Section
5 Special Survey - General - Hull requirements
5.1 General
5.1.1 The
survey is to be of sufficient extent to ensure that the hull and related
piping are in satisfactory condition and are fit for the intended
purpose for the new period of class of five years to be assigned,
subject to proper maintenance and operation and to periodical surveys
being carried out as required by the Regulations.
5.1.3 Additional requirements for general dry cargo ships are given in
this Section; dry bulk cargo ships bulk carriers in Pt 1, Ch 3, 6 Special Survey - Bulk carriers - Hull requirements; oil tankers (including ore/oil ships and
ore/bulk/oil ships) in Pt 1, Ch 3, 7 Special Survey - Oil tankers (including ore/oil ships and ore/bulk/oil ships) - Hull requirements; chemical tankers in Pt 1, Ch 3, 8 Special Survey - Chemical Tankers - Hull requirements; ships for liquefied gases in Pt 1, Ch 3, 9 Ships for liquefied gases, as applicable, gases or other low flashpoint fuels
in Pt 1, Ch 3, 23 Fuel installations using gases or other low-flashpoint fuels, as applicable.
5.1.5 During the Bottom Survey, for general dry cargo ships, oil tankers
(including ore/oil ships and ore/bulk/oil ships), chemical tankers and bulk carriers,
the overall and close-up surveys and thickness measurements, as applicable, of the lower
portions of the cargo spaces and ballast tanks are to be carried out as required, if not
already surveyed.
5.1.6 For
ships assigned the notation ‘laid-up’, an Underwater Examination
(UWE) and general examination of hull and machinery is to be carried
out in lieu of the normal Special Survey requirements.
5.2 Preparation
5.2.1 The
ship is to be prepared for Overall Survey in accordance with the requirements
of Table 3.5.1 Survey preparation. The preparation
should be of sufficient extent to facilitate an examination to ascertain
any significant corrosion, deformation, fractures, damages and other
structural deterioration.
Table 3.5.1 Survey preparation
Special Survey I (Ships 5 years
old)
|
Special Survey II (Ships 10
years old)
|
Special Survey III (Ships 15
years old)
|
(1)
|
The holds, ’tween decks,
peaks, deep tanks, engine and boiler spaces, and other spaces, are to be
cleared and cleaned as necessary, and the bilges and limbers all fore and
aft are to be cleaned and prepared for examination. Platform plates in
engine and boiler spaces are to be lifted as may be necessary for the
examination of the structure below. Where necessary, close and spar ceiling,
lining and pipe casings are to be removed for examination of the
structure
|
In addition to the requirements for Special Survey
I, the following are to be complied with:
|
In addition to the requirements for Special Survey
II the following are to be complied with:
|
(1)
|
A
sufficient amount of ceiling in the holds and other spaces is to be removed
from the bilges and inner bottom to enable the condition of the structure in
the bilges, the inner bottom plating, pillar feet, and the bottom plating of
bulkheads and tunnel sides to be examined. If the Surveyor deems it
necessary, the whole of the ceiling is to be removed
|
(1)
|
Ceiling in holds is to
be removed in order to ascertain that the steelwork is in good condition,
free from rust and coated. If the Surveyor is satisfied, after removal of
portions of the ceiling then it need not all be removed
|
(2)
|
In ships having a single bottom, a
sufficient amount of close ceiling is to be lifted all fore and aft on each
side from the bottom and bilges to permit the structure below to be
examined
|
(2)
|
In ships having a single bottom, the
limber boards and ceiling equal to not less than three strakes, all fore and
aft on each side are to be removed, one such strake being taken from the
bilges. Where the ceiling is fitted in hatches, the whole of the hatches and
at least one strake of ceiling in the bilges are to be removed. If the
Surveyor deems it necessary the whole of the ceiling and limber boards are
to be removed
|
(2)
|
Portions of wood
sheathing, or other covering, on steel decks are to be removed, as
considered necessary by the Surveyor, in order to ascertain the condition of
the plating
|
(3)
|
In ships having a double bottom, a sufficient amount of ceiling
is to be removed from the bilges and inner bottom to enable the condition of
the plating to be ascertained. If it is found that the plating is clean and
in good condition, and free from rust, the removal of the remainder of
ceiling may be dispensed with. The Surveyor may waive the removal of heavy
reinforced compositions if there is no evidence of leakages, cracking or
other faults in the composition
|
(3)
|
The chain locker is to be cleaned internally. The chain cables are to be
ranged for inspection. The anchors are to be cleaned and placed in an
accessible position for inspection
|
All subsequent Special Surveys
|
In addition to the requirements for Special Survey
III the following are to be complied with:
|
(4)
|
Casings,
ceilings or linings and loose insulation, where fitted, are to be removed
for examination of plating and framing, as required by the Surveyor.
