate.

Survey Systems for Class Renewal Survey:

The surveys scheme is chosen as per specific Owner request, through Owner CD.

Continuous Survey System (CS)

Refer to NR467, Part A, Ch. 2, Sec 2 [4.3.5]

NC Project Leader will draft a CSM (and CSR, if applicable) list at new building stage, at least for reference to support CD.

Planned Maintenance System for machinery (PMS)

PMS notation cannot be granted at NC stage and is to be dealt with by Owner CD.

Statutory certificates:

Refer to the related procedure, Statutory surveys - General, Survey, certification and reporting and the related survey procedure - Flag

Interim or short term issued certificates (and the additional descriptive forms) as specified in the contract will be delivered to the customer after completion of the surveys carried out according to the concerned International and/or National Regulations and applicable Flag and TNS instructions.

Issuance date of the certificates, type (Interim / short term) and expiry date shall be recorded in NPSS.

ATTENTION: No Statutory certificate is to be issued before the issuance of the Certificate of Registry from the Flag administration.

Issuance of Interim statutory certificates

After satisfactory completion of the initial surveys the Project Leader will issue Interim statutory certificates with a limited validity of 5 months. The issuance of the full term is to be done by the MOC (NC).

There should be no recommendation linked to an interim certificate unless Flag agreement.

Issuance of short-term certificates

When the initial survey is not satisfactorily completed the issuance of a “short term” certificate may be contemplated. Short term certificates cannot be issued without MOC (NC) agreement and as per the Flag administration instructions.

Such case is addressed on a case-by-case basis as an exceptional measure and does not stay as a rule. The general rule is that no recommendation remains upon completion of any Statutory survey.

Exemptions

Refer to Statutory surveys - General [1.3]

The Project Leader will liaise with the Plan Approval and the MOC (NC) in charge to follow-up the status of the exemption request, and that the application is timely send and the reply received with sufficient time before issuance of the related certificate. Statutory checklist (Initial statutory survey report) is filled up indicating the exemption, the NRS also, if necessary to close a comment.

The issuance date of the exemption as well as reference and details shall be recorded in NPSS:

  • In Statutory certificates > Type > Add exemption: the details of the exemption as granted by the flag

  • In Class certificate > Add memorandum: the deviation from the rules accepted based on flag exemption.

The issuance of an exemption either by Recognised Organisation (RO) if delegated or by the Administration is to be indicated on the correspondent Statutory certificate, in the NRS and initial statutory survey report (check list), as relevant.

A copy of the exemption certificate when issued by the administration is to be available in VPM

NPSS and Survey statement for statutory and other surveys:

NPSS (Neptune Provisional Survey Statement / ASMS system) is issued through VPM.

The ‘Delivery Statement’ generated through VPM (based on NPSS input) is part of the deliverable together with the class and statutory certificates as being the only documents listing the condition of class, the statutory recommendation and the memoranda to the attention of the shipbuilder and Shipowner.

NPSS shall be validated in VPM by the NC Manager and promptly* submitted by the Project Leader through VPM to the MOC (NC) - (But only after delivery is confirmed, see New Construction survey reports:)

Miscellaneous attestations:

Attestations to be issued to the Shipbuilder and/or to the Owner as required using model available in ASMS 2 certificate.

For model not available contact NCM or MOC (NC).

For attestation of non-presence of Asbestos and related requirements, refer to the corresponding Circulars/ Notes available in the Marine Reference Libraries in Recognised Organisation (RO) IT tools.

The sign scan copy of issued attestation shall be uploaded in VPM (SAY > Recognised Organisation (RO) Documents) for records.

Classification conditions:

(Ad 524) to be completed and signed by the Owner or his representative at the takeover of the ship.

After it is signed the original paper is to be transmitted to HO FM_REG for records (the related procedure).

A scan copy of the signed Classification conditions (Ad 524) shall be uploaded in Genesis Classification report (CR).

New Construction survey reports:

The new construction survey reports consist of:

  • The Classification report completed in Genesis with the applicable annexes.

  • The Recognised Organisation (RO) records of construction, The VPM required entries and documentations.

