Section
11 Factory Acceptance Test and Shipboard Trials of Engines
11.1 Safety
11.1.1 Before any test is carried out, all relevant equipment for the safety of
attending personnel is to be made available by the manufacturer/shipyard and is to be
operational. This is to include crankcase explosive conditions protection, overspeed
protection and any other shutdown function.
11.1.2 The overspeed protective device is to be set to a value which is not higher
than the overspeed value that was demonstrated during the type test for that engine.
This set point is to be verified by the Surveyor.
11.1.3 The low-pressure gas fuel piping on the engine is to be verified as gastight prior to
the engine being started.
11.2 General
11.2.1 Engines which are to be subjected to trials on the test bed at the
manufacturer's works and under attendance by the Surveyor(s) are to be tested in
accordance with the scope of works trials specified in Pt 5, Ch 2, 11.3 Works trials (factory acceptance test) . The
scope of the trials is to be agreed between LR and the manufacturer prior to testing.
11.2.2 Where
multiple engines of the same design are manufactured, a quality assurance
approach to approval may be applied if the manufacturer meets the
requirements of and is registered on the Quality Assurance Scheme
for Machinery (QAM). (See
Pt 5, Ch 1, 6 Quality Assurance Scheme for Machinery).
11.2.3 Before
any official testing the engines are to be run in as prescribed by
the engine manufacturer.
11.2.4 Adequate
test bed facilities for loads as required in Table 2.11.1 Scope of works trials for
engines are to be provided.
All fluids used for testing purposes such as fuel, lubrication oil
and cooling water are to be suitable for the purpose intended, e.g.
they are to be clean, and if necessary pre-heated to achieve the recommended
operating temperature. This applies to all fluids used temporarily
or repeatedly for testing purposes only.
11.2.5 Survey
of the engine is to include:
-
Jacketing of
high-pressure fuel oil lines including the system used for the detection
of leakage.
-
Screening of
pipe connections in piping containing flammable liquids.
-
Insulation of
hot surfaces by taking random temperature readings that are to be
compared with corresponding readings obtained during the type test.
This is to be done while running at the maximum approved rating for
the actual application. Use of contact thermometers may be accepted
at the discretion of the attending Surveyor. If the insulation is
modified subsequently to the Type Approval Test, LR may request
more enhanced temperature measurements as required by the LR’s
Type Approval Test Specification No. 4, Section 10.2.7 (Fire Protection
Measures).
These surveys are normally to be made during the works trials but at the
discretion of LR parts of these surveys may be postponed to the shipboard testing.
11.2.6 Where the type test was not carried out on the complete engine, as
described in the scope of this chapter, integration tests are to be conducted as part of
the works or shipboard trials to confirm satisfactory operation of the complete engine.
This includes satisfactory functioning on all fuel types on which the engine is to
operate. See also
Pt 5, Ch 2, 11.4 Shipboard trials 11.4.6.
11.2.7 For the duration of the acceptance test, no interventions or adjustments
will be made to the machinery under test.
11.3 Works trials (factory acceptance test)
11.3.1 The purpose of the works trials is to verify design parameters such as
power, fire protection and prevention arrangements, adherence to approved limits (e.g.
maximum pressure) and functionality, and to establish reference values or base lines for
later reference in the operational phase.
11.3.2 During testing the environmental conditions are to be recorded, including
ambient air temperature, ambient air pressure and atmospheric humidity.
11.3.3 For each trial condition the parameters to be recorded include: Power and
speed; Fuel index, both gas and fuel oil as applicable (or equivalent reading); Gas
pressure and temperature; Maximum combustion pressures; Exhaust gas temperature before
turbine and from each cylinder (or from manifold, see Note 5 in Table 2.7.1 Engines for propulsion purposes:
Alarms and slow-downs); Charge air temperature and pressure, and
turbocharger speed (only for category B and C turbochargers).