Compositions on plating are to be examined and sounded, but need not be
disturbed if found to be adhering satisfactorily to the plating. Where
structural defects are identified, any applied composition is to be locally
removed to enable further examination of the plating and adjacent frames, as
required by the Surveyor
|
|
|
(1)
|
In refrigerated cargo
spaces, sufficient insulation is to be removed in each of the chambers to
enable the Surveyor to be satisfied as to the condition of the steel
structure, and to enable the thickness of the structure to be ascertained as
required by Pt 1, Ch 3, 5.6 Thickness measurement
|
(5)
|
The
steelwork is to be exposed and cleaned and rust removed as may be required
for its proper examination by the Surveyor
|
|
|
|
|
(6)
|
All tanks
are to be cleaned as necessary to permit examination, where this is required
by Table 3.5.2 Tank internal examination
requirements
|
|
|
|
|
(7)
|
Casings or
covers of air, sounding, steam and other pipes, spar ceiling and lining in
way of the side scuttles are to be removed, as required by the
Surveyor
|
|
|
|
|
(8)
|
The masts
and the sail/wind propulsion system are to be unshipped for survey. The
whole of the standing rigging, including rigging screws, bolts, pins and
fittings, is to be fully or partly disassembled as considered necessary by
the Surveyor.
Note This requirement may be waived at alternate Special
Surveys or when the construction does not allow disassembly, provided
that the masts and rigging are thoroughly examined in situ.
|
|
|
|
|
Note ‘unshipped’ means removed from its fixed or regular position and laid
down, providing access for Close-up Survey.
‘disassembled’ means to dismantle and lay out all lines, tackles and
other removable parts to the extent necessary to establish the
condition of the rigging components.
|
5.3 Examination and testing
5.3.1 All spaces within the hull and superstructure are to be examined unless
specified otherwise by this Section.
5.3.2 At Special Survey III and subsequent special surveys, structural
downflooding ducts and structural ventilation ducts are to be internally examined.
5.3.3 The requirements for tank internal examination are given in Table 3.5.2 Tank internal examination
requirements.
Table 3.5.2 Tank internal examination
requirements
Tank
|
Special Survey
I (Ships 5 years old)
|
Special Survey
II (Ships 10 years old)
|
Special Survey
III (Ships 15 years old)
|
Special Survey IV and
subsequent (Ships 20 years old and over)
|
(1)
|
Peaks
|
All tanks
|
All tanks
|
All tanks
|
All tanks
|
(2)
|
Salt water
ballast, see Note 5
|
All tanks
|
All tanks
|
All tanks
|
All tanks
|
(3)
|
Lubricating
oil
|
None
|
None
|
None
|
One tank
|
(4)
|
Fresh
water
|
None
|
One tank
|
All tanks
|
All tanks
|
(5)
|
Fuel oil
|
|
|
|
|
|
(i) In
way of engine room
|
None
|
None
|
One
tank
|
One
tank
|
|
(ii) In
way of cargo area
|
None
|
One
tank
|
Two
tanks, see Note 3
|
50% of
tanks - see Notes 3 and 4.
|
|
(iii) If
no tanks in cargo length area, additional fuel tank(s) outside of engine
room (if fitted)
|
None
|
One
tank
|
One
tank
|
Two
tanks
|
Note
1. The above requirements apply to
integral tanks only.
Note
2. Where a selected number of tanks are
examined, then different tanks are to be examined at each Special
Survey on a rotational basis.
|
Note
3. To include one deep tank, if any.
Note
4. Where 50% of tanks are to be examined,
a minimum of two tanks are required to be examined depending upon the
overall number of tanks.