ATTENTION: After delivery and submission of the NPSS, VPM system will revoke automatically access for the SAY user (project leader and surveyor at yard). The NC Manager will be able to assign after this revocation a Project Leader - Documentation. This access is granted for six (6) weeks in order to allow completion of the Recognised Organisation (RO) record of construction by the project leader and or his delegate. Access to e-drawings (leadership included), uploading of documents to finalize the Recognised Organisation (RO) record of construction is permitted. No Survey could be entered nor modification on survey reports. NRS will be locked.

Statutory survey reports:

Reminder: The report of Initial Statutory Surveys at New construction, in particular for convention size ships must provide through records, check lists, inspection and test records, etc. evidence that the surveys have complied with each requirement (as applicable). This instruction applies also to additional specific flag requirement.

Untitled

The scheme of VPM survey reports is now based on Resolution A.1186(33) “Survey Guidelines under the Harmonized System of Survey and Certification (HSSC), 2023”

The statutory survey records relevant to the statutory certificates to be issued, and the initial survey reports are prepared following relevant check lists generated in VPM but also TNS, TNC and specific flag instructions (i.e. additional flag requirements). Several records, available within ASMS 2 Certificate Initial Records and / or another controlled format, are provided as reference to applicable provisions of the Convention and intended to be placed on board the ships at the first survey.

All statutory surveys shall be recorded in VPM and linked to the relevant check list item. This is to allow after completion of the surveys, the Statutory check lists be re-issued as an initial survey report, downloaded to the Recognised Organisation (RO) record of construction SAY folder and transmitted through VPM before NRS.

Untitled

Documents such as survey reports, records, flag or MOC instructions, exemptions, details / justifications on the remarks should also be attached, if necessary, in the same folder as the check list in the Recognised Organisation (RO) record of construction. (However, preferably is to be part of the relevant Survey in the SAY Tree)

Untitled

Attention to Safety Radio performed with the support of an approved service supplier (Safety Radio) The scan copy of the periodical survey report for issuance of safety radio certificate endorsed by the surveyor with the attached documents provided by the Radio Specialist is to be recorded in VPM (SAY Tree > Radio Installation System > Safety Radio Survey).

The template for the Initial Survey Report for issuance of Ship Safety Radio Certificate is available in Guidelines check lists for statutory survey (A11.5)

Documents handed over to Shipbuilder

The Project Leader will list all documents handed over to the Subscriber of the contract (Shipbuilder) at delivery of the unit. One copy of this list is to be countersigned by the Shipbuilder for acknowledgement receipt and uploaded in VPM.

Certificates and documents to be sent to the MOC (NC) at ship's delivery :

REMINDER: already sent before ship’s delivery are:

  • Statutory check lists (Initial Statutory survey reports) sent through VPM (Attention: to be transmitted after completion of survey and before NRS)

  • NRS sent through VPM (Attention: to be submitted after validation)

ADDITIONALLY TO BE SENT: at ship’s delivery

  • Classification Certificate sent through ASMS2.

  • Statutory certificates and records sent through ASMS2.

  • Survey statement NPSS and delivery statement sent through VPM (Attention: to be submitted after validation).

Information and Statutory survey reports (as required in TNS instructions) shall be completed and forwarded for subsequent processing without delay to the MOC (NC) after the delivery. Electronic transmission through VPM (to be submitted) or ASMS2.

The NC Survey Classification Report is to be completed and sent to the MOC (NC) within six (6) weeks after the delivery. Electronic transmission through Genesis.

Recognised Organisation (RO) record of construction

The Recognised Organisation (RO) record of construction is developed in Recognised Organisation (RO) Record of construction A2.1

Referring to Recognised Organisation (RO) Record of Construction The Recognised Organisation (RO) record of construction will include: Contractual documents; list of applicable rules and requirements; list of approved drawings and follow-up; list of material and equipment certification and follow-up; list of applicable shipyard fabrication standards and procedures; list of testing procedures; survey and testing program; request for survey, survey log book; the construction and all necessary inspections, tests and qualification tests that are to be made under the Surveyor’s satisfaction and the records, check lists, inspection and test records, etc. that prove Surveyors have complied with the requirement of the new building survey planning; the main correspondence; records, reports, certificates and attestation issued at delivery.