11.3.4 For all stages of the works trials the pertaining operation values are to be
measured and recorded by the engine manufacturer. All results are to be compiled in an
acceptance protocol to be issued by the engine manufacturer. Where the engine designer
requires through life monitoring of crankshaft deflections, such measurements are also
to be taken before and after works acceptance trials in accordance with the engine
designer’s requirements.
11.3.5 In each case given in Table 2.11.1 Scope of works trials for
engines, all measurements conducted at the various
trial conditions are to be carried out at steady operating conditions. The readings for
MCR, i.e. 100 per cent power (rated maximum continuous power at corresponding rpm) are
to be taken twice at an interval of at least 30 minutes. For all trial conditions
provision should be made for time needed by the Surveyor to carry out visual
inspections.
11.3.6 Calibration records for the instrumentation are, upon request, to be
presented to the attending Surveyor.
Table 2.11.1 Scope of works trials for
engines
Main engines driving propellers and water jets
|
Trial condition
|
Duration
|
Note
|
100 per cent power (rated power) at rated engine
speed, R
|
≥ 60 minutes
|
see Note 5
|
110 per cent power at engine speed corresponding
to 1,032R
|
15 minutes
|
Or after having reached steady conditions,
whichever is shorter, see Notes 1, 4 and 5
For DF engines, this
may be demonstrated in diesel mode.
|
Approved intermittent overload (if
applicable)
|
—
|
Testing for duration to be agreed
with the manufacturer
|
90 per cent (or normal continuous power), 75 per
cent, 50 per cent and 25 per cent power
|
—
|
Engine speed in accordance with the nominal
propeller curve, sequence to be selected by the manufacturer, see
Note 5
For DF engines, the load tests are to be carried out in gas mode
at the different percentages of the maximum available power.
|
Reversing manoeuvres (if applicable)
|
—
|
—
|
Testing of governor and independent overspeed
protective device
|
—
|
See
Pt 5, Ch 2, 7 Control and monitoring of main, auxiliary and emergency engines
|
Shutdown device
|
—
|
See
Pt 5, Ch 2, 7 Control and monitoring of main, auxiliary and emergency engines
|
Engines driving generators for electric propulsion or driving generators
for auxiliary purposes
|
Trial condition
|
Duration
|
Note
|
100 per cent power (rated power) at rated engine
speed, R
|
≥ 60 minutes
|
see Note 5
|
110 per cent power
|
15 minutes
|
Or after having reached steady conditions,
see Note 2. For auxiliary engines, see Notes 1 and 5
For DF engines, this may be demonstrated in diesel
mode.
|
75 per cent, 50 per cent and 25 per cent power
and idle run
|
—
|
see Notes 2 and 5
For DF
engines, the load tests are to be carried out in gas mode at the
different percentages of the maximum available power.
|
Start-up tests
|
—
|
—
|
Testing of governor and independent overspeed
protective device
|
—
|
See
Pt 5, Ch 2, 7.3 Auxiliary and emergency engine governors
|
Shutdown device
|
—
|
See
Pt 5, Ch 2, 7.4 Overspeed protective devices
|
Propulsion engines driving power take off (PTO)
generator
|
Trial condition
|
Duration
|
Note
|
100 per cent power (rated power) at
rated engine speed, R
|
≥ 60 minutes
|
See Note 5
|
110 per cent power
|
15 minutes
|
Or after having reached steady
conditions, see Notes 3 and 5
For DF engines, this may
be demonstrated in diesel mode.
|
Approved intermittent overload (if
applicable)
|
—
|
Testing for duration to be agreed
with the manufacturer
|
90 per cent (of normal continuous
power), 75 per cent, 50 per cent and 25 per cent power
|
—
|
Engine speed in accordance with the
nominal propeller curve or at constant speed R, sequence to be
selected by the manufacturer, see Note 5
For DF engines, the load
tests are to be carried out in gas mode at the different percentages of
the maximum available power.