Note
5. The requirements for Salt-water
ballast tanks are applicable to Bilge water, Sewage and Grey water
tanks.
|
5.3.4 For oil tankers (including ore/oil and ore/bulk/oil ships) and
chemical tankers, the condition of the corrosion prevention system, where
provided, is to be examined in cargo tanks and salt-water ballast tanks. When considered
necessary by the Surveyor, thickness measurements are to be carried out. The condition
of the corrosion prevention system identified during the Survey may result in the
salt-water ballast tanks being subject to further examination at Annual Surveys, in
accordance with Pt 1, Ch 3, 2.2 Annual Surveys 2.2.32.
5.3.5 For those ships not listed in Pt 1, Ch 3, 5.3 Examination and testing 5.3.4, the condition of the corrosion prevention system,
where provided, in salt-water ballast tanks is to be examined. When considered necessary
by the Surveyor, thickness measurements are to be carried out. The condition of the
corrosion prevention system identified during the Survey may result in the salt-water
ballast tanks being subject to further examination at Annual Surveys, in accordance with
Pt 1, Ch 3, 2.2 Annual Surveys 2.2.32. For double bottom ballast tanks, the examination at
Annual Surveys will be at the discretion of the Surveyor.
5.3.6 Double bottom, deep, ballast, peak and other tanks, including cargo holds
assigned also for the carriage of salt water ballast, are to be tested with a head of
liquid to the top of air pipes or to near the top of hatches for ballast/cargo holds.
Boundaries of fuel oil, lubricating oil and fresh water tanks are to be tested with a
head of liquid to the highest point that liquid will rise to under service conditions.
Tank testing of fuel oil, lubricating oil and fresh water tanks may be specially
considered based upon a satisfactory external examination of the tank boundaries, and a
confirmation from the Master stating that the pressure testing has been carried out
according to the requirements with satisfactory results. Surveyors may extend the
testing as deemed necessary. For oil tankers (including ore/oil
and ore/bulk/oil ships) and chemical tankers, the minimum requirements for cargo
tank testing are to be in accordance with Sections Pt 1, Ch 3, 7.5 Testing and
Pt 1, Ch 3, 8.5 Testing,
as applicable.
5.3.7 Where repairs are effected to the shell plating or bulkheads, any tanks in
way are to be tested to the Surveyor's satisfaction on completion of these repairs.
5.3.8 On ship-borne barges, in lieu of water testing, tanks and cofferdams may be
air tested.
5.3.9 In cases where the inner surface of the bottom plating is covered with
cement, asphalt, or other composition, the removal of this covering may be dispensed
with, provided that it is inspected, tested by beating or chipping, and found sound and
adhering satisfactorily to the steel.
5.3.10 All decks, casings and superstructures are to be examined.
5.3.11 Wood decks or sheathing are to be examined. If decay or rot is found or the
wood is excessively worn, the wood is to be renewed. When a wood deck, laid on stringers
and ties, has worn by 15 mm or more, it is to be renewed. Attention is to be given to
the condition of the plating under wood decks, sheathing or other deck covering. If it
is found that such coverings are broken, or are not adhering closely to the plating,
sections are to be removed as necessary to ascertain the condition of the plating,
see also
Pt 1, Ch 3, 1.2 Surveys for damage or alterations 1.2.1.
5.3.12 Mechanically-operated hatch covers are to be tested to confirm satisfactory
operation including stowage; and securing in open condition; proper fit and efficiency
of sealing in closed conditions; operational testing of hydraulic and power components,
wires, chains and link drives. The effectiveness of sealing arrangements of all hatch
covers is to be checked by carrying out hose testing or equivalent.
5.3.13 Rigs used for propulsion using wind force, associated structure and
equipment, where fitted, are to be examined, see
Table 3.5.1 Survey preparation.
The examination may be undertaken by a Surveyor and/or by a firm approved by LR.
5.3.14 The masts and standing rigging are to be examined.
5.3.15 The anchors are to be examined. If the chain cables are ranged they are to
be examined. If any length of chain cable is found to be reduced in mean diameter at its
most worn part by 12 per cent or more from its nominal diameter, it is to be renewed.
The windlass is to be examined. For equipment forming part of a positional mooring
system, see
Pt 1, Ch 3, 5.3 Examination and testing 5.3.18.
5.3.16 The chain cables are to be ranged and examined on all ships over five years
old.