Records to be made available in VPM

Recapitulation of documents and survey reports including review of procedures required to be available in VPM is developed in Recognised Organisation (RO) Record of construction (see also Project leader office main tasks)

Project information

See Annex A2.2 - 1

Survey Team

See Annex A2.2 - 2

Recognised Organisation (RO) record of construction

See Annex A2.2 - 3

Survey Logbook

All survey at yard including document review by Project Leader and Surveyor shall be recorded in VPM:

  • Record of surveys, including Patrol surveys

  • Follow-up and closing evidence through survey records of design review comments

  • Follow-up of material and equipment inspection at work certificates or MED

  • Details and follow-up of the survey findings

  • Statutory Surveys shall be recorded and properly linked to the relevant check list items including patrol, monitoring, documents review and survey not included in shipyard inspection plan but necessary to confirm information to be recorded in statutory reports / records.

Records followed by Outstanding “Cx” in VPM Dashboard

The following Items will trigger a warning in the VPM Dashboard when there is outstanding such as document missing, date missing or overdue, action not taken but required in this procedure.

  • C1: Generation of Statutory Check Lists

  • C2: Check List not updated after modification of RFC

  • C3: Milestone Forecast date missing

  • C4: Milestone Forecast date passed and actual date missing

  • C5: Steel Cutting* within 15 days or started and Surveyor not assigned

  • C6: Steel Cutting* within 5 days or started and Kick-off meeting not registered

  • C7: Kick-off meeting held more than 15 days ago and relevant documents not attached

  • C8: Review of Welding** procedures and WPQR not recorded

  • C9: Review of NDT plan*** not recorded

  • C10: Delivery within 15 days and Statutory Survey checklist (initial survey report) not transmitted to the Ship’s file (Warning - to be taking care of before NRS could be send)

  • C11: Sea trial within 5 days or carried out and attending Surveyor not identified

  • C12: Shipbuilder review record is missing or should be validated

  • C13: Indication on% of cleared comments on drawing (For Information)

  • C14: Shipbuilder reminders of outstanding items to be sent within 15 days before milestone dates, launching, sea trial, delivery

  • C15: NRS has not been sent and delivery is within 15 days (Warning - to be taking care of before delivery of class / statutory certificates and NPSS)

  • C16: Patrol plan has not been recorded

  • C17: SCF Version is not received or reviewed and delivery is within 15 days

  • PSG Nb.: Number of Patrol survey recorded for general items

  • PSW Nb: Number of Patrol survey recorded for Welding items

Internal Distribution of Documents and Filing

The distribution of documents is indicated in Distribution of documents issued

SURVEYS

General

Before starting the surveys, the Project Leader shall verify that the necessary documentation i.e. applicable rules, regulations, instructions and contractual documents is available to the surveyors.

Each survey is to be carried out by a surveyor holding the corresponding certification as per the new construction surveyor certification scheme requirements.

As a rule, attendance of surveyors for survey shall start with a formal question put to the shipyard lead personnel present when the attendance takes place. The question is whether there is anything they have to declare to the surveyor such as defects, failures or anomalies of any kind. The question, the answer and the name of the respondent are to be recorded in the ship's survey logbook. In VPM Survey logbook the following sentence is already printed: “No anomaly declared by the yard representative” after which the name of the representative is to be recorded.

The construction or conversion survey of a ship or an offshore floating unit is carried out to record the conformity with Recognised Organisation (RO) Rules and/or concerned Statutory Regulations by means of:

  • Reviews of the Shipyard fabrication documents as required by the Rules

  • Verification, if required, of materials and equipment certification

  • Verification that scantlings, construction and installation meet satisfactorily the Rules and/or the concerned Statutory Regulations requirements aspects of the examined drawings, documents and reviewed fabrication documents

  • Witnessing the tests and trials stipulated by the Rules and as per approved testing procedures and plans.

The Surveyor does not act in lieu of the Quality control department of the Yard.

Proof of consistency of surveys

Reminder: The classification society is to be able to provide evidence, e.g. through records, check lists, inspection and test records, etc. that its surveyors have complied with the requirements of the new building survey planning and duly participated in the relevant activities shown in the shipbuilder’s examination and test plans.

