Section
2 Structure
2.1 Plans and data submission
2.1.1 In addition to the structural plans and information as required by Ch 2,8
of LR's Guidance Note Mobile Offshore Units – Wind Turbine Installation
Vessels and also LR's Guidance Note Mobile Offshore Units –
Liftboats, the following additional plans and information are to be submitted as
applicable:
- General arrangement plans.
- Structural plans of the accommodation including deck houses and
modules.
- Design calculations for containerised modules (if
applicable).
- Structural arrangements in way of crane supports and boom rests
(if applicable).
- Structural arrangements in way of permanently attached, purpose
built cargo stacking and securing arrangements.
- Structural arrangements under the weather deck which support
heavy items of deck cargo such as nacelles, towers, blades, foundations and
temporary transportation frames.
- Structural arrangements and supports under any other major
mission or topsides equipment.
- Positional mooring equipment and supporting structures (if
applicable).
2.2 General
2.2.1 The hull strength is to take into account the applied weights and forces
due to the accommodation, deck cargo, cranes and, if applicable, mooring forces and
the local structure is to be suitably reinforced. Appendices A2, A3, A4 and A5 of
the Guidance Note referred to in Pt 3, Ch 16, 1.3 Guidance note include summary Tables indicating the relevant Parts and
Chapters of these Rules and the Rules for Ships, which are to be applied to the
individual unit types for hull strength requirements.
2.2.2 For the unit types identified in Pt 3, Ch 16, 1.2 General definitions, 1.2.3, 1.2.4 and 1.2.5, the hull scantlings
for each unit type are to be calculated in accordance with the relevant parts of the
Rules identified in Appendices A2, A3, A4 and A5 of the Guidance Note Mobile
Offshore Units – Wind Turbine Installation Vessels.
2.2.3 For the unit type identified in Pt 3, Ch 16, 1.2 General definitions, the hull scantlings for each unit type are to
be calculated in accordance with the relevant parts of the Rules identified in the
Guidance Note Mobile Offshore Units – Liftboats.
2.2.4 The design loadings for all purpose built cargo stacking arrangements,
support frames and trusses are to be defined by the designers/Builders and
calculations are to be submitted in accordance with an internationally recognised
Code or Standard as defined in Pt 12, Ch 1 Recognised Codes and Standards. The supporting structure and
attachments below the purpose built cargo stacking arrangements, support frames and
trusses are to be designed for all operating conditions and for the emergency
condition as defined in Pt 3, Ch 8, 1.4 Plant design characteristics. For a surface type self-elevating unit in the
afloat condition, the angle of inclination in the emergency static condition is to
be considered in accordance with the requirements for a self-elevating unit.
2.2.5 The supporting structure and attachments below any other mission
equipment items are to be designed for all operating conditions and for the
emergency condition as defined in Pt 3, Ch 8, 1.4 Plant design characteristics. For a surface type self-elevating unit in the afloat condition,
the angle of inclination in the emergency static condition is to be considered in
accordance with the requirements for a self-elevating unit.
2.2.6 When the unit is intended to operate in an area which could result in
the build-up of ice on the crane, leg and any other structure, the effects of ice
loading are to be included in the calculations. See
Pt 4, Ch 3, 4 Structural design loads.
2.2.7 For column-stabilised and self-elevating units, the decks and other
under-deck structure supporting the mission equipment and deck cargo are to be
suitable for the local loads at the mission equipment and deck cargo support points
and an agreed uniformly distributed load acting on the deck. See
Pt 4, Ch 6, 2 Design heads.
2.2.8 For surface type and surface type self-elevating units, the decks and
other under-deck structure supporting the mission equipment and deck cargo are to be
suitable for the local loads at the mission equipment and deck cargo support points
and an agreed uniformly distributed load acting on the deck. See
Pt 3, Ch 3, 5 Design loading of the Rules for Ships.
2.2.9 In general, all seatings, platform decks, girders and pillars supporting
mission equipment and deck cargo are to be arranged to align with the main hull
structure, which is to be suitably reinforced, where necessary, to carry the
appropriate loads.
2.2.11 Crane pedestals are classification items and are to comply with the
requirements of Chapter 11.
2.2.12 For liftboats, a fatigue life assessment of all relevant structural
elements in accordance with Pt 4, Ch 5, 5 Fatigue design is required. Structural elements to be
assessed include lattice legs and connections to mats and footings and leg support
structure. The fatigue loading spectrum may be based on the transit environmental
criteria.
2.2.13 The minimum fatigue life of a liftboat is to be specified by the Owners,
but is generally not to be less than 20 years, unless agreed otherwise with LR.
2.2.14 For liftboats, when considering the overturning moment, in no case is
the variable load to be taken greater than 10 per cent of the maximum variable load.
The percentage of variable load used when considering the overturning moment is to
be stated in the Operations Manual.
2.2.15 For liftboats, when calculating the overturning moment, the unit should
be considered supported through the centre line of the legs about which the unit is
considered rotating. However, for hard foundation bases, the maximum stressed edge
of the mat may be taken as an appropriate support position. In this instance, a
safety factor of at least 1,2 against overturning is considered acceptable.
2.2.16 For liftboats, the Owner is to specify the minimum design environmental
criteria and return periods for which the unit is to be approved. In general, a
return period of not less than 1 year should be used for operational conditions and
100 years for survival conditions.
2.2.17 For liftboats, restricted to seasonal operations in order to avoid
extremes of wind and wave, such seasonal limitations must be specified. The unit's
actual minimum design environmental criteria and return periods used in the design
of the liftboat are to be stated in the Operations Manual.
2.2.18 The thickness of marine growth to be taken into account during the design
of submerged members on lift boats is not to be less than 50 mm. The actual
thickness of marine growth used in the design of the liftboat is to be stated in the
Operations Manual and the design limit is not to be exceeded in service.
2.2.19 For liftboats, the minimum design deck loads are to be specified by the
Owner and are not to be less than the minimum design deck loads required by Pt 4, Ch
6,2.
2.2.20 For liftboats, the foundation fixity need not be considered for the
in-place strength analysis.
2.3 Deckhouses and modules
2.3.1 For column-stabilised and self-elevating units, the scantlings of
structural deckhouses are to comply with Pt 4, Ch 6, 9 Superstructures and deck-houses. Where deck-houses support equipment
loads, they are to be suitably reinforced.
2.4 Permissible stresses
2.4.1 In general, for column-stabilised and self-elevating units the
permissible stresses in the structure in operating, transit and survival conditions
are to comply with Pt 4, Ch 5, 2 Permissible stresses, but the minimum scantlings of the local structure are to comply
with Pt 4, Ch 6 Local Strength.
2.5 Watertight and weathertight
integrity
2.5.3 The integrity of the weather deck is to be maintained. Where mission
equipment penetrates the weather deck and is intended to constitute the structural
barrier to prevent the ingress of water to spaces below the deck, its structural
strength is to be equivalent to the Rule requirements for this purpose. Otherwise,
such items are to be enclosed in superstructures or deck-houses fully complying with
the Rules. Full details are to be submitted for approval.
2.5.4 Where items of mission equipment penetrate watertight boundaries, the
watertight integrity is to be maintained and full details are to be submitted for
approval.
2.6 Materials
|