5.3.17 The Surveyor is to be satisfied that there are suitable mooring ropes when
these are a Rule requirement.
5.3.18 On ships fitted with positional mooring equipment in accordance with Pt 7, Ch 8 Positional Mooring and Thruster-Assisted Positional Mooring Systems, or wire rope anchor cables in accordance with Pt 3, Ch 13, 7 Equipment, the anchors are to be cleaned and examined. Wire rope
anchor cables are to be examined. If cables are found to contain broken, badly corroded
or birdcaging wires they are to be renewed. Chain cables are to be ranged and examined.
If any length of chain cable is found to be reduced in mean diameter at its most worn
part by 12 per cent or more from its nominal diameter it is to be renewed. The
windlass(es) or winches are to be examined.
5.3.21 The Surveyor is to be satisfied as to the efficient condition of the
following:
-
For ships to which Pt 6, Ch 4 Fire Protection, Detection and Extinction Requirements applies, means of escape from crew and passenger
spaces, and spaces in which crew are normally employed.
-
Helm indicator, protection of aft steering wheel and gear.
5.3.22 Where the special features notation CCSA (certified container
securing arrangements) is assigned, the Surveyor is to be satisfied as to the efficient
condition of:
-
Cell guide structure including the connections between vertical cell
guides and cross ties.
-
Cell guide entry devices.
-
Portable frameworks or other forms of structural restraints.
-
Fittings attached to the ship structure, with special attention to
any signs of leakage in way of tanks or deck and shell plating.
-
End connecting pieces for lashings, twist locks and other loose
fittings, which are to be examined and verified with the Register, see
Pt 3, Ch 14, 10 Surveys.
-
Lashings, rods, wire ropes, and chains together with turn buckles and
other tightening devices are to be examined and verified with the Register as far
as necessary and practicable in order to be satisfied as to their general
condition, see
Pt 3, Ch 14, 10 Surveys.
-
Lashing wire ropes, which are to be renewed where more than five per
cent of the wires are broken, worn or corroded in any length of 10 diameters of
the wire rope.
-
Chains, which are to be renewed where worn or damaged.
Where renewals are required, the new item is to be of approved type and
manufacture. Where test certificates are not available, the item is to be tested in
accordance with Pt 3, Ch 14, 3 Loose container securing fittings, materials and testing.
5.3.23 It is the responsibility of the onboard personnel to examine, maintain or
renew cargo securing devices and maintain the appropriate certification. Records of
inspections, maintenance and renewals, as well as the procedures for accepting,
maintaining and repairing or rejecting cargo securing devices are to be kept onboard and
made available to the attending Surveyor on request.
5.3.24 All bilge and ballast piping systems are to be examined and operationally
tested to working pressure, to the satisfaction of the Surveyor, to ensure that
tightness and condition remain satisfactory.
5.3.25 Ship side valves (i.e. sea connections, scuppers and sanitary discharges)
are to be tested once reassembled.
5.3.26 For engine room and machinery space fire dampers the following is
applicable:
-
At Special Survey I, Surveyors are to select and internally examine
one engine room fire damper and one machinery space fire damper. Where considered
necessary by the Surveyor as a result of the examinations, the extent of
examinations may be extended to include other fire dampers.
-
At each subsequent Special Survey, all engine room and machinery space
fire dampers are to be internally examined by the Surveyor.
Note The examination of fire dampers may be specially considered by the
Surveyor where there is satisfactory documented evidence of their replacement within
the previous five years.
5.3.27 In refrigerated cargo spaces, the condition of the coating and structure
behind the insulation is to be examined at representative locations. Surveyors may limit
the examination to the verification that the protective coating remains effective and
that there are no visible structural defects. Where POOR coating condition is found, or
structural defects are identified, then sufficient insulation is to be removed in each
of the chambers in order to assess the condition of the remaining structure, as deemed
necessary by the Surveyor. Additionally, where indents, scratches or other defects are
identified during the survey of the shell plating from the outside, insulations in way
are to be removed to enable further examination of the plating and adjacent frames, as
required by the Surveyor.
5.4 Overall Survey
5.4.1 The
following requirements are applicable to general dry cargo ships.