In addition, the classification society is to maintain records of deficiencies found during the patrolling activities required in Kick off Meeting table 1. The records shall include the date when deficiency was found, description of the deficiency and the date the deficiency was closed

Scheduled inspections

The Recognised Organisation (RO) surveyor will attend on call inspections according to the programme agreed on during the preliminary meeting (Kick-off meeting) and defined as follows:

  1. Witness point surveys: the next step may be processed only after the item inspected is approved by the surveyor.

  2. Notified point surveys: the Shipyard is to call the Surveyor for attendance, but this attendance may be waived by the surveyor and dealt with under a Monitoring survey scheme.

  3. Review of documents: where the Shipyard may proceed with the inspection, and relevant records and/or certificates are to be provided to the surveyor.

The survey and or review performed shall be recorded in the survey logbook provided in VPM new intervention tree (SAY > Tree view, Interventions, Surveys)

Any significant outstanding shall be recorded as comment for proper follow-up (SAY > Surveys > Comments)

For the notified point survey, when the survey is not attended, the Surveyor is to review yard inspection records and set up appropriate monitoring to satisfy himself that the construction and installation meet acceptable standards and the rules requirements. This monitoring can be supplemented by the Patrol plan.

Patrol or Unscheduled inspections

The Recognised Organisation (RO) surveyor shall perform unscheduled inspections at any time during the construction including those indicated in the K.O meeting template table and the Patrol Plan Patrol Plan. The Shipyard once informed has to give the surveyor free access on-board and to the concerned workshops and to provide personnel to accompany the surveyor as he deems appropriate. Any refusal to do so is to be recorded.

The Patrol performed shall be recorded in VPM Survey logbook using the tree as setup (> PATROL, PS0X) to allow follow-up of the KPI through the dashboard and export the data.

Any significant deficiency found shall be recorded as a comment for proper follow-up (SAY > Surveys > _PATROL > Comments). The record shall be dated and with sufficient information, photo to clearly identify the defect and its location.

Record of surveys

The use of VPM is compulsory

All involved Surveyors on a day-to-day basis will record the scheduled and patrol surveys performed and comments raised during the construction. The records may partly consist of the written requests for survey and/or the survey report sheets received from the shipyard with dated handwritten comments, if necessary, that will be scanned and uploaded. Commented photos taken on the spot are also suitable evidence to highlight deficiency details and location.

VPM for SAY is a mobile application set to facilitate the Surveyor reporting, The use of tablet with online access to VPM is also a good support. Surveyor shall be trained for the use of those reporting tools.

Documentation to be available for the Surveyor during construction

The list of documents to be made available for the Surveyor is listed in various part of Recognised Organisation (RO) Rules and recalled for the most common items (not exhaustive) in this procedure, such as:

  • Note to surveyor, when deemed necessary by the project leader

  • Plan and supporting documents required in NR467 Pt A, Ch 2, Sec 1 [2.3]. Normally available in VPM after review by Plan Approval, or PL when authorized. Reference to (not exhaustive list):

    • NR467 Pt A, Ch3, Sec 7; NR 540;

    • NR467 Pt B, Ch13 and in particular Sec 4 (URW35), Sec 6(SOLAS Ch II-1 reg 11 & URS14);

    • NR467 Pt C, Ch1, Sec 18 & Ch2, Sec 15 & Ch3, Sec 6;

    • NR467 Pt F, Ch3, Sec 1;

    • Other relevant part of applicable NR depending on ship’s type and notations.

  • The applicable fabrication standards and procedures listed in the Recognised Organisation (RO) record of construction;

  • The testing procedures;

  • The applicable documents, requirements, rules and regulations;

  • The Survey logbook.

Particular construction Survey / Patrol

Verification of welders and NDT operators certification and calibration of testing equipment

Periodical verifications of the shipbuilder/shipyard and significant subcontractor certification system of welders at intervals not exceeding six months (refer to UR W32) and NDT operator’s certification at intervals not exceeding one year (refer to UR W33 and W34) will be recorded in VPM by the surveyor. This verification is based on shipyard overall records review and sampling to confirm the system is effective.