|
Engines driving mechanical auxiliaries
|
Trial condition
|
Duration
|
Note
|
100 per cent power (rated power) at
rated engine speed, R
|
≥ 30 minutes
|
For DF engines, this may be
demonstrated in diesel mode. See Note 5
|
110 per cent power
|
15 minutes
|
Or after having reached steady
conditions, see Notes 1 and 5
For DF engines, this may
be demonstrated in diesel mode.
|
Approved intermittent overload (if
applicable)
|
—
|
Testing for duration to be agreed
with the manufacturer
|
75 per cent, 50 per cent and 25 per
cent power
|
—
|
Engine speed in accordance with the
nominal power consumption curve, sequence to be selected by the
manufacturer, see Note 5
For DF engines, the load tests are to be
carried out in gas mode at the different percentages of the maximum
available power.
|
Note 1. After running on the
test bed, the fuel delivery system of main and auxiliary engines is
normally to be so adjusted that overload power cannot be given in service
unless intermittent overload power is approved by LR, in which case the
limit is to be adjusted to that power. The setting of the restriction is
to be made as applicable to the intended fuel. Any restriction settings,
and other changes to the engine’s fuel injection equipment required for
operation on special fuels, are to be recorded and included by the engine
manufacturer.
Note 2. After running on the
test bed, the fuel delivery system of diesel engines driving generators
is to be adjusted so that full power plus a 10 per cent margin for
transient regulation can be given in service after installation on board.
The transient overload capability is required so that the required
transient governing characteristics are achieved also at 100 per cent
loading of the engine, and so that the protection system utilised in the
electric distribution system can be activated before the engine
stalls.
Note 3. After running on the
test bed, the fuel delivery system of propulsion engines also driving
power take off (PTO) generators is to be adjusted so that full power plus
a margin for transient regulation can be given in service after
installation on board. The transient overload capability is required so
that the electrical protection of downstream system components is
activated before the engine stalls. This margin may be 10 per cent of the
engine power but at least 10 per cent of the PTO power.
Note 4. Only required once
for each different engine/turbocharger configuration.
Note 5. The gas methane number (where applicable) during the test is to be
recorded. The test should demonstrate that the engine reaches the
declared power output with the given methane number.
|
11.3.7 Alternatives to the detailed tests may be agreed between the manufacturer
and LR when the overall scope of tests is found to be equivalent. The scope of the
trials may be expanded depending on the engine application, service experience, or other
relevant reasons. Dual fuel (DF) engines using low pressure methane shall be tested in
both fuel oil and gas mode as applicable.
11.3.9 For electronically controlled engines:
-
factory acceptance tests in accordance with Pt 5, Ch 2, 1.4 Submission requirements 1.4.3;
- integration tests are to be made to verify that the response of the
complete mechanical, hydraulic and electronic system is as predicted for all intended
operational modes and the tests considered as a system are to be carried out at the
works. If such tests are technically unfeasible at the works, then these tests may be
conducted during sea trial; and
-
verification of engine configuration, see
Pt 5, Ch 2, 4.3 Control engineering systems 4.3.2, and that the approved software quality plans,
including the software configuration management process, are to be applied.
11.3.10 Gas fuel (GF) only and DF engines using low pressure methane are to undergo
integration tests to verify correct operation of the complete mechanical, hydraulic and
electronic system for all intended operational modes. The scope of these tests is to be
agreed with LR and is to be based on the results of the risk analysis required in Pt 5, Ch 2, 15.3 Risk analysis. Tests are to
include, but not be limited to:
- failure of ignition (spark ignition or pilot injection
systems), for one-cylinder unit;
- failure of a cylinder gas supply valve;
- failure of the combustion (to be detected by e.g. misfiring,
knocking, exhaust temperature deviation, etc.);
- abnormal gas pressure;
- abnormal gas temperature.