5.4.2 All
cargo holds, salt-water ballast tanks including double bottom tanks,
pipe tunnels, cofferdams and void spaces bounding cargo holds, decks
and outer hull are to be examined, and this is to be supplemented
by Close-up Survey, thickness measurement and testing as deemed necessary,
to ensure that the structural integrity remains effective.
5.4.3 The
examination is to be sufficient to ascertain substantial corrosion,
significant deformation, fractures, damages or other structural deterioration
and, if deemed necessary by the Surveyor, suitable non-destructive
examination may be required.
5.4.4 All
piping systems within the tanks and spaces indicated in Pt 1, Ch 3, 5.4 Overall Survey 5.4.2 are to be examined and operationally
tested to working pressure to the satisfaction of the Surveyor, to
ensure that conditions remain satisfactory.
5.4.5 Where
the salt-water ballast tanks have been converted to void spaces, the
survey extent is to be specially considered based upon salt-water
ballast tank requirements.
5.4.6 For
single hold general dry cargo ships, other than bulk carriers, fitted
with water level detectors in the cargo hold, an examination and a
test of the water ingress detection system and alarms are to be carried
out.
5.5 Close-up Survey
5.5.1 The
following requirements are applicable to general dry cargo ships.
5.5.2 The
minimum requirements for Close-up Survey are given in Table 3.5.4 Minimum requirements for Close-up
Survey - General dry cargo ships. The Close-up Survey
may be extended, as deemed necessary by the Surveyor, after taking
into account the maintenance of the spaces under survey, the condition
of the corrosion prevention system and where spaces have structural
arrangements or details which have suffered defects in similar spaces
or on similar ships according to available information.
5.5.3 For
areas in tanks and cargo holds where coatings are found to be in GOOD
condition, as defined in Pt 1, Ch 3, 1.5 Definitions,
the extent of Close-up Surveys may be specially considered.
5.6 Thickness measurement
5.6.1 The
general minimum requirements for thickness measurement are given in Table 3.5.3 Minimum requirements for thickness
measurements - General. For general dry
cargo ships, the minimum requirements for thickness measurement
are given in Table 3.5.5 Minimum requirements for Thickness
measurement - General dry cargo ships.
The Surveyor may extend the thickness measurements as deemed necessary.
Table 3.5.3 Minimum requirements for thickness
measurements - General
Special Survey I (Ships 5 years
old)
|
Special Survey III (Ships 15
years old)
|
Special Survey IV and subsequent
(Ships 20 years old and over)
|
(1)
|
Suspect
areas, as required by the Surveyor. See Note 8.
|
(1)
|
Within 0,5 L
amidships; 2 transverse sections in way of two different
cargo spaces. See Notes 2, 4(a), 5 and 7.
|
(1)
|
Within 0,5 L
amidships; a minimum of 3 transverse sections in way of
cargo spaces. see Notes 2, 4(b) and 7.
|
Special Survey II (Ships 10 years
old)
|
(2)
|
All cargo
hold hatch covers and coamings (plating and stiffeners). See Note
9.
|
(2)
|
All cargo
hold hatch covers and coamings (plating and stiffeners). See
Note 9.
|
(1)
|
Within
0,5 L amidships; 1 transverse section of deck
plating in way of a cargo space, See Notes 2 and 7.
|
(3)
|
Internals
and the transverse bulkhead complete in the fore peak ballast tank and aft
peak ballast tank. See Note 6.
|
(3)
|
All exposed main deck
plating over full length of ship.
|
(2)
|
Suspect
areas, as required by the Surveyor. See Note 8.
|
(4)
|
Suspect
areas, as required by the Surveyor. See Note 8.
|
(4)
|
All wind and water
strakes over the full length of the ship, port and starboard.
|
|
|
|
|
(5)
|
Representative exposed
superstructure deck plating (i.e. poop, bridge and forecastle deck).
|
|
|
|
|
(6)
|
Lowest strake and
strakes in way of ‘tween deck of all transverse bulkheads in cargo spaces
together with internals in way. See Notes 6 and 7.
|
|
|
|
|
(7)
|
Internals and the
transverse bulkhead complete in the fore peak ballast tank and aft peak
ballast tank. See Note 6.
|
|
|
|
|
(8)
|
All keel plates over
the full length of the ship. Also additional bottom plates in way of
cofferdams, machinery space and aft end of tanks.
|
|
|
|
|
(9)
|
Plating of sea chests.