The validity of the calibration of the testing equipment will be checked before each test and recorded or the calibration validity of the shipbuilder/shipyard testing equipment will be verified and recorded at intervals not exceeding one year. The record of this verification is to be available in VPM (SAY > Survey tree > Shipbuilder fabrication standards/NDT procedures as appropriate)

For non-destructive testing carried out by supplier, qualification of operators has to comply with the requirements set out in IACS UR W35 as amended and when applicable NR669 “Recognition of non-destructive testing suppliers”. The record of this verification is to be available in VPM (Survey tree > NDT Procedures)

Unscheduled inspections consisting in checking at random some welders currently working on the project, supervised and then verifying at yard department that they are duly certified for the type of work they are currently doing are to be carried out and recorded (_PATROL > _PS01)

Materials and equipment identification

The Surveyor is to check that relevant materials and equipment as per NR 266 are delivered to the Shipyard with Recognised Organisation (RO) certificates, and that their identification marks (including Recognised Organisation (RO) stamps) allow the traceability to these certificates. To that effect, the Shipyard is to submit the relevant certificates to the surveyor preferably before relevant installation survey. (Recognised Organisation (RO) COI could also be found in VPM > Product certification folder when properly located by RO)

The Project Leader evaluates and defines the adapted extent and method of this verification. The result of the verification is to be kept in the survey logbook and the record of the follow-up of inspection at works of materials and equipment certificates (COI, TAC or Work certificates as appropriate)

Scantlings and constructions surveys

The Project Leader evaluates the “Actual Scope of Work,” defining the adapted extent and method of survey for each particular newbuilding

Surveys will be carried out on the following:

  • Scantlings (to be measured and recorded by Shipyard's personnel and made available to the surveyor for random verifications during hull/blocks surveys. Normally includes thickness, main dimensions and welds size (fillet throat). Random verifications will be carried out and recorded by the surveyor)

  • Assessment through the operator's report of the NDT results and radiographic films. (X-ray or other approved methods to comply with Recognised Organisation (RO) rules and requirements. Acceptance criteria as per a recognized standard i.e. National standard, ASME, etc. NDT reports (RT, UT, etc.) are to be signed by the surveyor “for acknowledgment” the NDT operator keeps the responsibility of his report content.). The extent of testing can be extended at the surveyor’s discretion when repeated non-acceptable discontinuities are found. The Surveyor may require witnessing the testing.

  • Random verification (Patrol) of the application by the Yard of the reviewed fabrication procedures.

  • Visual examination (Witness) of the welds (as per K.O meeting template table).

  • Witness of Structural and tightness testing.

The result of such surveys is recorded in the VPM Logbook.

Survey of installation and testing on board of equipment and systems covered by the Rules

Surveys will be carried out according to the examination and testing plans agreed on with the builder as required by Recognised Organisation (RO) rules and/ or Statutory requirements. And the results of such surveys recorded in the VPM Logbook

The following information is normally to be provided for each test, as relevant:

  • scope of test

  • parameter to be recorded

Statutory surveys

General

Statutory surveys will be carried out based on the checklist provided by VPM tool and according to the relevant regulations and TNS instructions. Survey shall confirm the compliance to the regulations. Deviation shall be clearly identified and rectified before issuance of the certificate or a solution agreed with the Flag Administration.

Those survey guidelines checklist may deal with other aspects of statutory certification during new construction surveys which may not be addressed in Recognised Organisation (RO) Rules or covered by the ITP. They apply to all Convention ships unless the concerned Administration provides another interpretation or decides otherwise.

Statutory survey shall be recorded in VPM SAY > Tree view > ITP Item > Linked to statutory certificate and check list item. (See Preparation for Statutory surveys)

PSPC

For verification of PSPC implementation refer to attached instructions for implementation of PSPC(WBT) and PSPC(COT) and relevant UI_SC223 rev.3 corr1 (MSC215(82)), UI_SC227 rev.2 (MSC261(82)), UI_SC259 rev.1 corr1 (MSC288(87)). Instruction for IMO PSPC Surveys

Surveys and Patrol survey are performed by a PSPC qualified Surveyor and recorded in VPM.