The above tests may be carried out by simulation or other alternative methods subject to
special consideration and agreement by LR.
11.3.11 Checks of components to be presented for inspection after the works trials
are left to the discretion of the Surveyor.
11.4 Shipboard trials
11.4.1 The purpose of the shipboard testing is to verify compatibility with power
transmission and driven machinery in the system, safety, control and auxiliary systems
necessary for the engine and integration of engine/shipboard control systems, as well as
other items that had not been dealt with in the FAT (Factory Acceptance Testing).
11.4.2 After installation on board, engines are to undergo shipboard trials as
specified in Table 2.11.2 Scope of shipboard trials for
engines. The scope of the trials may be expanded
depending on the engine application, service experience or other relevant reasons, and
is to be agreed between the LR Surveyor and the Shipyard prior to testing.
Table 2.11.2 Scope of shipboard trials for
engines
Main engines driving fixed-pitch propeller or water jet (see
Note 1)
|
Trial
condition
|
Duration
|
Note
|
At rated engine speed, R
|
≥ 4 hours
|
– see Note 6
|
At engine speed corresponding to
1,032R
|
30 minutes
|
Where the engine adjustment permits,
see
Pt 5, Ch 2, 11.2 General 11.2.7, see Note 6
For DF engines, this may be demonstrated in diesel mode
|
Approved intermittent overload (if
applicable)
|
-
|
Testing for duration as agreed with
the manufacturer
|
Minimum engine speed to be
determined
|
–
|
–
|
Starting and reversing
manoeuvres
|
–
|
See
Pt 5, Ch 2, 9 Starting arrangements and Pt 5, Ch 2, 13 Air compressors (see Note 5)
|
Reverse direction of propeller
rotation is to be demonstrated (during the dock or sea trials)
|
10 minutes
|
See also
Pt 5, Ch 2, 11.4 Shipboard trials 11.4.7 and Pt 5, Ch 2, 11.4 Shipboard trials 11.4.8
|
Control, monitoring, alarms and safety
systems
|
–
|
Operation to be
demonstrated
|
Where
imposed, test to ensure engine can pass safely through barred speed
range
|
–
|
See
Pt 5, Ch 2, 11.4 Shipboard trials 11.4.7 and Pt 5, Ch 2, 11.4 Shipboard trials 11.4.8 for additional requirements in
the case of a barred speed range
|
Main engines driving controllable pitch
propellers
|
Trial
condition
|
Duration
|
Note
|
At 100 per
cent power
|
≥ 4
hours
|
See
Notes 2 and 6
|
Approved
intermittent overload (if applicable)
|
–
|
Testing for
duration as agreed with the manufacturer
|
With reverse
pitch suitable for manoeuvring
|
–
|
See
Pt 5, Ch 2, 11.4 Shipboard trials 11.4.7 and Pt 5, Ch 2, 11.4 Shipboard trials 11.4.8 for additional requirements in
the case of a barred speed range
|
Control,
monitoring, alarm and safety systems
|
–
|
Operation to
be demonstrated
|
Engine(s) driving generator(s) for electrical propulsion and/or main
power supply
|
Trial
condition
|
Duration
|
Note
|
100 per cent power (rated electrical
power of generator)
|
≥ 60 minutes
|
See Notes 3, 4
and 6
|
110 per cent power (rated
electrical power of generator)
|
≥ 10
minutes
|
See Notes 4 and
6
For DF engines, this may be demonstrated in diesel
mode
|
Starting manoeuvres
|
–
|
See Note 5
|
Control, monitoring, alarm and safety
systems
|
–
|
Operation to be demonstrated
|
Demonstration of the generator prime
movers’ and governors’ ability to handle load steps
|
–
|
See
Pt 5, Ch 2, 7.3 Auxiliary and emergency engine governors
|
Propulsion engines driving power take off
(PTO) generator
|
Trial condition
|
Duration
|
Note
|
100 per cent engine power (MCR) at
corresponding speed, R
|
≥ 4 hour
|
See Note 6
|
100 per cent propeller branch power
at engine speed, R (unless already covered above)
|
2 hours
|
See Note 6
|
100 per cent PTO branch power at
engine speed, R
|
≥ 1 hour
|
See Note 6
|
Control, monitoring, alarm and safety
systems
|
-
|
Operation to be demonstrated
|
Engines driving mechanical auxiliaries
|
Trial condition
|
Duration
|
Note
|
100 per cent engine power (MCR) at
corresponding speed, R
|
≥ 30 minutes
|
See Note 6
|
Approved intermittent overload (if
applicable)
|
–
|
Testing for duration as
approved
|
Control, monitoring, alarm and safety
systems
|
–
|
Operation to be demonstrated
|
Note 1. For main propulsion
engines driving reversing gears, the tests for main engines driving
fixed-pitch propellers apply as appropriate.