Also side shell plating in way of overboard discharges, as considered
necessary by the Surveyor.
|
|
|
|
|
(10)
|
Suspect areas, as required by the
Surveyor. See Note 8.
|
Note
1. Thickness measurement locations are to
be selected to provide the best representative sampling of areas
likely to be most exposed to corrosion, considering cargo and ballast
history and arrangement, and condition of protective coatings.
|
Note
2. A transverse section is to include all
longitudinal members such as plating, longitudinals and girders at the
deck, sides, bottom, inner bottom, hopper side and longitudinal
bulkheads, where fitted. For transversely framed vessels, a transverse
section includes adjacent frames and their end connections in way of
transverse sections.
|
Note
3. Where the protective coating is in
GOOD condition, then the extent of thickness measurements of internals
may be specially considered, but not dispensed with in its entirety,
at the discretion of the Surveyor.
|
4. For ships having length L less
than 100 m:
- the number of transverse sections required at Special Survey
III may be reduced to one;
- the number of transverse sections required at Special Survey
IV and subsequent surveys may be reduced to two.
|
Note 5. For ships having length L more than 100m, at Special Survey III,
thickness measurements of exposed deck plating within 0,5L
amidships may be required.
|
Note
6. Transverse bulkhead complete including
stiffening system.
|
Note 7. For vessels without defined cargo spaces, thickness measurements
are to be taken at the appropriate, most onerous locations selected to
provide the best representative sampling of areas likely to be exposed to
corrosion the most.
|
Note 8. Suspect Areas are locations showing substantial corrosion and/or
are considered by the Surveyor to be prone to rapid wastage.
|
Note 9. Subject to cargo hold hatch covers of approved design which
structurally have no access to the internals close-up survey/thickness
measurement shall be done of accessible parts of hatch cover
structures.
|
Table 3.5.4 Minimum requirements for Close-up
Survey - General dry cargo ships
Special Survey I (Ships 5 years
old)
|
Special Survey II (Ships 10 years
old)
|
Special Survey III (Ships 15 years
old)
|
Special Survey IV and subsequent (Ships 20
years old and over)
|
(1)
|
Selected
shell frames in one forward and one aft cargo hold and associated ‘tween
deck spaces.
|
(1)
|
Selected
shell frames in all cargo holds and ‘tween deck spaces.
|
(1)
|
All shell
frames in the forward lower cargo hold and 25% of shell frames in each
remaining cargo hold and ‘tween deck spaces, including their upper and
lower end attachments and adjacent shell plating.
|
(1)
|
All shell frames in
all cargo holds and ‘tween deck spaces, including their upper and lower end
attachments and adjacent shell plating.
|
(2)
|
One
selected cargo hold transverse bulkhead.
|
(2)
|
One
transverse bulkhead in each cargo hold, including stiffening system.
|
(2)
|
All cargo
hold transverse bulkheads, including stiffening system.
|
(2)
|
All cargo hold
transverse bulkheads, including stiffening system.
|
(3)
|
All cargo
hold hatch covers and coamings (plating and stiffeners). See Note
2.
|
(3)
|
Forward and
aft transverse bulkhead in one side ballast tank, including stiffening
system.
|
(3)
|
All
transverse bulkheads in ballast tanks, including stiffening system.
|
(3)
|
All transverse
bulkheads in ballast tanks, including stiffening system.
|
|
|
(4)
|
One
transverse web with associated plating and framing in two representative
water ballast tanks of each type (i.e. topside, hopper side, side tank, peak
tank or double bottom tank).
|
(4)
|
All
transverse webs with associated plating and framing in each water ballast
tank.
|
(4)
|
All transverse webs
with associated plating and framing in each water ballast tank.
|
|
|
(5)
|
All cargo
hold hatch covers and coamings (plating and stiffeners). See Note
2.
|
(5)
|
All cargo
hold hatch covers and coamings (plating and stiffeners). See Note
2.
|
(5)
|
All cargo hold hatch
covers and coamings (plating and stiffeners). See Note 2.
|
|
|
(6)
|
Selected
areas of all deck plating and underdeck structure inside the line of hatch
openings between cargo hold hatches.
|
(6)
|
All deck
plating and underdeck structure and inside the line of hatch openings
between cargo hold hatches.
|
(6)
|
All deck plating and
underdeck structure inside the line of hatch openings between cargo hold
hatches.
|
|
|
(7)
|
Selected
areas of inner bottom plating.
|
(7)
|
All areas
of inner bottom plating.
|
(7)
|
All areas of inner bottom
plating.
|
1. Close-up survey of cargo hold
transverse bulkheads to be carried out at the following areas:
- Immediately above the inner bottom and immediately above the
‘tween decks, as applicable.