IHM inventory Part I / GREENPASSPORT

Surveys are performed by an IHM qualified Surveyor only. Documents review and survey are recorded in VPM

Safety Radio

The Surveyor relies upon an approved Radio Specialist to perform the inspection of the ship’s radio equipment. The Surveyor is nevertheless responsible for the intervention. He endorses the survey report and issues the relevant certificate. Therefore, the Surveyor attends the survey. Safety Radio applies.

The result of such survey is recorded in the VPM Logbook.

Marine Statutory Equipment - European Directive 96/98 EC (MED) as amended and 2014/90/EU (NEW MED)

Requirements set in Statutory surveys - General (Section 8) are applicable.

The result of the survey is to be kept in the survey logbook and in the record of the “follow-up of inspection for MED equipment”.

Quay and sea trials

Trials

The list of statutory and class quay and sea trials (including gas trial) is to be pre-established and submitted by the builder/yard to the Project Leader, and if defined by the surveyor together with the builder/yard, it should be duly signed and endorsed by the builder/yard.

The surveyors attend the quay and sea trials as required per Rules. They decide on their attendance according to the a.m. reviewed pre-established list. The names of the surveyors attending the sea trials (including gas trials) are to be formally registered in VPM.

Main conditions of testing or trials are to be recorded. The survey performed and the sea trial comments are recorded individually in VPM Logbook. The sea trial result is to be reviewed and recorded in VPM.

Inspection of machinery after sea trials, as deemed necessary, are to be witnessed or monitored by the surveyor and an exhaustive inspection report submitted.

COMF and URN measurements

The measurement for the comfort notations is performed during sea trial by an acoustic and vibration specialist from an approved service supplier. A qualified surveyor attends the sea trial.

The measurement for the URN Notations is performed by an acoustic specialist from an external company. This Company shall have obtained relevant delegation from the Society. A qualified surveyor attends the sea trial. The results of such surveys are recorded in the VPM Logbook.

Survey before reactivation of a “Frozen” contract

Before reactivating a project and restarting the construction survey, a general examination of the Hull, Hull outfitting, Machinery and Electrical installation, Safety installation and systems is to be performed, as relevant depending on the stage of completion at the time the project construction was stopped.

A new kick of meeting is to be performed and a new survey plan prepared.

Shipyard facilities may also have to be re-assess.

Quality meetings

Quality meetings should be arranged when considered appropriate with the builder/shipyard (together with shipyard's main subcontractors when necessary)

The agenda for quality meetings may normally cover the following points (only point (a) is mandatory) as deemed necessary:

  1. declaration of the yard of any problem to be put to the surveyor's attention

  2. status of progress and quality (visual inspection of blocks, installation of equipment, tightness tests, NDT results, quay trials etc...)

  3. request for additional surveys or survey performance (survey or test to be added or modified)

  4. output of unscheduled inspections (Patrol surveys)

  5. documentation status (missing certificates for equipment / material and missing documents or procedures to be submitted by the shipyard)

  6. deficiencies and corrective actions (deficiencies found during surveys and outstanding items with respect to drawing review comments)

  7. review of punch list (review and up-dating of previously recorded deficiencies)

  8. amendment to RFC and to kick-off meeting

  9. delay of construction, temporary stop of construction (frozen), agreement for lay-up during construction and reactivation procedure.

Minutes of all quality meetings shall be recorded and followed up.

Appendix — Project leader office main tasks

Project Leader Office Main Tasks

See attached file A1-1.doc

For the distribution of documents see Annex Local new construction survey centre file

Appendix — Recognised Organisation (RO) Record of construction

Recognised Organisation (RO) Record of Construction

See attached file A2-1.doc

Records to be made available in VPM

See attached file A2-2.doc

Appendix — Notified Remarks Status (Paper form)

Notified Remarks Status to be sent using VPM

See attached file A3-1.doc for reference only - NOT TO BE USED unless agreed with DO_NCM

Appendix — Distribution of documents issued

Local new construction survey centre file

See attached file A4-1.doc

Appendix — Pure & Quasi Sisterships

Attributes of a new vessel with respect to a previous Recognised Organisation (RO) classed vessel