Note 2. Controllable pitch
propellers are to be tested with various propeller pitches. The 100 per
cent power test is to be conducted at rated engine speed R with a
propeller pitch set of MCR (or to the maximum achievable power if 100 per
cent cannot be reached).
Note 3. The tests are to be
performed at rated speed with a constant governor setting.
Note 4. Tests are to be
based on the rated electrical powers of the electric propulsion
motors.
Note 5. Starting manoeuvres
are to be carried out in order to verify the capacity of the starting
media. The ability of reversible engines to be operated in the reverse
direction is to be demonstrated. See
Pt 5, Ch 1, 3.9 Astern power.
Note 6. Gas methane number during the test is to be recorded. The test
should demonstrate that the engine reaches the declared power output with
the given methane number.
|
11.4.3 Engines driving electrical generators are to be tested either:
- at 100 per cent electrical power for at least 60 minutes and 110 per
cent of rated electrical power of the generator for at least 10 minutes; or
- During the electrical propulsion plant test which requires testing
with 100 per cent propulsion power (i.e. total electric motor capacity for
propulsion) by distributing the power on as few generators as possible. The
duration of this test is to be sufficient to reach stable operating temperatures
of all rotating machines or for at least 4 hours.
11.4.4 Trials are to include demonstration of engine control, monitoring, alarm
and safety system operation to confirm that they have been provided, installed and
configured as intended and in accordance with the relevant requirements for main,
auxiliary or emergency engines except items already verified during the works
trials.
11.4.5 For electronically controlled engines:
-
shipboard tests in accordance with the approved schedule, see
also
Pt 5, Ch 2, 1.4 Submission requirements 1.4.3; and
-
verification of engine configuration, see
Pt 5, Ch 2, 4.3 Control engineering systems 4.3.2 and Pt 5, Ch 2, 1.4 Submission requirements 1.4.3 (a), and that the approved software
quality plans, including the software configuration management process, are to be
applied.
11.4.6 The suitability of an engine to burn residual or other special fuels is to be
demonstrated, where the machinery installation is arranged to burn such fuels in
service. DF or multi-fuel engines are to be tested on all fuels that the engine is
specified to use. Where engines operate on a mix of different fuels then this is to be
demonstrated. See also
Pt 6, Ch 1, 7.2 Unattended machinery space operation - UMS notation 7.2.1.
11.4.7 For both manual and automatic engine control systems, acceleration and
deceleration through any barred speed range, is to be demonstrated. The transit times
are to be equal or less than the times stated in the approved documentation and are to
be recorded. This also applies when passing through the barred speed range in reverse
rotational direction, especially during the stopping test. The ship’s draft and speed
during all these demonstrations are to be recorded. Where a controllable pitch propeller
is fitted, the pitch is also to be recorded.
11.4.8 The engine is to be checked for stable running (steady fuel index) at both
upper and lower borders of the barred speed range. Steady fuel index means an
oscillation range less than five per cent of the effective stroke (idle to full index).
|