- Mid-height of the bulkhead for the holds without ‘tween
decks.
- Immediately below the main deck plating and ‘tween deck
plating.
Note
2. Subject to cargo hold hatch covers of
approved design which structurally have no access to the internals,
close-up survey/thickness measurement shall be done of accessible
parts of hatch covers structures.
|
Table 3.5.5 Minimum requirements for Thickness
measurement - General dry cargo ships
Special Survey I (Ships 5 years
old)
|
Special Survey III (Ships 15
years old)
|
Special Survey IV and subsequent
(Ships 20 years old and over)
|
(1)
|
Suspect areas, as required by the Surveyor. See Note
3.
|
(1)
|
Within 0,5 L amidships; 2 transverse
sections in way of two different cargo spaces. See Notes 2, and 4(a).
|
(1)
|
Within
the cargo length area:
(i) A minimum of three transverse
sections within the amidships 0,5 L. See Notes 2 & 4(b).
(ii) Each deck plate outside the line of cargo hatch
openings. See Note 6.
(iii) Each bottom plate,
including lower turn of bilge.
(iv) Duct keel or pipe
tunnel plating and internals.
|
Special Survey II (Ships 10 years
old)
|
(2)
|
Measurements for the general assessment and recording of
corrosion pattern of those structural members subject to Close-up Survey in
accordance with Table 3.5.4 Minimum requirements for Close-up
Survey - General dry cargo ships
|
(2)
|
Measurements for the general assessment and recording of corrosion pattern
of those structural members subject to Close-up Survey in accordance with
Table 3.5.4 Minimum requirements for Close-up
Survey - General dry cargo ships.
|
(1)
|
Within 0,5L amidships; 1 transverse
section of deck plating in way of a cargo space. See Note 2.
|
(3)
|
Within the cargo length area; each deck plate outside line of
cargo hatch openings. See Note 6.
|
(3)
|
All wind
and water strakes over the full length of the ship, port and
starboard.
|
(2)
|
Measurements for the general assessment and recording of corrosion pattern
of those structural members subject to Close-up Survey in accordance with
Table 3.5.4 Minimum requirements for Close-up
Survey - General dry cargo ships
|
(4)
|
All wind and water strakes within cargo length area.
|
(4)
|
Remaining
exposed main deck plates not considered in item (3) and representative
exposed superstructure deck plating (i.e. poop, bridge and forecastle
deck).
|
(5)
|
Selected wind and water strakes outside the cargo length
area.
|
(5)
|
Lowest strake and strakes in way of ‘tween deck of all transverse
bulkheads in cargo spaces together with internals in way.
|
(3)
|
Suspect areas, as required by the Surveyor. See Note
3.
|
(6)
|
Suspect areas, as required by the Surveyor. See Note
3.
|
(6)
|
All keel
plates over the full length of the ship. Also additional bottom plates in
way of cofferdams, machinery spaces and aft end of tanks.
|
|
|
|
|
(7)
|
Plating
of sea chests. Also side shell plating in way of overboard discharges, as
considered necessary by the Surveyor.
|
|
|
|
|
(8)
|
Suspect
areas, as required by the Surveyor. See Note 3
|
Note
1. Thickness measurement locations are to
be selected to provide the best representative sampling of areas
likely to be most exposed to corrosion, considering cargo and ballast
history and arrangement, and condition of protective coatings.
|
Note
2. A transverse section is to include all
longitudinal members such as plating, longitudinals and girders at
deck, sides, bottom, inner bottom and hopper side plating,
longitudinal bulkheads and bottom plating in top wing tanks, where
fitted. For transversely framed vessels, a transverse section includes
adjacent frames and their end connections in way of transverse
sections.
|
Note 3. Suspect areas are
locations showing substantial corrosion and/or are considered by the
Surveyor to be prone to rapid wastage.
|
4. For ships having length L less
than 100 m:
- the number of transverse sections required at Special Survey
III may be reduced to one.