See attached file A5-1.pdf

Appendix — Kick-off meeting template

Kick-off meeting template for steel ship

See attached A6-1 template Excel 072021-corr1-(UL).xls

Kick-off meeting template for Hull in composite

See attached A6-2 template.xls

Kick-off meeting template for steel ship

Under development A6-3 template Excel 112026.xls

Pre-Kick-off meeting template

Under development A6-4 template.xls

Appendix — Material and equipment

Template for Material and Equipment Follow-up

See attachment A7-1

Template for Material and Equipment Follow-up (EMC version)

Attachment A7-2 (2026)

Appendix — Statutory equipment

Template for MED Statutory Equipment follow-up

See Attachment A8-1

Template for MED Statutory Equipment follow-up

Attachment A8-1(2026)

Appendix — Hand-over and launching checklist

Template of Survey Statement for hand over to completion site before delivery

See attachment A9-1

Launching checklist

See attachment A9-2

Attestation of construction survey template

See attachment A9-3 (NEW)

Appendix — Shipyard review record

Template for Shipyard review record (UR Z23)

See attachment A10-1

Template for Shipyard review record (Composite)

See attachment A10-2

NR546, Sec 12 [5.1] or certificate or recognition

Appendix — Guidelines check lists for statutory survey

A1156(32)

See attachment A11-1

DR 68

See attachment A11-2

Deleted UI SC234 LL76 MPC96

See attachments A11-3

A1186(33)

See attachment A11-4 (NEW)

Initial Survey Report for issuance of Ship Safety Radio Certificate

See attachment A11-5 (NEW)

A1206(34)

Attachment A11-6 (NEW)

Appendix — Instruction for IMO PSPC Surveys

Instruction for implementation of PSPC (WBT)

See attachment A12-1

Instruction for implementation of PSPC (COT)

See attachment A12-2

Appendix — VPM user guide

VPM refreshment

See attachment A13 (VPM presentation)

SRM user guide

See NC0051 - SAY SRR user guide in VPM documents

Appendix — USE OF STAMP BY PL/SAY

Use of Stamp

See attachment A14-1(To be used if no access to Recognised Organisation (RO) Approbat)

Recognised Organisation (RO) Approbat

Refer to Recognised Organisation (RO) approbat user guide

Appendix — ZONE of responsibilities

Repartition of Countries by zone assigned to a NCM Quality Manager

CountryZone 1Zone 2Zone 3Zone 4QualifGET
NORTH ASIA      
China   xxx
Taiwan, Hong Kongx   xx
Koreax   xx
Japanx   xx
SOUTH EAST ASIA      
Singaporex   xx
Malaysia, Bruneix   xx
Philippinesx   xx
Vietnamx   xx
Thailandx   xx
Australia, New-Zeelandx   xx
INDIA, MIDDLE EAST, AFRICA      
Turkiyex   xx
Egyptx   xx
UAE, Omanx   xx
Saudi Arabiax   xx
Pakistanx   xx
India - Sri Lankax   xx
Bangladeshx   xx
- Sub-Saharan Africa      
South Africa and East Africa Countries  x xx
Angola  x xx
West and Central Africa Countries  x xx
Nigeria  x xx
SE EUROPE, BLACK SEA & ADRIATIC      
Greece, Malta, Cyprus  x xx
Ukraine   xxx
Serbia, Montenegro  x xx
Romania  x xx
Bulgaria  x xx
Croatia  x xx
Italy x  xx
SW EUROPE, N AFRICA, AMERICAS      
France & Overseas x xxx
Tunisia, Algeria, Morocco  xxxx
Spain - North & Northwest x  xx
Spain - South and East x  xx
Portugal x  xx
United Kingdom, Irelandx   xx
Canada   xxx
USA x  xx
Brazil x  xx
Panama, Colombia, Peru, Mexico, Cuba x  xx
Argentina, Chile, Paraguay, Uruguay x  xx
NORTH EUROPE      
Netherlands - Rotterdam  x xx
Netherlands - Groningen  x xx
Belgium, Luxembourg  x xx
Denmark, Iceland, Sweden  x xx
Norway  x xx
Finland, Estonia, Latvia, Lituania  x xx
Poland  x xx
Germany  x xx
Russian Federation