- the number of transverse sections required at Special Survey IV
and subsequent surveys may be reduced to two.
|
Note
5. For areas in spaces (Cargo Holds and
Water Ballast Tanks) where coatings are found to be in GOOD condition,
as defined in Pt 1, Ch 3, 1.5 Definitions 1.5.26, the extent
of thickness measurement may be specially considered, but not
dispensed with in its entirety.
|
Note
6. Deck plating outside line of cargo
hatch openings is deck plating between the ship sides and hatch
coamings in the transverse section concerned.
|
5.6.2 Thickness
measurements may be carried out in association with the fourth Annual
Survey.
5.6.3 In areas
where substantial corrosion, as defined in Pt 1, Ch 3, 1.5 Definitions, has been noted, then additional measurements are to be
carried out, as applicable, in accordance with Table 3.5.6 Thickness measurement - Additional
requirements in way of structure identified with substantial corrosion to determine the full
extent of the corrosion pattern. The survey will not be considered
complete until these additional thickness measurements have been carried
out.
Table 3.5.6 Thickness measurement - Additional
requirements in way of structure identified with substantial corrosion
Structural
member
|
Extent of
measurement
|
Pattern of
measurement
|
Plating
|
Suspect areas and
adjacent plates
|
5 point pattern over
1m2
|
Stiffeners
|
Suspect areas
|
3 measurements each in
line across web and flange
|
Table 3.5.7 Air pipe head internal examination
requirements (applicable for automatic air pipe heads installed on exposed decks of
all ships except passenger ships)
Special Survey I (Ships 5 years
old)
|
Special Survey II (Ships 10
years old)
|
Special Survey
III (Ships 15 years old) and subsequent
|
(1)
|
Two air pipe heads (one port and one starboard)
on exposed decks in the forward 0,25L. See Notes 1 to 5
|
(1)
|
All air pipe heads on exposed decks in
the forward 0,25L. See Notes 1 to 5
|
All air pipe heads on
exposed decks. See Notes 1 to 6
|
(2)
|
Two air pipe heads (one port and one starboard)
on the exposed decks, serving spaces aft of 0,25L. See Notes 1
to 5
|
(2)
|
At least 20% of air pipe heads on
exposed decks, serving spaces aft of 0,25L. See Notes 1 to 5
|
|
Note
1. Air pipe heads serving ballast tanks
are to be selected where available.
|
Note
2. The Surveyor is to select which air
pipe heads are to be examined.
|
Note
3. Where considered necessary by the
Surveyor as a result of the examinations, the extent of examinations
may be extended to include other air pipe heads on exposed decks.
|
Note
4. Where the inner parts of air pipe head
cannot be properly examined due to its design, it is to be removed in
order to allow an internal examination.
|
Note
5. Particular attention is to be given to
the condition of the zinc coating in heads constructed from galvanised
steel.
|
Note
6. Exemption may be considered for air
pipe heads where there is documented evidence of their replacement
within the previous five years.
|
5.6.4 Where
substantial corrosion is identified and not rectified, this will be
subject to examination and thickness measurement at Annual and Intermediate
Surveys.
5.6.5 Where
considered necessary by the Surveyor, thickness measurements are to
be carried out in way of critical areas. These include areas considered
prone to rapid wastage.
5.6.6 Where
required by LR, a check of the buckling capacity of the upper deck
is to be carried out for tankers having a length greater than 90 m.
5.6.7 Steel
evaluation of hatch covers on exposed decks and hatch coamings and
closing arrangements of cargo holds on ships with contract for construction
on or after 1 July 2012 is to be in accordance with IACS UR S21A.
Further information is provided in the LR document Thickness
Measurement and Close-Up Survey Guidance.
Steel renewal is required where the gauged thickness is less than
tnet + 0,5 mm. For definition of tnet, see
Pt 4, Ch 7, 12.1 General 12.1.2.
Where the gauged thickness is within the range tnet + 0,5
mm and tnet + 1,0 mm, a coating (applied in accordance with coating
manufacturer’s requirements) or annual gauging may be adopted as an alternative to steel
renewal.
|